The Prince2 Foundation certification is a globally recognized credential that demonstrates your understanding of the Prince2 project management framework. To excel in the 2025 exam, comprehensive preparation is key. SPOTO offers a variety of exam resources, including free practice tests and expertly curated study materials, to ensure you’re fully equipped for success. These tools are designed to reflect the latest exam syllabus, covering critical themes, principles, and processes. SPOTO’s free practice tests provide real-world scenarios and detailed explanations to help you build confidence and refine your problem-solving skills. Whether you're new to project management or aiming to enhance your expertise, SPOTO’s Prince2 Foundation resources offer the guidance you need. Start your preparation journey today with SPOTO and move closer to achieving your Prince2 Foundation certification!
Take other online exams

Question #1
According to PRINCE2, the quality review technique compliments the use of which of the following?
A. Product Descriptions
B. Quality Assurance
C. Issue and change control procedure
D. Customer's quality expectations
View answer
Correct Answer: A

View The Updated PRINCE2 Foundation Exam Questions

SPOTO Provides 100% Real PRINCE2 Foundation Exam Questions for You to Pass Your PRINCE2 Foundation Exam!

Question #2
Identify the missing words in the following sentence... A purpose of the Quality theme is to [ ? ]
A. Provide a systematic approach which ensures that issues possibly affecting the project's quality performance target are managed appropriately
B. Ensure any threats to the quality targets are identified, assessed and controlled
C. Provide all personnel involved in the project with information regarding whether the targets of time, cost and quality are achievable
D. Ensure the project's products meet business expectations
View answer
Correct Answer: D
Question #3
Which product is used to record information regarding any issues that are being managed informally?
A. Configuration Item Record
B. Issue Register
C. Daily Log
D. Risk Register
View answer
Correct Answer: C
Question #4
Identify the missing words in the following sentence. A problem/concern, a request for change and [ ? ] are the three types of issue.
A. a constraint
B. a deviation from tolerance
C. an off-specification
D. a threat
View answer
Correct Answer: C
Question #5
Which is NOT included in the PRINCE2 definition of a project?
A. A project is a temporary organization
B. A project'spurpose is to deliver one or more business products
C. A project is part of business as usual'
D. A project is based on an agreed Business Case
View answer
Correct Answer: C
Question #6
Which of the following risk responses can be used to seize an opportunity to ensure a risk will occur?
A. Accept
B. Exploit
C. Enhance
D. Transfer
View answer
Correct Answer: B
Question #7
Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
View answer
Correct Answer: B
Question #8
Which PRINCE2 role would design and appointment the project management team?
A. Project Manager
B. Executive
C. Senior User
D. Project Assurance
View answer
Correct Answer: B
Question #9
Which of the following statements about customer's quality expectations and acceptance criteria are true? 1. Customer's quality expectations form a specific and precise list of measurable criteria that a project product should meet in order to be acceptable to key stakeholders. 2. Acceptance criteria are often expressed in broad terms as a means to gain common understanding of general quality requirements.
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
View answer
Correct Answer: D
Question #10
Which role is the single focus for day-to-day management of the project?
A. Project Manager
B. Executive
C. Project Support
D. Team Manager
View answer
Correct Answer: A
Question #11
Which aspect of project performance must be managed to ensure the project's products are fit for purpose?
A. Benefits
B. Quality
C. Risk
D. Scope
View answer
Correct Answer: B
Question #12
Which is a PRINCE2 time-driven control?
A. End Stage Report
B. Project Brief
C. Project Initiation Documentation
D. Checkpoint Report
View answer
Correct Answer: D
Question #13
Which process is largely about preventing poorly conceived projects from ever being initiated?
A. Starting Up a Project
B. Initiating a Project
C. Closing a Project
D. Directing a Project
View answer
Correct Answer: A
Question #14
Who should act as the communication channel between a project and corporate or programme management?
A. Project Board
B. Project Assurance
C. Project Manager
D. Project Support
View answer
Correct Answer: A
Question #15
Are the following statements regarding the Starting Up a Project process true or false? 1. How the project will achieve the required quality will be established 2. How the corporate (or programme's) project management method will be tailored to suit the project will be defined
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Both 1 and 2 are false
View answer
Correct Answer: D
Question #16
Which product is used to inform the Project Board of a forecast deviation of stage-level tolerance?
A. Exception Plan
B. Exception Report
C. Off-specification
D. Highlight Report
View answer
Correct Answer: B
Question #17
Which should be used to document any uncompleted work that needs to be done, and any risks which need to be managed after the project has closed?
A. Follow-on action recommendations
B. Exception Report
C. Issue Register
D. Risk Register
View answer
Correct Answer: A
Question #18
Which is a valid statement about the Project Support role?
A. Can be performed by the Project Manager
B. Is an optional role for a PRINCE2 project
C. Produces Checkpoint Reports for the Project Manager
D. Can be combined with the Project Assurance role
View answer
Correct Answer: A
Question #19
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
View answer
Correct Answer: B
Question #20
Which is an objective of the Managing a Stage Boundary process?
A. Understand what has gone well and what can help the next stage
B. Review and approve the next Stage Plan
C. Assure the Project Board that all project products have been completed and approved
D. Prepare an Exception Report to advise the Project Board of aforecast deviation from tolerance
View answer
Correct Answer: A
Question #21
Please refer to section 1.3 and 'Programme' in the Glossary of the PRINCE2 Manual. (Note that a collection of related projects being directed to deliver outcomes and benefits related to the organization's strategic objectives would be a programme NOT a project)
A. A temporary team that is created to direct and oversee a collection of related projects in order to deliver outcomes and benefits related to the organization's strategic objectives
B. A temporary organization that is created for the purpose of delivering one or more business products according to an agreed Business Case
C. A permanent organization that is created for the purpose of realizing one or more business benefits
D. A permanent team that is created to deliver a series of business change initiatives
View answer
Correct Answer: B
Question #22
Which step in the issue and change control procedure would be used to evaluate the alternative options to respond to an issue?
A. Propose
B. Examine
C. Capture
D. Decide
View answer
Correct Answer: C
Question #23
What is the first task of product-based planning?
A. Produce the Initiation Stage Plan
B. Write the Project Product Description
C. Identify dependencies
D. Create the product breakdown structure
View answer
Correct Answer: B
Question #24
Which is a true statement about acceptance criteria?
A. Acceptance criteria are used to produce the customer's quality expectations
B. Acceptance criteria are less specific and precise than customer's quality expectations
C. Once agreed, acceptance criteria CANNOT be changed
D. Acceptance criteria should be agreed between the customer and the supplier
View answer
Correct Answer: D
Question #25
Which of the following management levels sits outside of the project management team?
A. Directing
B. Managing
C. Corporate or programme management
D. Delivering
View answer
Correct Answer: C
Question #26
Which statement is FALSE?
A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B. A project's output is any of the project's specialist products
C. A project benefit is only realized after the project has closed
D. A project outcome is the resultof the change derived from using the project's outputs
View answer
Correct Answer: C
Question #27
Which role is accountable to corporate or programme management for the ultimate success of the project?
A. Project Board
B. Project Manager
C. Senior User
D. Change Authority
View answer
Correct Answer: A
Question #28
Which is a benefit of using PRINCE2?
A. Provides a defined structure of accountability, delegation, authority and communication
B. Includes techniquesfor critical path analysis and earned value analysis
C. Enables a Project Manager to be accountable for the success of a project
D. Prevents any changes once the scope of a project has been agreed
View answer
Correct Answer: A
Question #29
Which is a type of issue?
A. A lesson
B. A request for change
C. An Exception Report
D. A risk with an estimated high impact
View answer
Correct Answer: B
Question #30
Which is assumed to be a supplier's responsibility in the PRINCE2 customer/supplier environment?
A. Specify the desired result
B. Provide the resources and skills to deliver the desired result
C. Pay for the project
D. Specify the benefits of the project
View answer
Correct Answer: B
Question #31
Where would a Team Manager find information regarding the specific quality required for a product?
A. Product Description
B. Quality Register
C. Quality Management Strategy
D. Checkpoint Report
View answer
Correct Answer: A
Question #32
What should influence the Project Board's decision whether to delegate its Project Assurance responsibilities?
A. The preference of the Project Manager
B. Having insufficient authority to perform the role
C. Having insufficient time to perform the role
D. The need to involve key stakeholders on the project management team
View answer
Correct Answer: C
Question #33
Which role would represent the interests of the people who will be operating the project's products?
A. Senior Supplier
B. Executive
C. Change Authority
D. Senior User
View answer
Correct Answer: B
Question #34
Who carries out audits that are independent of the project?
A. Quality assurance
B. Project Assurance
C. Project Support
D. Project Manager
View answer
Correct Answer: A
Question #35
Which project management team role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?
A. Project Manager
B. Executive
C. Project Assurance
D. Quality Assurance
View answer
Correct Answer: C
Question #36
Identify the missing word(s) in the following sentence. During a quality review meeting [ ? ] any identified defects.
A. a solution should be designed for
B. an issue should be created for
C. the agreed actions should be recorded for
D. the chair will approve the solution to
View answer
Correct Answer: C
Question #37
Which process would review the performance of the project against its baselines?
A. Initiating a Project
B. Closing a Project
C. Managing Product Delivery
D. Starting Up a Project
View answer
Correct Answer: B
Question #38
Which is an objective of the quality review technique?
A. Determine whether a product has been created
B. Agree the quality method that will be applied to a product
C. Formulate ideas on how the product will be developed
D. Provide consultation with a range of interested parties on a product's fitness for purpose
View answer
Correct Answer: D
Question #39
Which is a purpose of a Project Brief?
A. Enable the assembly of the project mandate
B. Describe the reporting requirements of the various layers of management involved with the project
C. Describe how changes to products will be controlled
D. Provide a solid basis for the initiation of the project
View answer
Correct Answer: A
Question #40
Which is NOT obtained from a product's Product Description?
A. The product's quality criteria
B. Who will approve the product
C. The qualitymethod to be used
D. The development method to be used
View answer
Correct Answer: D
Question #41
Which process covers the work done by external suppliers who may NOT be using PRINCE2?
A. Closing a Project
B. Managing a Stage Boundary
C. Managing Product Delivery
D. Directing a Project
View answer
Correct Answer: C
Question #42
Which process starts on completion of the Starting up a Project process?
A. Controlling a Stage
B. Directing a Project
C. Initiating a Project
D. Managing a Stage Boundary
View answer
Correct Answer: B
Question #43
Which is within the context of the Managing Product Delivery process?
A. Receiving and signing off completed Work Packages
B. Reviewing the work situation and triggering new Work Packages
C. The continuing correct focus of the project should be confirmed at the end of each stage
D. Demonstrate that each product meets its quality criteria through carrying out the specified quality methods
View answer
Correct Answer: C
Question #44
Which of the following is a specific quality review team role?
A. User
B. Approver
C. Reviewer
D. Project Support
View answer
Correct Answer: C
Question #45
Which does NOT reflect the PRINCE2 principle of continued business justification?
A. There must be a justifiable reason for starting a project
B. The business justification drives decision making
C. If a project is no longer forecast to deliver a financial benefit, it should be stopped
D. If a project can no longer be justified, it should be stopped
View answer
Correct Answer: C
Question #46
In what product should the quality criteria for a specialist product be recorded?
A. Quality Management Strategy
B. Quality Register
C. Product Description
D. Project Product Description
View answer
Correct Answer: C
Question #47
Which of the following statements about stakeholders are true? 1. Someone who thinks they will be affected by a project is a stakeholder on that project 2. Stakeholders may be internal or external to the corporate organization
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Neither 1 or 2 are true
View answer
Correct Answer: C
Question #48
What purpose does the Benefits Review Plan fulfill after the project has closed? 1. Defines how a measurement of the achievement of the project's benefits can be made 2. Defines what benefits assessments need to be undertaken 3. Contains details of what period the costs and benefits will be measured 4. Identifies the activities required to measure the expected project's benefits
A. 1,2,3
B. 1,2,4
C. 1,3,4
D. 2,3,4
View answer
Correct Answer: B
Question #49
When considering risks, which describes an opportunity in a project?
A. An uncertain event that could have a negative impact on objectives
B. An uncertain event that could have a favourable impact on objectives
C. An event that has occurred resulting in a negative impact on objectives
D. An event that has occurred resulting in a favourable impact on objectives
View answer
Correct Answer: B
Question #50
Which is a purpose of the Directing a Project process?
A. Provide the information required to confirm if it is worthwhile to initiate a project
B. Enable overall control of a project to be exercised by the Project Board
C. Establish the level of control required by the Project Board after initiation
D. Provide sufficient information so that the currentstage can be reviewed and the next Stage Plan approved
View answer
Correct Answer: B
Question #51
Identify the missing word(s) in the following sentence. Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a project.
A. technical stage
B. benefit
C. management stage
D. Team Plan
View answer
Correct Answer: C
Question #52
What characteristic relates to a project having a defined start and defined end?
A. Uniqueness
B. Uncertainty
C. Temporary in nature
D. Introduces change
View answer
Correct Answer: C
Question #53
Identify the missing product in the following sentence. When assessing an issue during the Controlling a Stage process, the [ ? ] provides essential information to evaluate the viability of the project.
A. Project Brief
B. Benefits Review Plan
C. Project Initiation Documentation
D. Configuration Management Strategy
View answer
Correct Answer: C
Question #54
What theme establishes the mechanisms to judge whether a project is worthwhile investing in?
A. Plans
B. BusinessCase
C. Risk
D. Quality
View answer
Correct Answer: B
Question #55
Which is NOT undertaken during the Initiating a Project process?
A. Review why the project is needed
B. Identify if the project is sufficiently aligned with corporate objectives
C. Show how the outcome is to be achieved
D. Appoint an Executive and Project Manager
View answer
Correct Answer: D
Question #56
What is the goal of the 'Identify context' step within the recommended risk management procedure?
A. Identify responses to risks identified in the Business Case
B. Understand the specific objectives that are at risk
C. Gather information about risks for inclusion in Highlight Reports to the Project Board
D. Identify the threats and opportunities that may affect the project's objectives
View answer
Correct Answer: B
Question #57
How does the Progress theme assist the Project Board to assess project viability at regular intervals?
A. Sends regular Checkpoint Reports to the Project Board
B. Only one management stage is authorized at a time
C. Creates Exception Reports when tolerances are forecast to be exceeded
D. Reports to the Project Board during project closure
View answer
Correct Answer: B
Question #58
Which of the following would be done during the initiation stage?
A. Appoint the Executive
B. Establish who needs information, when and in what format
C. Establish the quality expectations of the customer
D. Define how the project will deliver the chosen business solution
View answer
Correct Answer: B
Question #59
Which may be funded from a risk budget?
A. Capturing identified threats and opportunities in the Risk Register
B. Specific management responses to a project's threats and opportunities
C. Producing risk summaries for inclusion in Highlight Reports
D. Any remaining open risks after the project has been closed
View answer
Correct Answer: B
Question #60
Which is an objective of the Starting up a Project process?
A. Identify who will be responsible for creating the Project Plan
B. Agree how the project will be monitored and controlled after initiation
C. Authorize the Project Manager to proceed with the initiation stage
D. Agree how issues and changes will be identified, assessed and controlled
View answer
Correct Answer: A
Question #61
Which is one of the six aspects of project performance that needs to be managed?
A. Progress
B. Change
C. Risk
D. Security
View answer
Correct Answer: C
Question #62
Which takes place within the Managing a Stage Boundary process?
A. Periodic review of progress against the Stage Plan
B. Obtain approvals for all completed products
C. Escalation of Issue Reports created during the current stage
D. Review of the business justification for the project
View answer
Correct Answer: D
Question #63
Which role does NOT set tolerances?
A. Corporate or programme management
B. Project Board
C. Change Authority
D. Project Manager
View answer
Correct Answer: C
Question #64
Identify the missing word in the following sentence. The [?] theme defines that the Project Board is responsible for the overall direction and management of the project,
A. Progress
B. Plans
C. Organization
D. Business Case
View answer
Correct Answer: C
Question #65
Which is NOT a PRINCE2 principle?
A. Learn from experience
B. Customer/supplier environment
C. Defined roles and responsibilities
D. Continued business justification
View answer
Correct Answer: B
Question #66
Identify the missing words in the following sentence. When planning the next stage, the Project Manager needs to review and, if necessary, update the [ ? ] with regard to external resources or suppliers.
A. Configuration Item Records
B. Business Case
C. Project Brief
D. project management team and/or role descriptions
View answer
Correct Answer: D
Question #67
Which PRINCE2 role has a specific responsibility for ensuring that the quality activities relating to products at all stages has appropriate user representation?
A. Project Manager
B. Executive
C. Project Assurance
D. Quality Assurance
View answer
Correct Answer: C
Question #68
Which is a purpose of the Plans theme?
A. Identify, assess and control any potential changes to the baseline
B. Establish the project's structure of accountability
C. Assess and control uncertainty
D. Understand whether the targets are achievable
View answer
Correct Answer: A
Question #69
When should the Project Board refer to corporate or programme management for a decision?
A. The stage requires resources
B. It is forecast that project level tolerance will be exceeded
C. The Senior Supplier or Senior User needs to be changed
D. Any request for change needs to be approved
View answer
Correct Answer: B
Question #70
Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.
A. controls
B. products
C. project management team
D. stages
View answer
Correct Answer: B
Question #71
What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
View answer
Correct Answer: B
Question #72
What takes place within the Managing a Stage Boundary process?
A. Periodic review of progress against the Stage Plan
B. Approval and acceptance of all products created during the current stage
C. Escalation of Issue Reports and risks captured during the current stage
D. Review and if necessary update the Project Initiation Documentation
View answer
Correct Answer: D
Question #73
Which is an objective of the Closing a Project process?
A. Provision has been made to address any open issues or risks with follow-on action recommendations
B. Request authorization to start the next stage
C. Prepare an Exception Plan as directed by the Project Board
D. Ensure that the planned products are delivered to expectations and within tolerance
View answer
Correct Answer: A
Question #74
Identify the missing words from the following sentence... For a project to start and carry on, a PRINCE2 principle states that a project must have [?]?
A. Lesson applied throughout
B. Continued business justification
C. At least two stages
D. Focus on products that will meet business expectations
View answer
Correct Answer: B
Question #75
Which should be funded by a change budget?
A. Increase in agreed scope
B. Initiation stage
C. Change Authority
D. Handover activities
View answer
Correct Answer: A
Question #76
Which of the following steps looks at the aggregated net effect of a project's threats and opportunities?
A. Plan
B. Assess
C. Examine
D. Assess
View answer
Correct Answer: D
Question #77
Which product would be updated to show that a decision has been made to accept an off- specification?
A. Quality Register
B. Daily Log
C. Issue Report
D. Risk Register
View answer
Correct Answer: C
Question #78
Which of the following are a purpose of the Benefits Review Plan? 1. Define how a measurement of the achievement of the project's benefits can be made 2. Define what benefits assessments need to be undertaken 3. Define the project, in order to form the basis for its management and an assessment of its overall success 4. Define the activities required to measure the expected project's benefits
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
View answer
Correct Answer: B
Question #79
Select the missing words from the following sentence... The Senior User is responsible for ensuring that the project produces products which will deliver the desired [ ? ].
A. Outcomes
B. Benefits
C. Outputs
D. Changes
View answer
Correct Answer: A
Question #80
In which process would it be demonstrated that each product meets its quality criteria?
A. Closing a Project
B. Managing a Stage Boundary
C. Directing a Project
D. Managing Product Delivery
View answer
Correct Answer: D
Question #81
Which should be provided by corporate or programme management before the Starting up a Project process commences?
A. A Project Brief
B. Sufficient information to identify the prospective Executive
C. The Project Initiation Documentation
D. Authority to initiate a project
View answer
Correct Answer: B
Question #82
Which of the following take place before the initiation of a project? 1. Appoint the Executive 2. Capture requirements 3. Develop the Project Brief 4. Develop the detailed Business Case
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
View answer
Correct Answer: A
Question #83
In which product would you find a product's quality tolerance defined?
A. Product Description
B. Quality Management Strategy
C. Quality Register
D. Configuration Item Record
View answer
Correct Answer: A
Question #84
Which is an objective of the Managing Product Delivery process?
A. Sign-off completed Work Packages
B. Ensure the Business Case is kept under review
C. Report progress to the Project Board
D. Ensure that work on products is authorized and agreed with the team
View answer
Correct Answer: D
Question #85
Are the following statements regarding The Managing Product Delivery process true or false? 1. Towards the end of the last stage, this process will invoke the Closing a Project process 2. The Team Manager obtains approval for completed products from the authorities identified in the Product Description
A. Only 1 is true
B. Only 2 is true
C. Both 1 and 2 are true
D. Both 1 and 2 are false
View answer
Correct Answer: B
Question #86
Which of the following is funded from a change budget?
A. Fallback plan
B. Request for change
C. Action to reduce a threat
D. Change Authority
View answer
Correct Answer: B
Question #87
Which best describes a purpose of the Benefits Review Plan?
A. Used to define how and when a measurement of the project's benefits can be made
B. Documents the justification for undertaking the project
C. Provides all the right information for decisions to be made regarding continued business justification
D. Describes just the benefits which are only to be delivered after the project
View answer
Correct Answer: A
Question #88
When is the Risk Register created?
A. During the first End Stage Assessment
B. During the initiation stage
C. When preparing a Project Brief during pre-project work
D. When authorizing the project
View answer
Correct Answer: B
Question #89
How many management stages should a PRINCE2 project consist of?
A. Start up stage, initiation stage and at least one other management stage to cover the remainder of the project
B. Start up stage, at least one other management stage to cover the remainder of the project and a closing stage
C. Initiation stage and at least one other management stage to cover the remainder of the project
D. Start up stage, initiation stage and a closing stage
View answer
Correct Answer: C
Question #90
Which is a purpose of a Risk Register?
A. Capture risks that may occur during the project
B. Record how risk management activities will be undertaken on the project
C. Record the risk tolerance for the project
D. Capture issues which are impacting on the delivery of the project objectives
View answer
Correct Answer: A
Question #91
When are Work Package tolerances agreed?
A. When accepting a Work Package
B. When approving a Stage Plan
C. When creating the Project Plan
D. When creating the Project Brief
View answer
Correct Answer: A
Question #92
Which may be funded from a risk budget?
A. Corrections due to off-specifications
B. Impact analysis of requests for change
C. Implementation of a fallback plan
D. Preparation of the Risk Management Strategy
View answer
Correct Answer: C
Question #93
Which of the following is NOT part of quality planning?
A. Define quality responsibilities
B. Gain acceptance of the project product
C. Agree acceptance criteria
D. Set quality tolerances
View answer
Correct Answer: B
Question #94
Which product would hold details of each product's current version and any important relationships between them?
A. Product Description
B. Highlight Report
C. Configuration Item Record
D. Work Package
View answer
Correct Answer: C
Question #95
Identify the missing words in the following sentence... A Benefits Review Plan is used to show [?]
A. Opportunities which, if occurred, would have a favourable impact on the projects costs and benefits
B. Resources required to measure the expected benefits
C. An investment appraisal for the project
D. The project's outputs and outcomes
View answer
Correct Answer: B

View The Updated Prince2 Exam Questions

SPOTO Provides 100% Real Prince2 Exam Questions for You to Pass Your Prince2 Exam!

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: