SPOTO's latest exam dumps on the homepage, with a 100% pass rate! SPOTO delivers authentic Cisco CCNA, CCNP study materials, CCIE Lab solutions, PMP, CISA, CISM, AWS, and Palo Alto exam dumps. Our comprehensive study materials are meticulously aligned with the latest exam objectives. With a proven track record, we have enabled thousands of candidates worldwide to pass their IT certifications on their first attempt. Over the past 20+ years, SPOTO has successfully placed numerous IT professionals in Fortune 500 companies.
Take other online exams

Question #1
If a user creates a new demand from the demand workbench, what state will the system save the record in?
A. pproved
B. pen
C. raft
D. ualified
View answer
Correct Answer: D
Question #2
The Business Unit field on a Project or Demand form displays values from a specific table. What type of field is this?
A. Journal
B. References
C. Conditions
D. List
View answer
Correct Answer: B
Question #3
What is a resource event?
A. non-scheduled activity impacting capacity
B. block of time that a resource spends on a task
C. n external event
D. n event scheduled by a project manager
View answer
Correct Answer: B
Question #4
What is the demand workbench used for? (Choose two.)
A. pproving ideas
B. pproving demands
C. omparing and prioritizing demands against other demands
D. omparing demands with portfolios
View answer
Correct Answer: BC
Question #5
Which role is needed to group related projects and demands?
A. t_project_user
B. t_project_manager
C. t_demand_manager
D. t_program_manager
View answer
Correct Answer: D
Question #6
Which demand category would a demand manager select, if they need to create an enhancement?
A. ADefect
B. BChange
C. COperational
D. DStrategic
View answer
Correct Answer: C
Question #7
The project property to update actual effort from time card is controlled at what level?
A. Application Level (Global)
B. Portfolio Level
C. Program Level
D. Project Level
View answer
Correct Answer: D
Question #8
Which of the following can be used to calculate planned cost when creating a resource plan? Choose 2 answers
A. Demand ratecorrect
B. Rate cardcorrect
C. Default rate
D. Project ratecorrect
View answer
Correct Answer: ABD
Question #9
Which demand category would a demand manager select, if they need to create an enhancement?
A. Defect
B. Change
C. Operationalcorrect
D. Strategic
View answer
Correct Answer: C
Question #10
Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.
A. Apm_project
B. Bpm_toplevel_project
C. Cpm_home_page_config
D. Dproject_template_config
View answer
Correct Answer: C
Question #11
Which statement defines the Project Workspace?
A. A central location to view of all projects in a portfolio to prioritize work
B. A central location for creating and managing projects
C. A central location for viewing and assessing business demands
D. A central location transform the navigation of lists and forms into an interactive graphical experience
View answer
Correct Answer: B
Question #12
Idea [im_idea_core] is directly extended from which table?
A. It is not extended from any tablecorrect
B. Task
C. Idea Modules
D. Project
View answer
Correct Answer: A
Question #13
A user's availability is calculated as:
A. Allocated time
B. Capacity minus allocation
C. Sum of allocated and confirmed hours, divided by the total capacity
D. Allocated hours divided by the total capacitycorrect
View answer
Correct Answer: D
Question #14
Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.
A. pm_project
B. pm_toplevel_project
C. pm_home_page_config
D. project_template_config
View answer
Correct Answer: C
Question #15
Which property controls the changes in cost and resource plans with respect to the change in the start date of a demand or project?
A. A'Change Resource Plan, Cost Plan and Benefit Plan Start Date with Demand or Project Start Date Change'
B. B'Enable altering of planned date for task in WIP/Closed'
C. C'Rollup project start date from tasks'
D. D'Calculate ROI percentage based on a project's estimated cost and its net value'
View answer
Correct Answer: A
Question #16
Using the Request type field on a resource plan, which options can be used to request a resource? (Choose three.)
A. ay
B. erson Days
C. ours
D. TE
E. onth
View answer
Correct Answer: BCD
Question #17
In which table can you find cost information for a specific fiscal period?
A. ost_plan_breakdown
B. xpense_line
C. m_project
D. ost_plan
View answer
Correct Answer: A
Question #18
If a project manager is responsible for approving time sheets or submitting time cards on behalf of team members, they should be given what role?
A. activity_admin
B. timecard_admin
C. form_admin
D. approval_admin
View answer
Correct Answer: B
Question #19
If a sub-project and parent project have different project currencies, this property should be set to true for cost roll-ups.
A. com
B. com
C. com
D. com
View answer
Correct Answer: D
Question #20
What is a resource event?
A. AAn external event
B. BA non-scheduled activity impacting capacity
C. CA block of time that a resource spends on a task
D. DAn event scheduled by a project manager
View answer
Correct Answer: B
Question #21
Which related lists should primarily be used to capture financial data in a project? (Choose two.)
A. rograms
B. ost Plans
C. onetary Benefit Plans
D. isks
View answer
Correct Answer: BC
Question #22
The Project management application supports two types of external dependencies. What are they?Choose 2 answers
A. Hard Dependency
B. Task Dependency
C. Change Dependency
D. Soft Dependency
E. Milestone Dependency
View answer
Correct Answer: AD
Question #23
If a lens has four entities, which entity within the lens structure would not have a parent reference?
A. Top-level entitycorrect
B. Second-level entity
C. Third-level entity
D. Bottom entity
View answer
Correct Answer: A
Question #24
The color band at the top of the project card in Project Workspace displays what project attribute?
A. Statuscorrect
B. Risk
C. State
D. Issues
View answer
Correct Answer: A
Question #25
When copying a source project to a target project, what fields are copied by default? Choose 3 answers
A. Planned dates
B. State
C. Short description
D. Duration fields
E. Number
View answer
Correct Answer: ACD
Question #26
What features are not included in a teamspace application but can be added in teamspace settings? Choose 2 answers
A. Idea
B. Demand Assessments
C. Workbench configuration
D. Project
View answer
Correct Answer: AB
Question #27
Which statement defines the Project Workspace?
A. A central location to view of all projects in a portfolio to prioritize work
B. A central location for creating and managing projectscorrect
C. A central location transform the navigation of lists and forms into an interactive graphical experience
D. A central location for viewing and assessing business demands
View answer
Correct Answer: B
Question #28
Use this table to configure the parameters displayed on a project card on the My Projects Space page of the Project Workspace.
A. pm_project
B. pm_toplevel_project
C. pm_home_page_configcorrect
D. project_template_config
View answer
Correct Answer: C
Question #29
How many WBS levels can be shown on the planning console?
A. One
B. Two
C. Three
D. No Limit
View answer
Correct Answer: D
Question #30
What role can configure the default columns in the project planning console? Choose 2 answers
A. it_pps_admin
B. it_project_manager
C. it_console_admin
D. admin
View answer
Correct Answer: AD

View The Updated ServiceNow Exam Questions

SPOTO Provides 100% Real ServiceNow Exam Questions for You to Pass Your ServiceNow Exam!

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: