SPOTO's latest exam dumps on the homepage, with a 100% pass rate! SPOTO delivers authentic Cisco CCNA, CCNP study materials, CCIE Lab solutions, PMP, CISA, CISM, AWS, and Palo Alto exam dumps. Our comprehensive study materials are meticulously aligned with the latest exam objectives. With a proven track record, we have enabled thousands of candidates worldwide to pass their IT certifications on their first attempt. Over the past 20+ years, SPOTO has successfully placed numerous IT professionals in Fortune 500 companies.
Take other online exams

Question #1
What is the main reason why some teams never reach Stage 4 (PerforminG. in the stages of high performing teams?
A. Because no one guides them
B. Because leadership is spontaneous
C. Because there are conflicts
D. Because the team is not structured correctly
View answer
Correct Answer: A
Question #2
Program Increment (PI) Objectives should be written in the SMART format. What does the "R" in SMART stand for?
A. Realistic
B. Rationalized
C. Random
D. Required
View answer
Correct Answer: A
Question #3
Who can the Release Train Engineer work with to help eliminate policies and procedures that demotivate employees?
A. Product Management
B. Lean-Agile Leaders
C. Business Owners
D. Portfolio Managers
View answer
Correct Answer: B
Question #4
Why would a Release Train Engineer use an Iteration and Program Increment Calendar?
A. To know the cycle time between important team and train events
B. To create a BVIR of the important team and ART milestones
C. To ensure that key ceremonies don't conflict with non-SAFe ceremonies
D. To visualize the Agile Release Train's cadence and synchronization
View answer
Correct Answer: D
Question #5
In systems thinking, value of a system passes through its what?
A. Integrations
B. Interactions
C. Interconnections
D. Interdependencies
View answer
Correct Answer: C
Question #6
What should the Release Train Engineer do during the final plan review on Day two of Program Increment (PI) Planning?
A. Verify that each team's uncommitted objectives have lower business value than the committed PI Objectives in order to reflect proper prioritization
B. Facilitate the ROAMing of each team's risks
C. Encourage discussion of each team's product Vision as part of the final plan review
D. Facilitate all teams when they are presenting their final plans to the entire Agile Release Train
View answer
Correct Answer: D
Question #7
Which two behaviors are an important part of the Release Train Engineer role? (Choose two.)
A. Coach leaders to increase alignment
B. Provide answers about Features
C. Manage dependencies for teams
D. Encourage teams to self-organize
E. Drive teams to specific outcomes
View answer
Correct Answer: AD
Question #8
The goal of Lean is to deliver the maximum customer value in the shortest sustainable lead time while providing what else?
A. Significant team contributions
B. A Continuous Delivery Pipeline
C. The highest possible quality
D. Improved capacity allocation
View answer
Correct Answer: C
Question #9
What can a Release Train Engineer use to support relentless improvement for the Program Increment?
A. Inspect and Adapt event
B. Release management meeting
C. Product Owner sync
D. Iteration retrospective
View answer
Correct Answer: A
Question #10
When should a Product Owner (PO) develop preliminary Iteration Goals?
A. During PI Planning
B. Prior to iteration planning
C. After PI Planning
D. During backlog refinement
View answer
Correct Answer: B

View Answers after Submission