DON'T WANT TO MISS A THING?

Certification Exam Passing Tips

Latest exam news and discount info

Curated and up-to-date by our experts

Yes, send me the newsletter

PMP Practice Test - Free PMP Exam Questions and Answers

Exam NameProject Management Professional
Exam CodePMP
Exam Fee MemberUSD $ 405.00
Exam Fee Non-memberUSD $ 555.00
Exam Duration230 Minutes
Number of Questions180
Passing ScoreAbove Target / Target / Below Target / Needs Improvement
FormatMultiple Choice Questions

Download this free PMP exam dump to get real PMP practice test questions. This PMP question dump serves as a practice exam to help you prepare for the Project Management Professional certification. Prepare for the PMP exam with this free set of PMP practice questions. 

Take other online exams

Question #1
A project manager is working with a Scrum team that is continually missing deadlines The steering committee is concerned about the project as it is not dear that it will deliver the expected value After some analysis, the project manager discovers there is a mismatch of competencies in one of the teams. What should the project manager do?
A. rovide appropriate raining to compensate for the mismatch
B. pdate the project schedule to reflect the delay
C. mphasize to the teams the importance of meeting the agreed deadlines
D. ccept the risk of the project missing deadlines due to the mismatch
View answer
Correct Answer: A
Question #2
An external project manager is managing the construction of new corporate offices for a large company The project management plan states that it is necessary to contract a highly trained external resource to revise and validate an important project component The client has rejected hiring the external resource because of the high cost, even though it is within the project budget. What should the project manager do to resolve this issue?
A. valuate the consequences and meet with the client to explain the possible scenarios
B. ry to accomplish the task internally by leveling resources from other projects
C. ire the resource in order to achieve the project objectives
D. sk the client for a meeting and explain that the task will not be performed
View answer
Correct Answer: A
Question #3
In a newly formed project team, one experienced team member is overwhelmed by the complexity of the tasks and is not happy with the project team. What should the project manager do?
A. ctively listen to the team member and identify ways to support their needs in completing the tasks
B. xplain that the tasks are unavoidable and ask the team member to find a solution to overcome the challenges
C. et up team-building activities with the project team members to reduce tension
D. sk the team member to enter this potential schedule delay in the risk register
View answer
Correct Answer: A
Question #4
Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release. What should the project manager do to obtain agreement from both companies and acceptance from marketing?
A. reate a special release 4 weeks after the current release to deliver the new feature in its entirety
B. lan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value
C. dd the new feature to the list for the next release and continue working on the current release
D. top the current release work for 4 weeks in order to work and deliver the new feature completely
View answer
Correct Answer: B
Question #5
A project manager decided to use a highly adaptive approach to manage a large-scale project In this project, there are many iterative tasks that utilize highly specialized experts. The project manager would like to create practical plans with high levels of buy-in from the team members. What should the project manager do next?
A. eview lessons learned from similar projects with the team
B. eview the budget with the team for the needed resources
C. xplain the higher-level objectives to be assigned to the team
D. ssign critical tasks to the most experienced team members
View answer
Correct Answer: C
Question #6
A project team is prioritizing the creation of project artifacts and enforcing it rigidly, while they face issues with delays in deliverables. How should the project manager respond?
A. dvise the team that solely focusing on artifacts will not produce successful project deliverables
B. ecognize the team's efforts for documenting artifacts and motivate them with an incentive mechanism
C. acilitate the implementation of an automated tool for the team to manage project artifacts
D. mplement stricter controls so that project artifact creation is given the utmost importance
View answer
Correct Answer: B
Question #7
An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end- of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price. What should the product owner do about this situation?
A. eprioritize the backlog based on value and cost of delay divided by duration
B. eprioritize the backlog based on story size and competence availability
C. witch to a predictive approach to prevent any further delays to completion
D. emove low-value items from the backlog to compensate for the higher cost
View answer
Correct Answer: A
Question #8
A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed. What should the project manager do immediately about this situation?
A. egister the schedule risk and present the new resources requirement to the change management board for schedule recovery
B. repare a monthly report by highlighting the completed deliverables and communicate the delay to management
C. sk the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay
D. sk the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team
View answer
Correct Answer: C
Question #9
A project manager notices that a new junior team member's suggestions are constantly rejected by senior team members. The senior team members find the suggestions valid and innovative, but unrealistic. Following several project assignments, the senior members request to have the junior team member removed. What should the project manager do next?
A. roup the new team members together for training purposes
B. ncourage further and deeper discussions among team members
C. ccept the demands and remove the junior team member
D. emove possible conflicts from future project assignments
View answer
Correct Answer: B
Question #10
A new team member has joined a project team. During the first sprint, the new team member approached the project manager and requested to implement a new way of testing. The team has been resistant to the proposed change. What should the project manager do?
A. sk the new team member to focus only on development and not do the testing
B. oach the new team member to conduct the testing the way it has always been done for this project
C. chedule a meeting with the new team member to learn about the new method of testing
D. equest that the new team member do the testing the way it has always been done for this project
View answer
Correct Answer: C
Question #11
An urgent meeting has been established with the project team to discuss the cause of some quality issuers that are preventing delivery to the client. The product owner commends a root cause analysis (RCA). What should the project lead do?
A. iscuss the product owner's recommendations with the team and implement the agreed-on solutions
B. iscuss the recommendations with the test manager and request better quality control
C. acilitate the meeting so anyone can share their ideas and is heard during the session
D. llow the team to self-organize so one of the resources can lead the team to achieve consensus
View answer
Correct Answer: A
Question #12
During a project's execution phase, two team members are having conflicts with other team members within the team on technical and interpersonal levels. Which two actions should the project manager take first to address this conflict? (Choose two)
A. rrange individual meetings with the team members who cannot work together effectively
B. lan to resolve the team members' conflicts after the sprint and focus on achieving the goal
C. sk human resources (HR) to intervene before it escalates and affects the team's performance
D. iscuss the conflict early among the affected team members using a direct, collaborative approach
E. ddress the conflict during team meetings for the entire team to participate and find solutions
View answer
Correct Answer: AD
Question #13
A project manager is performing the scrum master role for a project team of developers. At the daily standup, a couple of developers complain about the noise from a neighboring team, the performance of their laptops, and the difficulty in booking meeting rooms.What should the project manager do?
A. ote the impediments and escalate them to the product owner
B. ote the impediments and work on addressing them later
C. cknowledge the impediments and facilitate their resolutions
D. ssign actions to all stakeholders and oversee their implementation
View answer
Correct Answer: B
Question #14
A project has completed design activities ahead of schedule. Suddenly, the project manager is informed by a vendor that a deliverable may not meet the agreed delivery time frame due to a resource shortage. The internal team asked if they should continue to deliver as per the schedule. What should the project manager do?
A. iscuss with the project team alternative options to deliver as planned
B. iscuss with the team the need for longer hours to minimize the impact
C. nform the project team that they may proceed at a more relaxed pace
D. nform the project team that some of them will work for the vendor
View answer
Correct Answer: A
Question #15
An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project. was promoted to a more senior role. A new project lead has joined the project. Which artifact should the project lead use to ensure that the project benefits have been identified?
A. tatement of work (SOW)
B. olution architecture
C. roduct backlog
D. usiness case
View answer
Correct Answer: B

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: