Scenario A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff
A. During stage 4, the selected service provider will manage any risks to their Business Case and report these to the Project Manager on a weekly basis
B. The Project Board should hold monthly meetings to review project progress
C. When closing a project, the follow-on action recommendations should be updated with any risks relating to the realization of benefits after the outsourced services go live
D. Any new risks identified during product development should be reported to the Project Manager by the Team Manager when delivering the completed Work Package
E. When authorizing a stage, the Project Board will check that the exposure to risk is still acceptable