SPOTO's latest exam dumps on the homepage, with a 100% pass rate! SPOTO delivers authentic Cisco CCNA, CCNP study materials, CCIE Lab solutions, PMP, CISA, CISM, AWS, and Palo Alto exam dumps. Our comprehensive study materials are meticulously aligned with the latest exam objectives. With a proven track record, we have enabled thousands of candidates worldwide to pass their IT certifications on their first attempt. Over the past 20+ years, SPOTO has successfully placed numerous IT professionals in Fortune 500 companies.
Take other online exams

Question #1
What does the business value assigned to PI objective communicate?
A. the customer satisfaction of achieving the objective
B. the potential business impact of achieving the objective
C. the monetary gain of achieving the objective
D. the cost of achieving the objective
View answer
Correct Answer: B
Question #2
What is the role of the Product Owner?
A. To ensure quality by testing the Solution
B. To prioritize the Program Backlog
C. Estimate the Stories in the Product Backlog
D. To represent the Customer to the Agile Teamcorrect
View answer
Correct Answer: D
Question #3
An Agile Team has which two characteristics? (Choose two.)
A. A stand-alone unit of individuals who do not require input from other teams to complete their taskscorrect
B. A group of dedicated individuals who are empowered, self-organizing, self-managing, and deliver valuecorrect
C. A small group of typically 5 - 11 dedicated individuals who have the skills necessary to define, build, test, and deploy increments of valuecorrect
D. A large group of individuals who all work together to create value for the client
E. A group of dedicated individuals that work in phase-gate steps to complete their PI Objectives
View answer
Correct Answer: ABC
Question #4
What is at the base of the House of Lean?
A. Innovation
B. Value
C. Leadership
D. Relentless Improvement
View answer
Correct Answer: C
Question #5
What information does a cumulative flow diagram provide?
A. The cycle time system information which starts the implementation
B. The self-assessment information for the teams
C. The data for the team to identify current bottleneckscorrect
D. The derived predictability data for the team
View answer
Correct Answer: C
Question #6
On the seventh day of the Iteration, the team realizes that they will not complete 5 of the 13 Stories. The Product Owner (PO) says she cannot negotiate the scope of the remaining Stories any further. What is the PO's best course of action?
A. Defer acceptance testing to the next Iteration
B. Communicate the status of the Iteration to all stakeholderscorrect
C. Have an emergency Iteration Planning meeting
D. Stop the current Iteration and plan a new Iteration with the new knowledge
View answer
Correct Answer: B
Question #7
What is one of the six steps in the Problem Solving Workshop?
A. Apply root solution analysis
B. Brainstorm possible failures
C. Identify the biggest root cause using the Pareto Analysiscorrect
D. Choose a problem to solve―agreement not required
View answer
Correct Answer: C
Question #8
The daily stand-up timebox should not exceed how many minutes?
A. 5 minutescorrect
B. 20 minutes
C. 15 minutes
D. 10 minutes
View answer
Correct Answer: A
Question #9
Which statement defines the purpose of Iteration Planning?
A. It is to analyze, approve, and ready Features for implementation
B. It is to organize the work and define a realistic scope for the Iterationcorrect
C. It is to break Stories into tasks that are achievable in the team's capacity
D. It is to explore and implement program Epics and split them into Features to be further explored
View answer
Correct Answer: B
Question #10
Which statement is true about pair work in the Scaled Agile Framework?
A. It comes from pair programming in Extreme Programming (XP)correct
B. It is a best practice that team members should spend 50% to 100% of the time in pair work
C. It occurs during Iteration Planning
D. It is for developers only
View answer
Correct Answer: A
Question #11
A research story, considered an exploration style Enabler is called
A. spike
B. slice
C. smell
D. stretch task
View answer
Correct Answer: A
Question #12
The Scrum Master wants to establish a team's initial velocity. A team has two testers, three developers, one full-time Scrum Master, and a Product Owner split between two teams. What is their normalized velocity before calculating for time off?
A. 40correct
B. 32
C. 48
D. 52
View answer
Correct Answer: A
Question #13
What type of information can be easily seen in a cumulative flow diagram?
A. Time to complete a Feature
B. Team capacity
C. Work in process across the teamcorrect
D. The number of defects that escape to production
View answer
Correct Answer: C
Question #14
The Release Train Engineer is a servant leader who displays which two actions or behaviors? (Choose two.)
A. You have reached the max number of allowed answerscorrect
B. Establishes Feature acceptance criteria
C. Listens and supports teams in problem identification and decision-makingcorrect
D. Identifies market needs
E. Leads by examplecorrect
F. Owns Vision and Roadmaps, Program Backlog, and ROI
View answer
Correct Answer: ACE
Question #15
What is meant by Realistic in the SMART model used for PI Objectives?
A. factors are out of control
B. all factors are under full control
C. factors that cannot be controlled are recognized
C. none of the above
View answer
Correct Answer: B
Question #16
Which statement describes a cross-functional team?
A. Each team can deliver Features across multiple domainscorrect
B. Each team member can do all the activities to define, build, and test a Solution
C. Each team member can define and build, with a System Team testing the Solution
D. Each team member can define, build, and test a component or Feature
View answer
Correct Answer: A
Question #17
Who removes impediments and protects the team from outside influence?
A. Project Manager
B. Business Owner
C. Product Owner
D. Scrum Master
View answer
Correct Answer: D
Question #18
The CALMR approach to DevOps includes Automation, Lean flow, Measurement, and Recovery. What does the "C" represent?
A. Cycle-time
B. Cadence
C. Continuous Integration
D. Culturecorrect
View answer
Correct Answer: D
Question #19
Which two statements best describe elements of Continuous Delivery? (Choose two.)
A. Development and test environments should be separate from productioncorrect
B. Automate testing Features and nonfunctional requirements
C. Maintain manual deployment
D. Maintain a staging environment that emulates production
E. Deploy to staging every third Iteration
View answer
Correct Answer: A
Question #20
How many are the SAFe Lean-Agile principles?
A. five
B. Four
C. twelve
D. ten
View answer
Correct Answer: D
Question #21
How does a team demonstrate progress?
A. By presenting status slides
B. By having the Product Owner verbally communicate to the stakeholders
C. By showing the actual working productcorrect
D. By showing screen shots of the product
View answer
Correct Answer: C
Question #22
Which process guides the final approval for a release in SAFe?
A. Release Governance
B. Lean Portfolio Management
C. Product Managementcorrect
D. Continuous Delivery Pipeline
View answer
Correct Answer: C
Question #23
Which of the following is not one of the four activities of continuous deployment?
A. test
B. respond
C. deploy
D. Verify
View answer
Correct Answer: A
Question #24
What are three practices of Extreme Programming (XP)? (Choose three.) You have reached the max number of allowed answers
A. Behavior-driven developmentcorrect
B. Intentional architecture
C. Test-driven developmentcorrect
D. Deployment automation
E. Pair programmingcorrect
F. Continuous Integrationcorrect
View answer
Correct Answer: ACEF
Question #25
What is the recommended length of an Iteration?
A. Two weekscorrect
B. Ten weeks
C. Four weeks
D. Eight weeks
View answer
Correct Answer: A
Question #26
What is the goal of the PI Planning event?
A. Build a release Roadmap
B. Achieve alignment on what needs to and can be builtcorrect
C. Create a plan for the upcoming PI showing how Stories map to Iterations
D. Identify the risks in the upcoming Features using a ROAMing exercise
View answer
Correct Answer: B
Question #27
Which statement describes the balance between emergent design and intentional architecture when talking about building in quality?
A. It is required for implementation speed and maturity
B. It is required for speed of value delivery and Solution Intent
C. It is required for speed of development and maintainabilitycorrect
D. It is required for backlog speed and designed refinement
View answer
Correct Answer: C
Question #28
Which is an example of a part of an Iteration retrospective?
A. Estimation of Stories
B. Team discussion around opportunities for continuous improvementcorrect
C. Program level analysis of a problem using root cause analysis techniques
D. Gathering feedback from the stakeholders
View answer
Correct Answer: B
Question #29
A User Story includes which three things? (Choose three.)
A. Whocorrect
B. Level of Risk
C. Whycorrect
D. Whatcorrect
E. Definition of Done
F. How
View answer
Correct Answer: ACD
Question #30
What are two behaviors of an effective Scrum Master? (Choose two.) You have reached the max number of allowed answers
A. Facilitate the PI Planning sessioncorrect
B. To act as a servant leader and exhibit Lean-Agile Leadershipcorrect
C. To guarantee no changes are made to the scope during an Iteration
D. To facilitate the team's progress toward the Iteration goalscorrect
E. Facilitate more than two teams
View answer
Correct Answer: ABD

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: