Latest Cisco, PMP, AWS, CompTIA, Microsoft Materials on SALE Get Now Get Now
Home/
Blog/
Download Free PMI-CAPM Exam Questions Demo and Practice Tests | Updated 2025
Download Free PMI-CAPM Exam Questions Demo and Practice Tests | Updated 2025
SPOTO 2023-05-22 00:00:00
HOW.png

     If you believe that PMI exam study guides are out of your price range, reconsider because SPOTO gives you the competitive edge in the most cost-effective manner possible. In addition, we produce a comprehensive study guide that collects everything under one roof. There is no need to spend countless hours perusing through numerous textbooks and course materials because everything is organized based on its relevance to the exams. Thus, it is possible to rapidly prepare for IT certification exams while maintaining one's current employment.

get 100% pass dumps

QUESTION 1

A project manager is performing the procurement management process with three vendors. The project team is reviewing the requests for proposal (RFPs)

What type of procurement document is the RFP?

 

A. Bid document

B. Statement of work(Sow)

C. Source selection criteria

D. Independent cost estimate

 

Correct Answer: A

 

QUESTION 2

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders?

 

A. Prioritization

B. Directions of influence

C. Salience model

D. Power/influence grid

 

Correct Answer: D

 

QUESTION 3

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

 

A. Predictive

B. Adaptive

C. A mix

D. Agile

 

Correct Answer: C

 

QUESTION 4

A project manager needs to tailor the Project Cost Management process Which considerations should the project manager apply?

 

A. Diversity background

B. Stakeholder's relationships

C. Technical expertise

D. Knowledge management

 

Correct Answer: C

 

QUESTION 5

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

 

A. Plan Quality Management

B. Control Quality

C. Risk Management

D. Plan Scope Management 

Correct Answer:


get 100% pass dumps


QUESTION 6



Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

 

A. List of identified risks, potential risk owners ,list of potential risk response

B. List of identified risks, list of causes, list of risk categories

C. Short risk titles, list of potential risk owners, list of impacts on objectives

D. List of activities affected, list of potential risk responses, list of causes

 

Correct Answer: A

 

QUESTION 7

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

 

A. Project Schedule Management

B. Project Scope Management

C. Project Resource Management

D. Project Integration Management

 

Correct Answer: D

 

QUESTION 8

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

 

A. Project level

B. Organizational level

C. Industry level

D. Influential level

 

Correct Answer: B

 

QUESTION 9

What does the creation of a project management plan accomplish?

 

A. Defines the basis of all project work and how it will be performed

B. Acknowledges the existence of a project, and defines its high-level information

C. Authorizes the project manager to apply organizational resources to project activities

D. Provides the project manager with organizational standards, policies, processes, and procedures

 

Correct Answer: A

 

QUESTION 10

The project manager is working in the processes of Project Resource Management Which process is the project manager developing if they are using parametric estimation?

 

A. Plan Resource Management

B. Estimate Activity Resources

C. Estimate Costs

D. Acquire Resources

 

Correct Answer: B

    SPOTO provides comprehensive, downloadable training resources. These materials include practice test questions and answers, PMI exam files, a video training course, and a study guide. Exam candidates can pass certification examinations more quickly with the aid of these study tools. The most recent questions added to the question pool are used to rapidly update PMI exam papers, practice test questions, and accurate answers validated by industry experts.


get 100% pass dumps

Latest SPOTO Candidates Pass Feedback


Latest Passing Reports from SPOTO Candidates
PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP-P

PMI-PMP

PMI-PMP

PMI-PMP-P

PMI-PMP-P

Write a Reply or Comment
Home/Blog/Download Free PMI-CAPM Exam Questions Demo and Practice Tests | Updated 2025
Download Free PMI-CAPM Exam Questions Demo and Practice Tests | Updated 2025
SPOTO 2023-05-22 00:00:00
HOW.png

     If you believe that PMI exam study guides are out of your price range, reconsider because SPOTO gives you the competitive edge in the most cost-effective manner possible. In addition, we produce a comprehensive study guide that collects everything under one roof. There is no need to spend countless hours perusing through numerous textbooks and course materials because everything is organized based on its relevance to the exams. Thus, it is possible to rapidly prepare for IT certification exams while maintaining one's current employment.

get 100% pass dumps

QUESTION 1

A project manager is performing the procurement management process with three vendors. The project team is reviewing the requests for proposal (RFPs)

What type of procurement document is the RFP?

 

A. Bid document

B. Statement of work(Sow)

C. Source selection criteria

D. Independent cost estimate

 

Correct Answer: A

 

QUESTION 2

What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders?

 

A. Prioritization

B. Directions of influence

C. Salience model

D. Power/influence grid

 

Correct Answer: D

 

QUESTION 3

In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?

 

A. Predictive

B. Adaptive

C. A mix

D. Agile

 

Correct Answer: C

 

QUESTION 4

A project manager needs to tailor the Project Cost Management process Which considerations should the project manager apply?

 

A. Diversity background

B. Stakeholder's relationships

C. Technical expertise

D. Knowledge management

 

Correct Answer: C

 

QUESTION 5

If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?

 

A. Plan Quality Management

B. Control Quality

C. Risk Management

D. Plan Scope Management 

Correct Answer:


get 100% pass dumps


QUESTION 6



Which of the following must be included in the risk register when the project manager completes the Identify Risks process?

 

A. List of identified risks, potential risk owners ,list of potential risk response

B. List of identified risks, list of causes, list of risk categories

C. Short risk titles, list of potential risk owners, list of impacts on objectives

D. List of activities affected, list of potential risk responses, list of causes

 

Correct Answer: A

 

QUESTION 7

Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?

 

A. Project Schedule Management

B. Project Scope Management

C. Project Resource Management

D. Project Integration Management

 

Correct Answer: D

 

QUESTION 8

A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?

 

A. Project level

B. Organizational level

C. Industry level

D. Influential level

 

Correct Answer: B

 

QUESTION 9

What does the creation of a project management plan accomplish?

 

A. Defines the basis of all project work and how it will be performed

B. Acknowledges the existence of a project, and defines its high-level information

C. Authorizes the project manager to apply organizational resources to project activities

D. Provides the project manager with organizational standards, policies, processes, and procedures

 

Correct Answer: A

 

QUESTION 10

The project manager is working in the processes of Project Resource Management Which process is the project manager developing if they are using parametric estimation?

 

A. Plan Resource Management

B. Estimate Activity Resources

C. Estimate Costs

D. Acquire Resources

 

Correct Answer: B

    SPOTO provides comprehensive, downloadable training resources. These materials include practice test questions and answers, PMI exam files, a video training course, and a study guide. Exam candidates can pass certification examinations more quickly with the aid of these study tools. The most recent questions added to the question pool are used to rapidly update PMI exam papers, practice test questions, and accurate answers validated by industry experts.


get 100% pass dumps

Latest SPOTO Candidates Pass Feedback


Latest Passing Reports from SPOTO Candidates
PMI-PMP-P
PMI-PMP-P
PMI-PMP-P
PMI-PMP-P
PMI-PMP-P
PMI-PMP-P
PMI-PMP-P
PMI-PMP-P
PMI-PMP
PMI-PMP-P
Write a Reply or Comment
Don't Risk Your Certification Exam Success – Take Real Exam Questions
Eligible to sit for Exam? 100% Exam Pass GuaranteeEligible to sit for Exam? 100% Exam Pass Guarantee
SPOTO Ebooks
Recent Posts
IBM BI ecosystem's authoritative Cognos v12 Professional Certification for Operations and Maintenance: IBM C9006600 
A leading senior solutions expert certification in the field of cybersecurity: F5 401
Globally recognized leading certification in access management: F5 304
IBM's DataPower certification, a leading authority in the integrated ecosystem: C0000308
IBM C9002700: Global IBM i Enterprise Application Development Certification
The world's leading certification in application security for Web application firewalls: F5 303
Global DNS Specialist Certification for Application Delivery: F5 302
IBM Cloud Ecosystem Professional Cloud Development Certification: C9005400
The world's premier practical certification exam in the storage field: H13-636
The cradle of F5 technical sales talent: F5 202 Pre-Sales Fundamentals certification
Excellent
5.0
Based on 5236 reviews
Request more information
I would like to receive email communications about product & offerings from SPOTO & its Affiliates.
I understand I can unsubscribe at any time.