Prince2 Practitioner Exam Essentials: Exam Questions & Practice Tests, PRINCE2® Practitioner Exam | SPOTO

PRINCE2 Practitioner is the advanced level of certification that confirms sufficient understanding of how to tailor and implement PRINCE2 in a project. Our comprehensive practice tests, including free tests and sample questions, provide robust exam practice to help you pass the certification exam. We offer online exam questions, mock exams, and detailed exam questions and answers, ensuring you are well-prepared. Our exam materials and exam dumps cover a variety of scenarios to simulate the actual exam experience. The latest practice tests are designed to help you succeed and achieve your PRINCE2 Practitioner certification.
Take other online exams

Question #1
Reference Scenario: click here
A. As an off-specification, because the recording of the songs will not fulfil the criteria specified
B. As a request for change, because the product description will need to be updated
C. As a request for change, because the recording will be of better quality
D. As an off-specification, because a proposal to change a baseline has been received
View answer
Correct Answer: B

View The Updated Prince2-Practitioner Exam Questions

SPOTO Provides 100% Real Prince2-Practitioner Exam Questions for You to Pass Your Prince2-Practitioner Exam!

Question #2
Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required.
A. Must be kept to a minimum
B. Must be kept to a level acceptable to the Ministry of Food Hygiene
C. Subject to market conditions
D. The annual increase to be less than half the rate of inflation
View answer
Correct Answer: BE
Question #3
Reference Scenario: click here
A. Yes, because the project cannot be closed until the impact from sales are measured
B. Yes, because the follow-on action will enable this risk to be closed in the risk register
C. No, because a follow-on action should be addressed to an individual rather than a department
D. No, because the benefits management approach should include post-project activities
View answer
Correct Answer: D
Question #4
Extract from the Project Product Description (with errors) Which 2 statements apply to the Derivation section?
A. Move entry 9 to Composition because this is within the scope of the project
C. Delete entry 11 as this is already correctly shown under Development Skills required
D. Move entry 12 to Composition, because this is within the scope of this project
E. Add 'Professional photographer'
View answer
Correct Answer: D
Question #5
Reference Scenario: click here
A. 'Manage by stages', because the project manager reviews the contents of the project initiation documentation when planning stage 4
B. 'Manage by stages', because the project manager reviews the status of stage 3 products at the end of the stage
C. 'Manage by exception', because the project board delegates the authority to the project manager on a stage-by-stage basis
D. 'Manage by exception', because the team manager's performance should be reviewed before authorizing the next work package
View answer
Correct Answer: A
Question #6
Additional Information Product Description Quality notes from the Daily Log The Director of Information Technology Division (DIT) has been asked to ensure that any changes to the outsourced staff employment contracts adhere to employment law. The DIT will review future job descriptions of the transferred staff before the final contract is signed with the selected service provider. The service level agreement between MFH and the selected service provider will specify the type and quality of service required.
A. No staff are to be left behind
B. Staff should be transferred as soon as possible
C. All legal requirements are adhered to for the transfer of staff
D. Retained staff should be of reasonable competence to maintain the SLA
View answer
Correct Answer: DE
Question #7
Reference Scenario: click here
A. It applies it well, because the executive needs to be confident that controls and tolerances are being implemented effectively
B. It applies it well, because a PRINCE2 project should structure the project into management stages to enable approval on a stage-by-stage basis
C. It applies it poorly, because roles should be combined in a small project as long as there is no conflict of interest
D. It applies it poorly, because a PRINCE2 project should focus on delivering quality outputs rather than on the work required to deliver the products
View answer
Correct Answer: A
Question #8
Reference Scenario: click here
A. Yes, because the project manager should ensure that the quality controls for the 'launch event plan' will meet the defined quality criteria
C. No, because it is the senior user who should confirm the customer quality expectations and acceptance criteria for the project
View answer
Correct Answer: D
Question #9
Reference Scenario: click here
A. Project assurance
B. Project manager
C. Team manager
D. Executive
View answer
Correct Answer: C
Question #10
Extract from the Project Product Description (with errors) Which 2 statements apply to the Acceptance criteria section?
A. Amend entry 21 to 'Appearance - 12 photos each showing different members of staff
C. Delete entry 22 because the development of the new company logo is not within the scope of the Calendar project
D. Move entry 23 to Derivation because the Data Protection Act already exists
E. Delete entry 24 because this is NOT a suitable acceptance criteria for this project
View answer
Correct Answer: D
Question #11
Reference Scenario: click here
A. Plan the next management stage
B. Prepare premature closure
C. Produce an exception plan
D. Create the project plan
View answer
Correct Answer: C
Question #12
Reference Scenario: click here
A. 'Transfer the risk', because using a cheaper company transfers the threat to the third party
B. 'Transfer the risk', because using a cheaper company reduces the financial impact on the project
C. 'Reduce a threat', because the threat is being made certain by increasing the probability of it occurring
D. 'Reduce a threat', because the threat is being made less likely to occur and would have less impact
View answer
Correct Answer: D
Question #13
Reference Scenario: click here
A. Yes, because project costs should be recorded as part of the project's business case
B. Yes, because the project's business case should record any benefits for the project's stakeholder
View answer
Correct Answer: A

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.