DON'T WANT TO MISS A THING?

Certification Exam Passing Tips

Latest exam news and discount info

Curated and up-to-date by our experts

Yes, send me the newsletter

Prince2 Practitioner Exam Questions 2024 Updated: Get Ready for Exams, PRINCE2® Practitioner Exam | SPOTO

PRINCE2 Practitioner is the advanced level of certification that confirms sufficient understanding of how to tailor and implement PRINCE2 in a project. Our comprehensive practice tests, including free tests and sample questions, are designed to provide essential exam practice to help you pass the certification exam. We offer a variety of online exam questions, mock exams, and detailed exam questions and answers, ensuring you are well-prepared. Our exam materials, including exam dumps, cover diverse scenarios to simulate the actual exam experience. The latest practice tests are crafted to help you succeed by addressing the complexity of the project at hand and leveraging your individual project management experience. Utilize our up-to-date resources to gain confidence and achieve your PRINCE2 Practitioner certification, ensuring you can effectively apply PRINCE2 principles in your professional environment.
Take other online exams

Question #1
HOTSPOT Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required. Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of
A. Mastered
B. Not Mastered
View answer
Correct Answer: CD

View The Updated Prince2-Practitioner Exam Questions

SPOTO Provides 100% Real Prince2-Practitioner Exam Questions for You to Pass Your Prince2-Practitioner Exam!

Question #2
Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required.
A. Delete entry 4 because external suppliers are responsible for applying any relevant standards to their work
B. Delete entry 5 because the lack of a change management procedure makes the MFH document standards unsuitable
C. Add 'All contracts must conform to current employment laws"
D. Add 'PRINCE2 change control procedures will be used to manage any changes to baselined products'
View answer
Correct Answer: A
Question #3
If the Project Board are too busy to authorize all change requests themselves they can appoint?
A. A Change Authority
B. A Change Board
C. A Change Committee
D. A Change Budget
View answer
Correct Answer: A
Question #4
In which strategy would the change control process be recorded?
A. Quality Management Strategy
B. Configuration Management Strategy
C. Risk Management Strategy
D. Communication Management Strategy
View answer
Correct Answer: C
Question #5
Which other management product is created when the Business case is updated during Initiating a Project?
A. Post project review plan
B. Risk Register
C. Benefits Review plan
D. Issue Register
View answer
Correct Answer: A
Question #6
The Work Package has been in progress for four weeks and has four weeks remaining. The Information Technology Team Manager is concerned that he has no idea what the service provider is doing about preparing to accept the transfer of Information Technology equipment and staff. He is uncertain about what should be happening. Which 2 initial actions should the Team Manager take in response to this concern?
A. Notify the Project Manager by raising an Exception Report
B. Raise this concern in the next fortnightly Checkpoint Report
C. Check the Communication Management Strategy to ascertain what records of communications with the service provider are required
D. Check the Information Technology Work Package for development interfaces to seewhether the service provider Team Manager should have been liaising with the Information Technology team during development
E. Raise an issue to notify the Project Manager of this concern
View answer
Correct Answer: A
Question #7
Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required.
A. Obtain agreement from the Director of Facilities Division to add these into the glossary of terms within the remaining +2 days tolerance
B. Raise an issue (off-specification)
C. Raise an issue (request for change)
D. No action required
View answer
Correct Answer: A
Question #8
Which statement is an appropriate entry for the Initiation Stage Plan?
A. The Daily Log has been updated with the new risks which were identified while preparing the Initiation Stage Plan
B. The plan is based on the external outsourcing consultants being available at the start of the initiation stage
C. The initial project cost estimate of £2
D. The project management team will consist of representatives from the IT and Facilities Divisions
View answer
Correct Answer: CD
Question #9
Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required.
A. Must be kept to a minimum
B. Must be kept to a level acceptable to the Ministry of Food Hygiene
C. Subject to market conditions
D. The annual increase to be less than half the rate of inflation
View answer
Correct Answer: B
Question #10
Scenario Additional Information During the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes: There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff
A. Benefits will be lost if the project is not completed on time
B. A recruitment campaign to fill the existing staff vacancies will need to take place in the next 12 months
C. Additional 10% increase in orders in year two
D. The prepared calendar pack must be delivered by the first week in December
E. The print company requires a 2 week notification period of the calendar pack delivery
View answer
Correct Answer: CD
Question #11
Which management product defines the detailed nature, purpose and function of a product?
A. Plan
B. Quality Register
C. Project Product Description
D. Product Description
View answer
Correct Answer: A
Question #12
While preparing the Risk Management Strategy, the Project Manager considered the commercial customer/supplier environment and how this may affect the management of risk. Which approach should the Outsourcing project adopt?
A. Plan to use the selected service provider's risk management procedures
B. All project risks associated with the specialist deliverables should be owned by the selected service provider
C. Due to the sensitive nature of this project, consideration should be given to creating a separate Risk Register to be held by MFH and the selected supplier
View answer
Correct Answer: AB
Question #13
When considering the business options in the business case, which of these is NOT an option?
A. Do nothing
B. Do the maximum
C. Do the minimum
D. Do something
View answer
Correct Answer: B
Question #14
When examining a project issue, which three aspects should be considered? 1. Performance targets 2. Business Case 3. Resources 4. Risk
A. 1, 3, 4
B. 2, 3, 4
C. 1, 2, 4
D. 1, 2, 3
View answer
Correct Answer: D
Question #15
Which of the following represents the four key characteristics a good Project board should display?
A. Authority, Credibility, Commitment, Availability
B. Authority, Credibility, Delegation, Availability
C. Authority, Availability, Connections, Delegation
D. Authority, Credibility, Connections, Delegation
View answer
Correct Answer: A

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: