The Scrum PSM I exam (Professional Scrum Master I) tests your understanding of Scrum principles, frameworks, and the role of a Scrum Master. This certification is designed to evaluate your ability to guide Scrum teams, foster continuous improvement, and promote agile practices. SPOTO provides the latest exam questions and exam questions and answers to help you prepare. You can download free PDF exam questions, use practice tests, and review exam sample questions to familiarize yourself with the exam format. SPOTO also offers practice questions and exam dumps to deepen your understanding. Using these study materials as part of your exam prep will enhance your readiness and increase your chances of passing the PSM I exam. Prepare effectively with SPOTO’s comprehensive resources.
Take other online exams

Question #1
True or False: The Product Owner makes sure the Developers select enough from the ProductBacklog tor a Sprint to satisfy the stakeholders.
A. rue
B. alse
View answer
Correct Answer: B

View The Updated PSM I Exam Questions

SPOTO Provides 100% Real PSM I Exam Questions for You to Pass Your PSM I Exam!

Question #2
How much work Is required of the Developers to complete a Product Backlog Item selected during the Sprint Planning?(choose the best answer)
A. ll development work and at least some testing
B. s much as is required to meet the Scrum Team's Definition of Done
C. proportional amount of time on analysis, design development and testing
D. s much as they can fit into the Sprint, with remaining work deferred to the next Sprint
View answer
Correct Answer: B
Question #3
What is the function or purpose of management in Scrum?(choose the best answer)
A. o identify and remove people that are not working hard enough
B. o present the Scrum Teams with insights and resources that help them improve
C. o monitor the productivity of the Developers
D. o continually monitor staffing levels of the Scrum Team
View answer
Correct Answer: B
Question #4
You are a new Scrum Master and have been asked to take a lead in the development of a new product. Seven teams new to Scrum will build this product. You have the beginnings of a Product Backlog from gathering requirements.How would you minimize dependencies between the Scrum Teams?
A. You create an independent Product Backlog per Scrum Team
B. You identify the dependencies and re-order the Product Backlog for them
C. You work with the Developers on how to best analyze and break apart the work
D. You divide Product Backlog items among the six Product Owners
View answer
Correct Answer: C
Question #5
When Goes a Developer become accountable for the value 01 a Product BacKlog item selected for the Sprint'(choose the best answer)
A. ever The entire Scrum Team is accountable for creating value every Sprint
B. t the Sprint Planning Evented
C. henever a team member can accommodate more worn
D. uring the Daily scrum
View answer
Correct Answer: B
Question #6
The CEO asks the Developers to add a "very important" item to a Sprint that is in progress. What should the Developers do?(choose the best two answer)
A. Add the item to the current Sprint without any adjustments
B. Inform the other members of the Scrum Team so the team can decide what to do
C. Add the item to the current Sprint and drop an item of equal size
D. Add the item to the next Sprint
View answer
Correct Answer: B
Question #7
user documentation is part ot your Definition ot Done. However, there are not enough technicalwriters for all teams. Your Scrum Team does not have a technical writer. What should theScrum Team do?(choose the best answer)
A. he Developers on the Scrum Team should write the user documentatiom
B. ait until you have a technical writer on your Scrum Team to take care of this
C. orm a separate team of technical writers that will work on an on-demand basis tor\rthe various Product Owners
D. et the user documentation remain undone and accumulate until after the last\rdevelopment Sprint
View answer
Correct Answer: A
Question #8
What is the function or purpose of management in Scrum?(choose the best answer)
A. o identify and remove people that are not working hard enough
B. o monitor the productivity of the Developers
C. o present the Scrum Teams with insights and resources that help them improve
D. o continually monitor staffing levels of the Scrum Team
View answer
Correct Answer: C
Question #9
What are the two primary ways a Scrum Master keeps a Development Team working at its highest level of productivity?
A. By keeping high value features high in the Product Backlog
B. By starting and ending the meetings at the proper time
C. By facilitating Development Team decisions
D. By removing impediments that hinder the Development Team
View answer
Correct Answer: C, D
Question #10
How much work must a Development Team do to a Product Backlog item it selects for a Sprint?
A. As much as it can fit into the Sprint
B. All development work and at least some testing
C. Analysis, design, programming, testing and documentation
D. As much as it has told the Product Owner will be done for every Product Backlog item it selects in conformance with the definition of "Done"
View answer
Correct Answer: D
Question #11
What are two ways a Scrum Master serves to enable effective Scrum Teams?(choose the best answers)
A. By keeping high value features high in the Product Backlog
B. By removing impediments that hinder the Scrum Team
C. By starting and ending the meetings at the proper time
D. By facilitating Developer decision-making
View answer
Correct Answer: B, D
Question #12
Which three behaviors demonstrate that a team is NOT self-organizing and are NOT following the Scrum Guide?
A. Stakeholders attend the Daily Scrum to check progress and work with the Scrum Master to optimize the functional scope for the Sprint
B. The Development Team invites external people to the Sprint Planning to ask them how to turn a Product Backlog item into an Increment via a complete and detailed Sprint Backlog
C. Development Team members collaboratively selecting their own work during the Sprint
D. The Development Team has all the skills needed to create a releasable Increment
View answer
Correct Answer: A, B, E
Question #13
Who can cancel a Sprint?(choose the best answer)
A. he Scrum Master
B. he Scrum Team
C. he Stakeholders
D. he Product Owner
View answer
Correct Answer: D
Question #14
You have been hired as a Scrum Master of seven new Scrum Teams. These teams will build one product.Select 2 conditions you should ensure.
A. There should be six Product Owners, reporting to a chief Product Owner
B. Each Scrum Team should have a separate Product Backlog
C. There should be six Product Owners, one for each Scrum Team
D. The product has one Product Backlog
View answer
Correct Answer: D, E
Question #15
True or False: The purpose of a Sprint Is lo produce a valuable useful Inclement.
A. rue
B. alse
View answer
Correct Answer: A
Question #16
Burn-down charts can be used to visualize progress towards reaching a goal. What do the burn-down charts track?
A. Individual Development Team members productivity over time
B. The amount of work remaining across time
C. Cost across time
D. The capacity of the Development Team
View answer
Correct Answer: B
Question #17
An organization has decided to adopt Scrum, but management wants to change the terminology to fit with terminology already used. What will likely happen if this is done?
A. Without a new vocabulary as a reminder of the change, very little change may actually happen
B. The organization may not understand what has changed with Scrum and the benefits of Scrum may be lost
C. Management may feel less anxious
D. All of the above
View answer
Correct Answer: D
Question #18
Which are characteristics of the Daily Scrum?(choose the best two answers)
A. ts location and time remain constant
B. ts purpose is to inspect progress toward the Sprint Goal and adapt the Sprint\rBacklog
C. t is tree form and designed to promote conversatiom
D. t is facilitated by the team lead
E. t is held first thing in the morning
F. t consists of the Scrum Master asking the team tor status
View answer
Correct Answer: A, B
Question #19
When must the Product Owner participate in the Dairy Scrum? (choose the best answer)
A. hen the Product Owner is actively working on items on the Sprint Backlog; however, they participate as a Developer
B. hen the Product Owner needs to represent the stakeholders point of view to the Developers
C. hen there are impediments to discuss
D. hen the Scrum Master asks the Product Owner to attend
View answer
Correct Answer: A
Question #20
True or False Developers do not meet with stakeholders: only the Product Owner meets with stakeholders
A. rue
B. alse
View answer
Correct Answer: B
Question #21
During a Sprint, a Developer determines that the Scrum Team will not be able to complete the items in their forecast.Who should be present to review and adjust the Product Backlog items selected?(choose the best two answer)
A. The Developers
B. The Scrum Master, the project manager, and the Developers
C. The Product Owner and all stakeholders
D. The Product Owner and the Developers
View answer
Correct Answer: D
Question #22
Who is responsible for collaboration with stakeholders?(choose the best answer)
A. he Business Analyst
B. he Scrum Team
C. he Team Manager
D. he Project Manager
E. he Developers
View answer
Correct Answer: B

View The Updated Scrum Exam Questions

SPOTO Provides 100% Real Scrum Exam Questions for You to Pass Your Scrum Exam!

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: