The IASSC Lean Six Sigma Green Belt certification validates your proficiency in utilizing Six Sigma methodologies to improve processes and drive quality management. Candidates pursuing this certification must demonstrate a solid understanding of the DMAIC methodology, data analysis, and problem-solving techniques. SPOTO offers expertly crafted IASSC Green Belt sample questions tailored to the latest 2024 exam standards. These sample questions simulate real exam scenarios, enabling candidates to familiarize themselves with the test structure and key topics. With SPOTO’s high-quality practice tests and study guides, you can effectively identify knowledge gaps, sharpen your skills, and build confidence for exam day. Whether you are a beginner or an experienced professional, SPOTO’s resources provide the comprehensive preparation needed to achieve certification success. Start your journey toward Lean Six Sigma excellence today with SPOTO!
Take other online exams

Question #1
Unequal Variances can be the result of differing types of distributions.
A. True
B. False
View answer
Correct Answer: A
Question #2
To create standardization of financial benefit calculations project savings are typically based on savings over what period of time?
A. 6 months
B. 12 months
C. 24 months
D. The remainder of the calendar year
E. The remainder of the fiscal year
View answer
Correct Answer: B
Question #3
When a Belt is analyzing sample data she should keep in mind that 95% of Normally Distributed data is within +/- 2 Standard Deviations from the Mean.
A. True
B. False
View answer
Correct Answer: A
Question #4
For the data shown here a Belt suspects the three grades are supplying the same results. Which statement(s) are true for proper Hypothesis Testing?
A. The most appropriate Central Tendency to test is the Means
B. An appropriate test to test Central Tendency is the Levene's test
C. An appropriate test to test Central Tendency is the ANOVA test
D. An appropriate test to test Central Tendency is the Mood's Median test
View answer
Correct Answer: D
Question #5
The Central Limit Theorem helps us understand the ___________ we are taking and is the basis for using sampling to estimate population parameters.
A. Analysis
B. Kurtosis
C. Risk
D. Route
View answer
Correct Answer: C
Question #6
When it comes to Control one of the most effective means of eliminating defects is to _________________ .
A. True
B. False
View answer
Correct Answer: C
Question #7
A primary benefit of using a Multi-Vari Chart is it provides a visual presentation of two-way interactions.
A. True
B. False
View answer
Correct Answer: A
Question #8
A Belt experienced an Alpha of .05 and a Beta of .10 and knew these are the most common risk levels when running a Statistical test.
A. True
B. False
View answer
Correct Answer: A
Question #9
When a Belt applies the practice of Poka-Yoke to a project challenge she is attempting to make certain the activity is _______________ .
A. Well documented
B. Removed from the line
C. Mistake proofed
D. Highly visible
View answer
Correct Answer: C
Question #10
A process can be defined as a repetitive and systematic series of steps or activities where inputs are modified or assembled to achieve a customer desired result.
A. True
B. False
View answer
Correct Answer: A
Question #11
A periodic time frame can be used to arrange for Control Limit and Center Line calculations with good SPC implementation in a process.
A. True
B. False
View answer
Correct Answer: A
Question #12
If a Histogram displays two peaks the distribution would likely be _____________.Please choose the correct answer.
A. Transformed
B. Multi-skewed
C. Bimodal
D. Bi-attribute
View answer
Correct Answer: C
Question #13
Bias in Sampling is an error due to lack of independence among random samples or due to systematic sampling procedures.
A. True
B. False
View answer
Correct Answer: A
Question #14
Which statement(s) describe an undesirable situation when implementing SPC?
A. The lower Control Limit for the R chart is equal to zero
B. Attempt to use SPC for tracking transaction times at a warehouse
C. A process is in Statistical Control before implementation of SPC
D. The Control Limits are wider than the customer specification limits
View answer
Correct Answer: D
Question #15
Cost of Poor Quality (COPQ) can be classified as Tangible (Visible) Costs and Hidden Costs.
A. True
B. False
View answer
Correct Answer: A
Question #16
The Mann-Whitney Test is used to test if the Means for two samples are different.
A. Illustrate one-tail proportions
B. Analyze the "what if" scenario
C. Contrast the Outliers under the tail
D. Compare more than two sample proportions with each other
View answer
Correct Answer: B
Question #17
The Regression Model for an observed value of Y contains the term ?o which represents the Y axis intercept when X = 0.
A. True
B. False
View answer
Correct Answer: A
Question #18
The purpose of a Process Map is to identify the complexity of the process and to assist in identifying critical steps in the process.
A. True
B. False
View answer
Correct Answer: A
Question #19
The 5 Why Analysis is only useful if the possible independent variable can be broken down into five possible causes.
A. True
B. False
View answer
Correct Answer: B
Question #20
Fractional Factorial designs for an experimental approach are used when ____________ about the multiple metric interaction in a process.
A. Only a Few Are Tested
B. Opposite Factors Affect Technique
C. One Factor At a Time
D. Ordinary Fractional Approach Technique
View answer
Correct Answer: B
Question #21
The higher the sigma level of a process the better the performance.
A. True
B. False
View answer
Correct Answer: A
Question #22
The very best way to begin an effort to map a process is to do which of these?
A. Interview the process owner
B. Interview the manager of the department
C. Walk the actual process from beginning to end
D. Take pictures of the factory floor at each shift
View answer
Correct Answer: C
Question #23
Which element of waste best describes "the cost of an idle resource"?
A. Waiting
B. Motion
C. Inventory
D. Correction
View answer
Correct Answer: A
Question #24
What is the Range (R) of the data set: 2, 5, 6, 9, 8, 5, 7?
A. 7
B. 5
C. 1
D. 6
View answer
Correct Answer: A
Question #25
The X-Y Diagram is a tool used to identify/collate potential X's and assess their relative impact on multiple Y's.
A. True
B. False
View answer
Correct Answer: A

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: