Since the last iteration, the team has grown from six members to 14 members. As a result, in the current iteration, the team room is crowded and uncomfortable during the team's daily standup. It takes the team longer than the ideal amount of time to complete their standup, which creates problems for the team's current schedule. Based on this information, the project manager should:
A. ove the standup to a conference call format so space is not a problem
B. ncrease the standup duration and update the team's calendars
C. ssign each team member a maximum speaking time for future standups
D. plit the team into sub teams and have them schedule separate standups