Free PMI-CAPM Exam Questions and Detailed Answers

Exam name:Certified Associate in Project Management
Number of exam questions:150
Exam format:multiple choice questions, drag-and-drop questions
Exam time: 3 hours
Exam fee: 300$

free PMI-CAPM exam questions with detailed explanations. Our CAPM practice test contains exam-like questions to help you prepare for the Certified Associate in Project Management exam and get CAPM certified.

Take other online exams

Question #1
A project manager is performing the procurement management process with three vendors. The project team is reviewing the requests for proposal (RFPs) What type of procurement document is the RFP?
A. id document
B. tatement of work(Sow)
C. ource selection criteria
D. ndependent cost estimate
View answer
Correct Answer: A
Question #2
What method for categorizing stakeholders is suitable for small projects with simple relationships among stakeholders?
A. rioritization
B. irections of influence
C. alience model
D. ower/influence grid
View answer
Correct Answer: D
Question #3
In a large organization, with projects of different types and sizes, what kind of approach or method would be best to use?
A. redictive
B. daptive
C. mix
D. gile
View answer
Correct Answer: C
Question #4
A project manager needs to tailor the Project Cost Management process Which considerations should the project manager apply?
A. iversity background
B. takeholder's relationships
C. echnical expertise
D. nowledge management
View answer
Correct Answer: C
Question #5
If you are using an Ishikawa diagram to determine the root cause of problems, which process are you engaged in?
A. lan Quality Management
B. ontrol Quality
C. isk Management
D. lan Scope Management
View answer
Correct Answer: B
Question #6
Which of the following must be included in the risk register when the project manager completes the Identify Risks process?
A. ist of identified risks, potential risk owners ,list of potential risk response
B. ist of identified risks, list of causes, list of risk categories
C. hort risk titles, list of potential risk owners, list of impacts on objectives
D. ist of activities affected, list of potential risk responses, list of causes
View answer
Correct Answer: A
Question #7
Deciding the phases of a project life cycle would be considered a part of which of these knowledge areas?
A. roject Schedule Management
B. roject Scope Management
C. roject Resource Management
D. roject Integration Management
View answer
Correct Answer: D
Question #8
A project manager uses their networking skills to build agreement with a difficult stakeholder. What level of influence did the project manager apply?
A. roject level
B. rganizational level
C. ndustry level
D. nfluential level
View answer
Correct Answer: B
Question #9
What does the creation of a project management plan accomplish?
A. efines the basis of all project work and how it will be performed
B. cknowledges the existence of a project, and defines its high-level information
C. uthorizes the project manager to apply organizational resources to project activities
D. rovides the project manager with organizational standards, policies, processes, and procedures
View answer
Correct Answer: A
Question #10
The project manager is working in the processes of Project Resource Management Which process is the project manager developing if they are using parametric estimation?
A. lan Resource Management
B. stimate Activity Resources
C. stimate Costs
D. cquire Resources
View answer
Correct Answer: B

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: