Scenario: Techniques, processes and procedures 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements 2. Work is to start at the beginning of week 2 (Stage 4). 3. The project will take two years to complete, at an estimated cost of £2.5m. Tolerances 4. None. Constraints 5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment. 6. Installation work must take place during MFH normal working hours. 7. +£10,000 / -£25,000. Re
A. Delete entry 12 because this should be the Team Plan not the Stage Plan
B. A suitable entry for Extracts or references would be 'Product Descriptions are available from Project Support'
D. Project Manager
E. Delete entry 13 because this is NOT a Project Assurance responsibility
F. Add 'The Project Manager is to be advised of completion of the Work Package by email'