PRINCE2 Practitioner is the advanced level of certification that confirms sufficient understanding of how to tailor and implement PRINCE2 in a project. Our comprehensive practice tests, including free tests and sample questions, are designed to provide essential exam practice to help you pass the certification exam. We offer a variety of online exam questions, mock exams, and detailed exam questions and answers, ensuring you are well-prepared. Our exam materials, including exam dumps, cover diverse scenarios to simulate the actual exam experience. The latest practice tests are crafted to help you succeed by addressing the complexity of the project at hand and leveraging your individual project management experience. Utilize our up-to-date resources to gain confidence and achieve your PRINCE2 Practitioner certification, ensuring you can effectively apply PRINCE2 principles in your professional environment.
Take other online exams

Question #1
Extract from the Project Product Description (with errors) Which 2 statements apply to the Derivation section?
A. Move entry 9 to Composition because this is within the scope of the project
B. Delete entry 10 because this is NOT a source product for this project
C. Delete entry 11 as this is already correctly shown under Development Skills required
D. Move entry 12 to Composition, because this is within the scope of this project
E. Add 'Professional photographer'
View answer
Correct Answer: D

View The Updated Prince2-Practitioner Exam Questions

SPOTO Provides 100% Real Prince2-Practitioner Exam Questions for You to Pass Your Prince2-Practitioner Exam!

Question #2
Which of the following statements describes an outcome?
A. Any of the projects specialist products
B. A result of the change derived from using the project's products
C. A measurable improvement resulting from a change
D. Something perceived as advantages by a stakeholder
View answer
Correct Answer: B
Question #3
Extract from the Project Product Description (with errors) Which 2 statements apply to the Customer's quality expectations section?
A. Delete entry 16 because this should be shown on the Product Description for the photos
B. Delete entry 17 because this is beyond the scope of this project
C. Delete entry 18 because standards should NOT be shown here
D. Delete entry 19 because this should appear in the Product Description for the calendar and not the Project Product Description
E. Delete entry 20 because this is an expected benefit and should be recorded in the Business Case
View answer
Correct Answer: C
Question #4
Extract from the Project Product Description (with errors) Which 2 statements apply to the Composition section?
A. Amend entry 2 to 'Selected paper'
B. Delete entry 3 because this is NOT a major product to be delivered by this project
C. Move entry 6 to Derivation because this product already exists
D. Delete entry 7 because these will be produced by the photographer
E. Add 'Calendars distributed to customers'
View answer
Correct Answer: A
Question #5
Which role is responsible for providing the customer's quality expectations and acceptance criteria for the project?
A. Executive
B. Corporate or Programme Management
C. Senior User
D. Project Assurance
View answer
Correct Answer: BE
Question #6
Extract from the Project Product Description (with errors) Which 2 statements apply to the Acceptance criteria section?
A. Amend entry 21 to 'Appearance - 12 photos each showing different members of staff
B. Move entry 21 to Composition because the photos are part of the final product
C. Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project
D. Move entry 23 to Derivation because the Data Protection Act already exists
E. Delete entry 24 because this is NOT a suitable acceptance criteria for this project
View answer
Correct Answer: D
Question #7
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project. Director of Finance Division: She was transferred from the Information Technology
A. Remove because he will be impacted by the project and therefore represents a user
B. Replace with 'Project Manager' because this is a simple project that does not require additional business assurance
C. Add Outcome Consultants' because they carried out the feasibility study
D. Add 'Director of Finance Division' because she is responsible for checking that any supplier and contractor payments are authorized
E. Retain because he is familiar with the Ministry of Food Hygiene business strategy, the business level risk assessment and the Business Case standards
View answer
Correct Answer: BC
Question #8
Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project
B. The justification for the project should remain valid
C. The justification for the project may change
D. If the project is no longer justified it should be stopped
View answer
Correct Answer: B
Question #9
Which of the following should NOT be included in the business case?
A. Reasons
B. Major Risks
C. Business options
D. Business approach
View answer
Correct Answer: D
Question #10
Extract from the Project Product Description (with errors) Which 2 statements apply to the Development skills required section?
A. Move entry 13 to Composition because the appointment of the photographer is within the scope of this project
B. Move entry 13 to Derivation because this is a source of information for this project
C. Delete entry 14 because this skill is NOT required within this project
D. Delete entry 15 because this skill is NOT required within this project
E. Add 'Knowledge of Data Protection Act
View answer
Correct Answer: B
Question #11
Additional Information Further information on some resources who could be involved in the project: Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project. Director of Finance Division: She was transferred from the Information Technology
A. Retain because he provides the outsourcing resources required to support the project
B. Replace with 'Director of Research and Development' because she deals with both the Information Technology and the Facilities Divisions and can make sure her division's needs are specified
C. Remove because he has no authority to commit user resources
D. Add 'Hardware Manager' because he provides computer hardware to all business functions and will be impacted by the outcome
E. Retain because he will be providing support to the Information Technology and Facilities teams during the project
View answer
Correct Answer: CE
Question #12
Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required.
A. The SLA must extend for the full duration of the service contract
B. Any changes to the SLA must be managed through formal change control
C. External consultants are to assist in the creation of the SLA
D. The selected service provider should be located locally
View answer
Correct Answer: AB
Question #13
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required. Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the bus
A. He started the company 25 years ago
B. He knows his job very well
C. He restricts his visits to the engineering area
D. He has the authority to commit resources as required
E. He has an overall perspective of the business's strategic requirements
View answer
Correct Answer: D
Question #14
PRINCE2 proposes 3 levels of Plan, which are they?
A. Initiation, Project and Stage Plans
B. Project, Stage and Exception Plans
C. Initiation, Project and Benefit Review Plans
D. Project, Stage and Team Plans
View answer
Correct Answer: D
Question #15
Additional Information Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required. Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the bus
A. She can represent the Marketing department
B. She previously had a successful career in publicity
C. The Marketing department will help to deliver the benefits of this project
D. The project will be funded from the business marketing budget
E. A number of the products will be produced by the Sales department and the Marketing department
View answer
Correct Answer: A
Question #16
Which of the following principles uses Product Descriptions to provide clarity by defining each product's purpose, composition, derivation, format, quality criteria and quality method?
A. Tailor to suit the project environment
B. Focus on products C
D. Continued business justification
View answer
Correct Answer: B

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: