DON'T WANT TO MISS A THING?

Certification Exam Passing Tips

Latest exam news and discount info

Curated and up-to-date by our experts

Yes, send me the newsletter

Prince2 Practitioner Exam Practice Made Easy: Latest Mock Exams, PRINCE2® Practitioner Exam | SPOTO

PRINCE2 Practitioner is the advanced level of certification that confirms sufficient understanding of how to tailor and implement PRINCE2 in a project. Our comprehensive practice tests, including free tests and sample questions, provide robust exam practice to help you pass the certification exam. We offer online exam questions, mock exams, and detailed exam questions and answers, ensuring you are well-prepared. Our exam materials and exam dumps cover a variety of scenarios to simulate the actual exam experience. The latest practice tests are designed to help you succeed and achieve your PRINCE2 Practitioner certification.
Take other online exams

Question #1
Who would be responsible for maintaining the Configuration Item Records?
A. Project Manager
B. Project Support
C. Project Assurance
D. Team Manager
View answer
Correct Answer: A

View The Updated Prince2-Practitioner Exam Questions

SPOTO Provides 100% Real Prince2-Practitioner Exam Questions for You to Pass Your Prince2-Practitioner Exam!

Question #2
Which statement best explains the purpose of Tailor to suit the project environment?
A. Ensure project controls are based on project's scale, complexity, importance, capability and risk
B. To use a set of pre-defined templates for the size of project
C. To tailor the use of the principles to suit the project
D. To pick which PRINCE2 processes to apply and which to leave out
View answer
Correct Answer: D
Question #3
Which statement is TRUE with regard to technical stages?
A. Technical stages can only occur sequential
B. Technical stages define where management decisions are appropriate
C. Technical stages often overlap
D. Technical stages define the commitment of resources and authority to spend
View answer
Correct Answer: B
Question #4
Scenario A central government department, the Ministry of Food Hygiene (MFH), faces increasing pressure to cut costs, better manage suppliers’ performance and reduce the confusion caused by inadequate internal controls, outdated standards and outdated technology. External consultants were employed to conduct a feasibility study to identify options to address the problems, and the likely costs and benefits. The following options were considered: Do nothing. Re-engineer selected business functions. Outsource
A. The 10-year outsourcing contract, at current prices, will be worth £80m
B. Outsourcing would allow MFH to take advantage of the best services the outsourcing industry has to offer
C. The total expected savings over 10 years, at current prices, is £20m
D. The 10-year outsourcing contract will enable MFH to stabilize costs at agreed levels
E. The confirmed cost of the Outsourcing project is £2
View answer
Correct Answer: B
Question #5
Scenario: Techniques, processes and procedures 1. Any threat that may result in a loss of MFH data must be escalated immediately. Joint agreements 2. Work is to start at the beginning of week 2 (Stage 4). 3. The project will take two years to complete, at an estimated cost of £2.5m. Tolerances 4. None. Constraints 5. MFH staff must not be involved in any heavy lifting during the removal of existing IT equipment. 6. Installation work must take place during MFH normal working hours. 7. +£10,000 / -£25,000. Re
A. Replace entry 8 with 'Checkpoint Report every Monday by 10
B. Delete entry 9 because this level of detail is unnecessary
C. Move entry 10 to Problem handling and escalation because that section describes how issues are handled
D. Add 'Any risks identified to be added to the Risk Register' to Reporting arrangements
E. Delete entry 11 because the impact analysis should be provided when the issue is notified
View answer
Correct Answer: DE
Question #6
Who is responsible for appointing the Project Manager?
A. Corporate or Programme Management
B. The Project Board
C. The Executive
D. Project Assurance
View answer
Correct Answer: AE
Question #7
While preparing the Configuration Management Strategy, the Project Manager considered the options for change control. He decided to recommend a change budget of £250k, but was undecided on the Change Authority to recommend. Which option is an appropriate Change Authority for the Outsourcing project?
A. The selected service provider to approve and implement all changes
B. Senior User(s) and Project Assurance representatives, within the limits of therecommended change budget
C. The Director of Facilities and the Director of Information Technology to approve all changes
View answer
Correct Answer: AD
Question #8
Which of the following statements would NOT be included in the Project Product Description?
A. Purpose of the product
B. Composition
C. Project level tolerances
D. Quality criteria
View answer
Correct Answer: A
Question #9
HOTSPOT Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes: There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replaceme
A. Mastered
B. Not Mastered
View answer
Correct Answer: A
Question #10
Who is responsible for the initial creation of the Configuration Item records?
A. Project Manager
B. Team Manager
C. Project Assurance
D. Project Support
View answer
Correct Answer: A
Question #11
There are two time driven controls in PRINCE2, which are they?
A. Highlight and End Stage Reports
B. Highlight and Checkpoint Reports
C. Checkpoint and End Project Reports
D. Highlight and Lessons Reports
View answer
Correct Answer: A
Question #12
Which of the following principles uses Product Descriptions to provide clarity by defining each product's purpose, composition, derivation, format, quality criteria and quality method?
A. Tailor to suit the project environment
B. Focus on products
C. Manage by stages
D. Continued business justification
View answer
Correct Answer: B
Question #13
Scenario A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff
A. Project Support will maintain the Risk Register
B. The evaluated net effect of all risks will be updated at the end of each stage and included in the End Stage Report
C. The Change Authority will report monthly to the Project Manager on the status of the change budget
D. Risks that are likely to occur within the next two weeks should be recorded as imminent
E. A summary of risks will be maintained and included with the monthly Highlight Reports to the Project Board
View answer
Correct Answer: D

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: