Free PRINCE2-Practitioner Practice Questions & Answers 2026 Part2

Are you preparing for the PRINCE2 PRINCE2 Practitioner certification exam? SPOTO offers the PRINCE2 PRINCE2 Practitioner Premium File; all questions are aligned with the latest exam content and come with expert-provided answers. Our question banks cover the latest question types, core concepts, and detailed explanations, helping you familiarize yourself with the exam format and difficulty level. Whether you are reviewing core concepts or simulating a real exam environment, these resources will rapidly boost your confidence and readiness.
For over two decades, SPOTO has successfully helped numerous IT professionals secure their ideal positions at Fortune 500 companies. Download now to start practicing efficiently and ensure a high score on the actual exam. Don't miss this opportunity to pass your certification exam with ease!
Take other online exams

Question #1
In which Management product would the Project Board specify where the authority for change requests lies?
A. isk Management Strategy
B. uality Management Strategy
C. ommunication Strategy
D. onfiguration Management Strategy
View answer
Correct Answer: D

View The Updated PRINCE2 Practitioner Exam Questions

SPOTO Provides 100% Real PRINCE2 Practitioner Exam Questions for You to Pass Your PRINCE2 Practitioner Exam!

Question #2
Scenario -Additional Information -Further information on some resources who could be involved in the project:Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running theFinance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.Which 2 alternative actions apply to the proposed business assurance for this project?
A. emove because he will be impacted by the project and therefore represents a user
B. eplace with 'Project Manager' because this is a simple project that does not require additional business assurance
C. dd Outcome Consultants' because they carried out the feasibility study
D. dd 'Director of Finance Division' because she is responsible for checking that any supplier and contractor payments are authorized
E. etain because he is familiar with the Ministry of Food Hygiene business strategy, the business level risk assessment and the Business Case standards
View answer
Correct Answer: DE
Question #3
Scenario -Additional Information -Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started.VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.Central Records: This group of five staff looks after all company records and document control.They now maintain all project files.Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.Which 2 statements explain why the Sales Manager should be appointed as User Assurance for this project?
A. e joined the company last year with huge enthusiasm and is keen to increase sales
B. e can provide an evaluation of the potential impact the calendar will have on sales
C. e is able to advise on suitable stakeholder engagement of current and prospective customers
D. e would like to move into the Marketing department in the future and sees this as an opportunity to work closely with the Marketing Director
E. e can resolve any conflict in requirements between the Sales department and the Marketing department
View answer
Correct Answer: BC
Question #4
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard.He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The delivery of the pilot courses has been split into two separate products: `planned pilot courses' and `delivered pilot courses'. `Planned pilot courses' will be produced during stage 3, and the `delivered pilot courses' will take place during stage 4. This will allow the project board to approve the plan for the pilot courses before the resources are committed to delivering the pilot courses.Why is this an appropriate application of the plans theme to control the project?
A. Because a PRINCE2 project should focus on the quality of the products being delivered
B. Because the pilot courses have been broken down into two separate products
C. Because the project board should ensure that lessons from one stage are applied to the next stage
D. Because the delivery steps to create the pilot courses have been aligned to the management stages
View answer
Correct Answer: D
Question #5
Scenario 2: Louistown City CouncilLouistown is a historical town which is home to over 40,000 residents and attracts over 20,000 visitors per year. The city council has been criticized for the lack of investment and modernization of the town centre.They have recently decided to improve the vibrancy of the area and offer increased opportunities for business by approving the funds for the ‘Louistown is Open for Business’ (LOB) portfolio. This is an ambitious portfolio of projects covering the next five-year plan cycle.A new shopping centre, provisionally named ‘LouisShopping’, is seen as a key project within this portfolio. This is a complex infrastructure project due to the: location of the building and historical nature of the surrounding buildings requirement for the design to be consistent with the environment while offering modern facilities supported by the latest technology need to include underground parking space importance of minimizing disruption to residents and businesses during the construction works recent award of ‘green town’ status to Louistown, and the sustainability requirements this will impose on the development.Due to the nature of the work, in which just the construction element is likely to span over two financial years, the council has approved the strategic business case, the initial high-level project plan and has appointed BuildyBrick as the main contractor. They have established a requirement for a traditional delivery approach in line with their standard approach to projects. The general view is that this project is long overdue, and the council would like ‘LouisShopping’ to be open to the public by the end of financial year three.The project has just completed the initiation stage and commenced the first delivery stage (stage 2). The high-level project plan is as follows:Stage 1 (initiation)strategic business case and high-level project plan approvalappoint contractorStage 2 -designStage 3 -site preparationutilities and systemsconstructionStage 4 -testinginspectionsStage 5 -demobilization.The main output from the project is a shopping centre constructed and ready to open to the public.Additional Information -The Mayor of Louistown has worked at the city council for 20 years. She was elected mayor one year ago as she is a firm believer in the need for modernization, while preserving the city’s historic buildings. She is very busy with commitments to the city’s 40,000 residents.The Heritage Director has worked at several historical sites and he has been brought in to the City Council to ensure a focus on preserving the city’s history and tourist revenue from the 20,000 annual visitors to its historic sites.The Heritage Manager reports to the Heritage Director and is responsible for monitoring whether the City is retaining its important historic buildings and any impacts modernization is having on this.The Business Opportunities Director has recently been promoted to provide a focus on improving business opportunities in Louistown. She has worked on several modernization projects at a senior level and understands the need to improve the vibrancy of the area, while meeting sustainability targets. She is keen to be involved in the LouisShopping Project in support of her role in promoting business opportunities.The members of the City Council, which has made the major planning decision to improve the vibrancy of the area and to offer increased opportunities for businesses by approving funds for the ‘Louistown is Open for Business’ (LOB) portfolio.The City Planning Officer will need to approve the design of the new LouisShopping, shopping centre. She is uncertain whether it will be possible for this major construction project to achieve its diverse goals relating to sustainability, developing business opportunities.The Regeneration Manager has led several regeneration projects in Louistown and has proved their ability to manage major construction projects. They are PRINCE2 qualified.The Regeneration Officer provides administrative services to the Regeneration Manager including maintaining a list of the department’s key stakeholders and maintaining the risk register for the department.The Sustainability Officer assisted the Sustainability Manager in collecting data to support the development of the City’s sustainability targets. She collects performance data to identify whether the City is on track to meet its sustainability targets.The Sustainability Manager has been on several courses on city modernization and has helped develop the City’s sustainability targets. They have managed several sustainability projects and are keen for the LouisShopping Project to be managed in a way that does not risk the City losing its ‘green town’ award.The Chief Technology Officer is responsible for the City’s IT strategy. Her department will be providing the specialists to ensure that the latest technology is used in the LouisShopping centre to promote shoppers as well as visitors to the centre’s restaurants and bars in the evenings.The CEO of BuildyBrick, the major contractor who will be doing much of the demolition and construction work for the LouisShopping Project.The Inspector employed by the City Council to provide an independent view that the BuildyBrick is complying with environmental and sustainability targets as well as City building regulations.The Portfolio Director for the Louistown is Open for Business (LOB) portfolio sees the LouisShopping Project as a key project in the portfolio. They believe that the success of the entire portfolio is dependent on the on-time delivery of this project, while achieving its sustainability targets.The Head of the Portfolio Office reports to the Portfolio Director and is responsible for reviewing the business cases and project plans of all projects in the Louistown is Open for Business (LOB) portfolio.The following entry has been recorded in the issue register:“It will be more difficult to ensure the security of the construction site due to its size. As a result, there may be unauthorized access to the site, leading to high levels of theft.”Is this an appropriate application of the ‘issues’ practice, and why?
A. es, because the project management team should be concerned about security on the site
B. es, because the project management team should consider the impact of the thefts on the project budget
C. o, because the project management team should record these thefts as a threat, rather than an issue
D. o, because the project management team should focus on the important issues
View answer
Correct Answer: C
Question #6
ScenarioAdditional InformationDuring the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.In financial terms, there were a total of 1, 500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.A number of alternatives were explored, including:20% discount for all repeat customers - not cost-effective and very short termA promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second yearA series of television and press advertisements was too expensiveA direct mail shot to all customers - benefit would be short termCreation of an internet website - would not suit all customersThe calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity.Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.Which 2 statements should be recorded under the Business options heading?
A. Produce a promotional calendar as a free Christmas gift to current and prospective customers
B. Use a professional photographer to create the photographs for the calendar
C. Create the photographs for the calendar internally
D. Outsource the creation of the calendar to a professional marketing company
E. Do nothing
View answer
Correct Answer: AE
Question #7
ScenarioAdditional InformationDuring the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.In financial terms, there were a total of 1, 500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.A number of alternatives were explored, including:20% discount for all repeat customers - not cost-effective and very short termA promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second yearA series of television and press advertisements was too expensiveA direct mail shot to all customers - benefit would be short termCreation of an internet website - would not suit all customersThe calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity.Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.Which 2 statements should be recorded under the Reasons heading?
A. The Marketing department believes that sending a promotional calendar to current and prospective customers will increase orders by at least 10%
B. 10% of customers have not re-ordered in this financial year
C. 1, 500 orders are expected, each with an average profit of £2k
D. The Marketing department believes that the effect of a good company image, portrayed by a successful calendar, will last into a second year
E. MNO Manufacturing is experiencing a fall in orders due in part to the increased marketing activities of its competitors
View answer
Correct Answer: BE
Question #8
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.Is this an appropriate application of the `tailor to suit the project' principle, and why?
A. Yes, because the project manager can adapt or combine PRINCE2 process to suit the project
B. Yes, because the standard course development structure should be tailored to suit the project
C. No, because a simple project should have no more than two management stages
D. No, because the standard course development structure should be applied to the project
View answer
Correct Answer: B
Question #9
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 4, a work package was authorized for the `delivered pilot courses' to be completed by the end of week 2. The `finalized materials' work package will start in week 3. Both work packages have zero tolerances, and finalizing the materials is dependent on feedback from the pilot courses.During week 1, there were some problems with the pilot courses, so at the start of week 2 the team manager rescheduled the courses to week 3, and reported this in the weekly checkpoint report as the end of week 2.Should the team manager have reported this delay previously as an issue, and why?
A. Yes, because the work package to deliver the pilot courses was forecast to exceed its time tolerance
B. Yes, because a team manager should not change the scheduled order of a work package
C. No, because the checkpoint report for week 1 should include information on any issues that occurred
D. No, because the feedback from the rescheduled courses can be used in week 4 to finalize the materials
View answer
Correct Answer: C
Question #10
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The project is now closed. The expected increase in revenue is not being achieved. It has been agreed with the team manager for the `marketing materials' that additional marketing activities will be undertaken to achieve the expected increase in revenue.Who should be responsible for monitoring the results of the marketing activities, and why?
A. Senior user, because this person is responsible for realizing the benefits post-project
B. Senior user, because this person is responsible for specifying the desired from the project
C. The team manager for the `marketing materials', because this person has the skills to demonstrate that the activities are effective
D. The team manager for the `marketing materials', because the project board is disbanded at the end of the project
View answer
Correct Answer: A
Question #11
ScenarioAdditional InformationDuring the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.In financial terms, there were a total of 1, 500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.A number of alternatives were explored, including:20% discount for all repeat customers - not cost-effective and very short termA promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second yearA series of television and press advertisements was too expensiveA direct mail shot to all customers - benefit would be short termCreation of an internet website - would not suit all customersThe calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity.Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.Which 2 statements should be recorded under the Reasons heading?
A. The Marketing department believes that sending a promotional calendar to current and prospective customers will increase orders by at least 10%
B. 10% of customers have not re-ordered in this financial year
C. 1, 500 orders are expected, each with an average profit of £2k
D. The Marketing department believes that the effect of a good company image, portrayed by a successful calendar, will last into a second year
E. MNO Manufacturing is experiencing a fall in orders due in part to the increased marketing activities of its competitors
View answer
Correct Answer: BE
Question #12
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard.He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The Health and Safety Training Project is part of a programme of strategic expansion, which is important for ABC Company's continued operation. At the end of stage 2, the estimated project costs are greater than the expected benefits in the business case. The project board has reviewed the situation and asked programme management to decide whether the project should be closed prematurely.Is this an appropriate application of the `manage by stages' principle, and why?
A. Yes, because decisions about closure should be escalated to programme management, unless otherwise instructed
B. Yes, because the project board should escalate significant decisions to programme management
C. No, because this contradicts the `manage by exception' principle
D. No, because the project board should decide whether to continue with the project
View answer
Correct Answer: A
Question #13
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The project is at the start of stage 3, and there will be six teams working on product delivery. In order to exercise control, the project manager has asked each team to submit a detailed team plan for approval. The external team manager for the `e-learning course' has agreed to submit a summary to the project manager, but will submit the detailed team plan to the senior supplier to review and approve.Is the team manager's response appropriate, and why?
A. Yes, because a supplier may want to keep the details of the specialist work confidential
B. Yes, because team plans are mandatory on a project of this size and complexity
C. No, because the project manager needs detailed plans to manage the work of several teams
D. No, because the team plan must be submitted to project assurance to check it is viable
View answer
Correct Answer: C
Question #14
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.One of the senior managers of the company that is developing the `e-learning course' has worked with ABC Company before. The team manager for the delivery of the `e-learning course' has looked on ABC Company's intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project.Is this an appropriate application of the `learn from experience' principle, and why?
A. Yes, because the project involves more than one organization
B. Yes, because the team manager should actively look for useful information
C. No, because the senior manager should advise the team manager of any lessons
D. No, because every project is unique and should deliver specific business objectives
View answer
Correct Answer: B
Question #15
Project Scenario – Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to developtraining materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in governmentlegislation relating to health and safety on construction sites. The project will deliver“capability to provide health and safety training”, including the materials needed forclassroom-based training and e-learning. The expected benefits for construction companiesinclude a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materialsfor classroom-based training will be delivered by ABC Company’s development team. Allcourse materials will be piloted before they are used. ABC Company will deliver training toits customers and also hopes to sell the course materials to other training companies as part oftheir operational business. ABC Company will use their own sales and marketingdepartments to promote the courses.The legislation requires construction companies to comply with the new legislation withintwo years. The course materials and trainers have to be accredited by a government agencybefore courses can be delivered. ABC Company is planning to deliver pilot courses withinfive months of starting the project.The ABC Company standard development model for new courses recommends the followingstages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under herleadership, ABC Company has grown quickly into a successful training company. It deliversa range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible forauthorizing budgets for the Operations and Development Teams. She authorizes all largecontracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing andmonitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the trainingdevelopment budget. His department organizes courses, venues and trainers. They work withthe Product and the Sales teams to provide a comprehensive training schedule. ABCCompany’s IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new trainingneeds and propose new products. She will work with the Operations. Director to ensure acost-conscious approach and that appropriate development technologies are used for thehealth and safety course.The Training Development Manager reports to the Business Development Director and isresponsible for developing training materials and gaining accreditation, in accordance withthe standard course development model. Course developers in his team have skills in a rangeof development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible forensuring that internal and external trainers deliver ABC Company training courses to therequired standard. He also checks course materials to ensure they are fit for purpose and ofthe required quality.The Central Services Director has responsibility for corporate communications, facilitiesmanagement and configuration management. He recently led a project to consolidate allcompany quality systems into one quality management system and set up a corporate qualitydepartment, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helpedestablish the company’s document management system and now operates it across thebusiness. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself bysuggesting new markets for the courses and material. All account managers and themarketing team report to him. They promote existing training courses to other trainingcompanies and existing customers.End of the additional information.In order for ABC Company to achieve the expected sales of the health and safety trainingcourse, the senior user will need to ensure that all staff understand the objectives and targetaudience for the course. In addition, these sales will need to be added to each individual’ssales targets. These activities have been included in the benefits management approach.Is this appropriate, and why?
A. es, because how the benefits will be measured needs to be documented
B. es, because the actions required to achieve the outcomes need to be documented
C. o, because the expected sales increase should be recorded in the business case
D. o, because actions to deliver the outputs should be recorded in the stage plan
View answer
Correct Answer: A
Question #16
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with theProduct and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 3, project costs are increasing but there will still be a positive return on investment, as documented in the business case. However, corporate management has recently revised its targets for return on investment and has decided to stop the project as it will not meet the new targets.Is this an appropriate application of the `continued business justification' principle?
A. Yes, because changes in corporate strategy may impact a project's justification
B. Yes, because a change in a project's justification should trigger premature closure
C. No, because the project business case still justifies a project
D. No, because changes in corporate strategy should not impact a project once authorized
View answer
Correct Answer: C
Question #17
Scenario 2: Louistown City CouncilLouistown is a historical town which is home to over 40,000 residents and attracts over 20,000 visitors per year. The city council has been criticized for the lack of investment and modernization of the town centre.They have recently decided to improve the vibrancy of the area and offer increased opportunities for business by approving the funds for the ‘Louistown is Open for Business’ (LOB) portfolio. This is an ambitious portfolio of projects covering the next five-year plan cycle.A new shopping centre, provisionally named ‘LouisShopping’, is seen as a key project within this portfolio. This is a complex infrastructure project due to the: location of the building and historical nature of the surrounding buildings requirement for the design to be consistent with the environment while offering modern facilities supported by the latest technology need to include underground parking space importance of minimizing disruption to residents and businesses during the construction works recent award of ‘green town’ status to Louistown, and the sustainability requirements this will impose on the development.Due to the nature of the work, in which just the construction element is likely to span over two financial years, the council has approved the strategic business case, the initial high-level project plan and has appointed BuildyBrick as the main contractor. They have established a requirement for a traditional delivery approach in line with their standard approach to projects. The general view is that this project is long overdue, and the council would like ‘LouisShopping’ to be open to the public by the end of financial year three.The project has just completed the initiation stage and commenced the first delivery stage (stage 2). The high-level project plan is as follows:Stage 1 (initiation)strategic business case and high-level project plan approvalappoint contractorStage 2 -designStage 3 -site preparationutilities and systemsconstructionStage 4 -testinginspectionsStage 5 -demobilization.The main output from the project is a shopping centre constructed and ready to open to the public.Additional Information -The Mayor of Louistown has worked at the city council for 20 years. She was elected mayor one year ago as she is a firm believer in the need for modernization, while preserving the city’s historic buildings. She is very busy with commitments to the city’s 40,000 residents.The Heritage Director has worked at several historical sites and he has been brought in to the City Council to ensure a focus on preserving the city’s history and tourist revenue from the 20,000 annual visitors to its historic sites.The Heritage Manager reports to the Heritage Director and is responsible for monitoring whether the City is retaining its important historic buildings and any impacts modernization is having on this.The Business Opportunities Director has recently been promoted to provide a focus on improving business opportunities in Louistown. She has worked on several modernization projects at a senior level and understands the need to improve the vibrancy of the area, while meeting sustainability targets. She is keen to be involved in the LouisShopping Project in support of her role in promoting business opportunities.The members of the City Council, which has made the major planning decision to improve the vibrancy of the area and to offer increased opportunities for businesses by approving funds for the ‘Louistown is Open for Business’ (LOB) portfolio.The City Planning Officer will need to approve the design of the new LouisShopping, shopping centre. She is uncertain whether it will be possible for this major construction project to achieve its diverse goals relating to sustainability, developing business opportunities.The Regeneration Manager has led several regeneration projects in Louistown and has proved their ability to manage major construction projects. They are PRINCE2 qualified.The Regeneration Officer provides administrative services to the Regeneration Manager including maintaining a list of the department’s key stakeholders and maintaining the risk register for the department.The Sustainability Officer assisted the Sustainability Manager in collecting data to support the development of the City’s sustainability targets. She collects performance data to identify whether the City is on track to meet its sustainability targets.The Sustainability Manager has been on several courses on city modernization and has helped develop the City’s sustainability targets. They have managed several sustainability projects and are keen for the LouisShopping Project to be managed in a way that does not risk the City losing its ‘green town’ award.The Chief Technology Officer is responsible for the City’s IT strategy. Her department will be providing the specialists to ensure that the latest technology is used in the LouisShopping centre to promote shoppers as well as visitors to the centre’s restaurants and bars in the evenings.The CEO of BuildyBrick, the major contractor who will be doing much of the demolition and construction work for the LouisShopping Project.The Inspector employed by the City Council to provide an independent view that the BuildyBrick is complying with environmental and sustainability targets as well as City building regulations.The Portfolio Director for the Louistown is Open for Business (LOB) portfolio sees the LouisShopping Project as a key project in the portfolio. They believe that the success of the entire portfolio is dependent on the on-time delivery of this project, while achieving its sustainability targets.The Head of the Portfolio Office reports to the Portfolio Director and is responsible for reviewing the business cases and project plans of all projects in the Louistown is Open for Business (LOB) portfolio.The project is at the end of stage 3 and the stage 4 plan has been produced and submitted to the project board for approval in the ‘directing a project’ process. The Portfolio Director is happy that the project is proceeding according to plan and has advised that the project management team can release funds for stages 4 and 5, without the need for further approval from the City Council or the Portfolio Board.Which role should be responsible for approving the plans for stages 4 and 5?
A. roject executive
B. usiness layer
C. enior user
D. enior supplier
View answer
Correct Answer: A
Question #18
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.Is this an appropriate application of the `tailor to suit the project' principle, and why?
A. Yes, because the project manager can adapt or combine PRINCE2 process to suit the project
B. Yes, because the standard course development structure should be tailored to suit the project
C. No, because a simple project should have no more than two management stages
D. No, because the standard course development structure should be applied to the project
View answer
Correct Answer: B
Question #19
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard.He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The Health and Safety Training Project is part of a programme of strategic expansion, which is important for ABC Company's continued operation. At the end of stage 2, the estimated project costs are greater than the expected benefits in the business case. The project board has reviewed the situation and asked programme management to decide whether the project should be closed prematurely.Is this an appropriate application of the `manage by stages' principle, and why?
A. Yes, because decisions about closure should be escalated to programme management, unless otherwise instructed
B. Yes, because the project board should escalate significant decisions to programme management
C. No, because this contradicts the `manage by exception' principle
D. No, because the project board should decide whether to continue with the project
View answer
Correct Answer: A
Question #20
ABC has experience of delivering training projects that respond to new legislation. Previous projects have had to change the acceptance criteria, due to further updates being made to legislation during the project.What action should be taken to address this, and why?
A. et the quality tolerances for the acceptance criteria in the product descriptions, because quality tolerances define the acceptable range
B. gree and prioritize the acceptance criteria during the initiation stage, because these criteria will be used to determine if the project can be closed
C. gree and prioritize the acceptance criteria during the initiation stage, because they can be amended through change control, if needed
D. et the quality tolerances for the acceptance criteria in the product descriptions, because this would allow for additional changes in legislation
View answer
Correct Answer: C
Question #21
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with theProduct and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.Is this an appropriate application of the `focus on products' principle, and why?
A. Yes, because the goal is to seek opportunities to implement improvements after the life of the project
B. Yes, because the project needs to fulfill stakeholder expectations by delivering the products required
C. No, because there needs to be an understanding of the products from the start of the project
D. No, because existing product descriptions provide a means to estimate effort to planning
View answer
Correct Answer: B
Question #22
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.In order for ABC Company to achieve the expected sales of the health and safety training course, the senior user will need to ensure that all staff understand the objectives and target audience for the course. In addition, these sales will need to be added to each individual's sales targets. These activities have been included in the benefits management approach.Is this appropriate, and why?
A. Yes, because how the benefits will be measured needs to be documented
B. Yes, because the actions required to achieve the outcomes need to be documented
C. No, because the expected sales increase should be recorded in the business case
D. No, because actions to deliver the outputs should be recorded in the stage plan
View answer
Correct Answer: A
Question #23
The change control approach defines how products should be controlled and protected during the project. The accreditation of the 'classroom-based training materials' was planned to take place during stage 2. At the end of the stage, the configuration item record shows that the 'classroom-based training materials' have been accredited. However, the project manager decides to request an audit of the product as well.Is this appropriate, and why?
A. o, because the project manager should ensure that the change control approach is tailored to the project
B. es, because the project should verify that the recorded status reflects the actual status of the products
C. es, because the change control approach should specify how the configuration item records are approved
D. o, because the issue management and change control procedures can be treated as separate, but related, procedures
View answer
Correct Answer: C
Question #24
Project Scenario - Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom- based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered.ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company' s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.ABC Company has a number of projects in progress. The executive of the Health and Safety Training Project is also a member of the project board for two other projects and is very busy. As a result, during this initiation stage, the executive has appointed another person to carry out both their business assurance and the role of change authority for minor and medium severity issues.Is this appropriate, and why?
A. es, because people with delegated project assurance roles may act as the change authority
B. o, because the decision to have a change authority should be made before the project is authorized
C. o, because the project manager identifies the level of tailoring that is relevant for the project
D. es, because projects that are likely to have many changes should delegate the change authority
View answer
Correct Answer: A
Question #25
Scenario -Additional Information -Chief Executive Officer (CEO): He started the company 25 years ago and knows his job very well. He injured his leg two years ago which has restricted his visits to the engineering area. As CEO he has an overall perspective of the business strategic requirements and the authority to commit resources as required.Marketing Director: She has been with the company for three years, following a successful career with a publicity company. She has the ability to represent the needs of the business, particularly as this is a marketing project. She has the authority to commit the annual business marketing budget, from which the project will be funded, as she sees appropriate. She will be responsible for monitoring the expected benefits of the calendar, in particular the improvement of the company's image.Engineering Manager: He has been responsible for many engineering innovations in the company and is still as keen and energetic as the day he started.VVhilst he will not be part of the project team, his staff will feature in the photos for the promotional calendar.Central Records: This group of five staff looks after all company records and document control.They now maintain all project files.Bright Lights: This is the local office supplies company. It supplies all the stationery and office equipment needs of the company and will supply the stationery for this project.Portraits ltd: This is a professional photographic company with a number of excellent photographers and a history of successful work. This company has been selected to take the photos for the company calendar. It has yet be decided which of the photographers to use.Which 2 statements explain why the Marketing Director should be appointed as a Senior User for this project?
A. he can represent the Marketing department
B. he previously had a successful career in publicity
C. he Marketing department will help to deliver the benefits of this project
D. he project will be funded from the business marketing budget
E. number of the products will be produced by the Sales department and the Marketing department
View answer
Correct Answer: AC
Question #26
ScenarioAdditional InformationDuring the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.In financial terms, there were a total of 1, 500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.A number of alternatives were explored, including:20% discount for all repeat customers - not cost-effective and very short termA promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second yearA series of television and press advertisements was too expensiveA direct mail shot to all customers - benefit would be short termCreation of an internet website - would not suit all customersThe calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity.Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.Which 2 statements should be recorded under the Business options heading?
A. Produce a promotional calendar as a free Christmas gift to current and prospective customers
B. Use a professional photographer to create the photographs for the calendar
C. Create the photographs for the calendar internally
D. Outsource the creation of the calendar to a professional marketing company
E. Do nothing
View answer
Correct Answer: AE
Question #27
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e-learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.CLOSING A PROJECTBenefits relating to income and business reputation after the project has closed cannot be shown at project closure.Which statement describes how the `closing a project' process makes provision for this?
A. As part of the `prepare planned closure' activity
B. As part of the `prepare planned closure' activity
C. As part of the `hand over products' activity, the benefits management approach will be updated to include future activities for benefit measurement
D. As part of the `hand over products' activity, the `finalized materials' will be passed to the operational business environments
View answer
Correct Answer: D
Question #28
Which of the following statements is FALSE regarding the Continued Business Justification?
A. The justification for the project must remain the same throughout the project
B. The justification for the project should remain valid
C. The justification for the project may change
D. If the project is no longer justified it should be stopped
View answer
Correct Answer: B
Question #29
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.An external consultant has signed a contract and agreed a work package to accredit the trainers. The Purchasing Manager will monitor the contract, which states the requirement to organize the accreditation with the Training Delivery Manager. The Training Delivery Manager has tried to contact the consultant but there has been no response. The project manager believes there is a risk that the consultant is prioritizing other clients' work.The Purchasing Manager has been assigned as the risk owner. Is this an appropriate approach to managing this risk, and why?
A. Yes, because the Purchasing Manager is monitoring the contract and therefore best suited to controlling the risk
B. Yes, because the Purchasing Manager should have identified the risk when the work package was agreed
C. No, because the team manager should be the risk owner to risks concerning the delivery of a work package
D. No, because the risk was transferred to the Training Delivery Manager when the work package was authorized
View answer
Correct Answer: A
Question #30
Project Scenario – Health and Safety Training Project ABC Company is a well - established training company that uses a standard model to develop training materials and deliver courses to customers. ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver “capability to provide health and safety training”, including the materials needed for classroom - based training and e - learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents. The e - learning course will be developed by a specialist external consultancy. The materials for classroom - based training will be delivered by ABC Company’s development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses. The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project. The ABC Company standard development model for new courses recommends the following stages End of the Project scenario. Additional Information The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training. The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally. The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts. The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company’s IT manager reports to the Operations Director. The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost - conscious approach and that appropriate development technologies are used for the health and safety course. The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed. The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality. The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager. The Corporate Document Manager reports to the Central Services Director. She helped establish the company’s document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high. The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers. End of the additional information. Based on lessons from previous projects that used the ABC Company standard development model, the project board has set low cost and time tolerances for stage 2. As a result, the project manager plans to set very low tolerances for time and cost for all work packages to be carried out during stage 2. Is this an appropriate application of the ‘manage by exception’ principle, and why?
A. Yes, because the project manager should set tolerance equally for all work packages in a stage
B. Yes, because setting appropriate tolerances for work packages will help keep the stage within tolerances
C. No, because tolerances set by the project manager should be the same as those set by the project board
D. No, because the project manager should divide the stage tolerances between the team managers
View answer
Correct Answer: B
Question #31
Reference Scenario: click hereAdditional Information: click hereThe following risk has been recorded in the risk register:"As the singer is new to the market, there is a threat that the music album sales will not exceed the production costs, which would result in the project no longer being viable".The record company plans to find an alternative graphic design company, to lower the overall production costs.Which risk response is being applied, and why?
A. 'Transfer the risk', because using a cheaper company transfers the threat to the third party
B. 'Transfer the risk', because using a cheaper company reduces the financial impact on the project
C. 'Reduce a threat', because the threat is being made certain by increasing the probability of it occurring
D. 'Reduce a threat', because the threat is being made less likely to occur and would have less impact
View answer
Correct Answer: D
Question #32
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with theProduct and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.Is this an appropriate application of the `focus on products' principle, and why?
A. Yes, because the goal is to seek opportunities to implement improvements after the life of the project
B. Yes, because the project needs to fulfill stakeholder expectations by delivering the products required
C. No, because there needs to be an understanding of the products from the start of the project
D. No, because existing product descriptions provide a means to estimate effort to planning
View answer
Correct Answer: B
Question #33
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The Health and Safety Training Project is closing as planned. According to the contract terms, suppliers must submit all invoices within one week of project closure. The project manager will issue a project closure notification informing all suppliers of this invoicing deadline as part of the ‘recommended project closure’ activity.Is this appropriate, and why?
A. Yes, because the project board should approve the project closure notification drafted by the project manager
B. Yes, because a project closure notification should be sent to suppliers as part of the `closing project' process
C. No, because the project board should issue a project closure notification as part of the `directing a project' process
D. No, because the project manager should notify stakeholders using the approved project closure notification
View answer
Correct Answer: B
Question #34
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The executive identified that there would be a benefit to the construction companies as their working time lost due to accidents would be reduced. This was included as a benefit to ABC Company in the business case for the Health and Safety Training Project.Is this appropriate, and why?
A. Yes, because the benefits to the customer are an essential part of business justification for a project
B. Yes, because both tangible and intangible benefits should be included in the business case
C. No, because ABC Company will not achieve their benefits if construction companies do not book the courses
D. No, because it is the customer's benefits that should be used to justify the project business case
View answer
Correct Answer: A
Question #35
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with theProduct and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.Is this an appropriate application of the `focus on products' principle, and why?
A. Yes, because the goal is to seek opportunities to implement improvements after the life of the project
B. Yes, because the project needs to fulfill stakeholder expectations by delivering the products required
C. No, because there needs to be an understanding of the products from the start of the project
D. No, because existing product descriptions provide a means to estimate effort to planning
View answer
Correct Answer: B
Question #36
ScenarioAdditional InformationDuring the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.In financial terms, there were a total of 1, 500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.A number of alternatives were explored, including:20% discount for all repeat customers - not cost-effective and very short termA promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second yearA series of television and press advertisements was too expensiveA direct mail shot to all customers - benefit would be short termCreation of an internet website - would not suit all customersThe calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity.Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.Which 2 statements should be recorded under the Reasons heading?
A. The Marketing department believes that sending a promotional calendar to current and prospective customers will increase orders by at least 10%
B. 10% of customers have not re-ordered in this financial year
C. 1, 500 orders are expected, each with an average profit of £2k
D. The Marketing department believes that the effect of a good company image, portrayed by a successful calendar, will last into a second year
E. MNO Manufacturing is experiencing a fall in orders due in part to the increased marketing activities of its competitors
View answer
Correct Answer: BE
Question #37
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The executive has set the following tolerances for stage 2:Time (+/- 1 week)Cost (+/- £20, 000)Scope (using MoSCoW prioritization technique)Risk (based on the risk appetite defined in the risk management approach)These tolerances have been recorded in the stage plan. The project manager will report progress regularly via highlight reports to the project board and use exception reports to raise exceptions. In addition, the project assurance role will monitor the stage to provide confidence to the project board that exceptions are being reported.How well does this apply the `manage by exception' principle, and why?
A. It applies the principle well, because tolerances should be set for the related aspects of project performance for each stage
B. It applies the principle well, because the project manager needs to control the project using discrete management stages
C. It applies the principle poorly, because tolerances should be set for each stage against each of the six aspects of project performance
D. It applies the principle poorly, because it is the regular reporting of progress that should give the project board the required confidence
View answer
Correct Answer: C
Question #38
When examining a project issue, which three aspects should be considered?1. Performance targets2. Business Case3. Resources4. Risk
A. , 3, 4
B. , 3, 4
C. , 2, 4
D. , 2, 3
View answer
Correct Answer: C
Question #39
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.One of the senior managers of the company that is developing the `e-learning course' has worked with ABC Company before. The team manager for the delivery of the `e-learning course' has looked on ABC Company's intranet, but cannot find any reference to this work. The team manager has contacted the senior manager to discuss this project.Is this an appropriate application of the `learn from experience' principle, and why?
A. Yes, because the project involves more than one organization
B. Yes, because the team manager should actively look for useful information
C. No, because the senior manager should advise the team manager of any lessons
D. No, because every project is unique and should deliver specific business objectives
View answer
Correct Answer: B
Question #40
Scenario 2: Louistown City CouncilLouistown is a historical town which is home to over 40,000 residents and attracts over 20,000 visitors per year. The city council has been criticized for the lack of investment and modernization of the town centre.They have recently decided to improve the vibrancy of the area and offer increased opportunities for business by approving the funds for the ‘Louistown is Open for Business’ (LOB) portfolio. This is an ambitious portfolio of projects covering the next five-year plan cycle.A new shopping centre, provisionally named ‘LouisShopping’, is seen as a key project within this portfolio. This is a complex infrastructure project due to the: location of the building and historical nature of the surrounding buildings requirement for the design to be consistent with the environment while offering modern facilities supported by the latest technology need to include underground parking space importance of minimizing disruption to residents and businesses during the construction works recent award of ‘green town’ status to Louistown, and the sustainability requirements this will impose on the development.Due to the nature of the work, in which just the construction element is likely to span over two financial years, the council has approved the strategic business case, the initial high-level project plan and has appointed BuildyBrick as the main contractor. They have established a requirement for a traditional delivery approach in line with their standard approach to projects. The general view is that this project is long overdue, and the council would like ‘LouisShopping’ to be open to the public by the end of financial year three.The project has just completed the initiation stage and commenced the first delivery stage (stage 2). The high-level project plan is as follows:Stage 1 (initiation)strategic business case and high-level project plan approvalappoint contractorStage 2 -designStage 3 -site preparationutilities and systemsconstructionStage 4 -testinginspectionsStage 5 -demobilization.The main output from the project is a shopping centre constructed and ready to open to the public.Additional Information -The Mayor of Louistown has worked at the city council for 20 years. She was elected mayor one year ago as she is a firm believer in the need for modernization, while preserving the city’s historic buildings. She is very busy with commitments to the city’s 40,000 residents.The Heritage Director has worked at several historical sites and he has been brought in to the City Council to ensure a focus on preserving the city’s history and tourist revenue from the 20,000 annual visitors to its historic sites.The Heritage Manager reports to the Heritage Director and is responsible for monitoring whether the City is retaining its important historic buildings and any impacts modernization is having on this.The Business Opportunities Director has recently been promoted to provide a focus on improving business opportunities in Louistown. She has worked on several modernization projects at a senior level and understands the need to improve the vibrancy of the area, while meeting sustainability targets. She is keen to be involved in the LouisShopping Project in support of her role in promoting business opportunities.The members of the City Council, which has made the major planning decision to improve the vibrancy of the area and to offer increased opportunities for businesses by approving funds for the ‘Louistown is Open for Business’ (LOB) portfolio.The City Planning Officer will need to approve the design of the new LouisShopping, shopping centre. She is uncertain whether it will be possible for this major construction project to achieve its diverse goals relating to sustainability, developing business opportunities.The Regeneration Manager has led several regeneration projects in Louistown and has proved their ability to manage major construction projects. They are PRINCE2 qualified.The Regeneration Officer provides administrative services to the Regeneration Manager including maintaining a list of the department’s key stakeholders and maintaining the risk register for the department.The Sustainability Officer assisted the Sustainability Manager in collecting data to support the development of the City’s sustainability targets. She collects performance data to identify whether the City is on track to meet its sustainability targets.The Sustainability Manager has been on several courses on city modernization and has helped develop the City’s sustainability targets. They have managed several sustainability projects and are keen for the LouisShopping Project to be managed in a way that does not risk the City losing its ‘green town’ award.The Chief Technology Officer is responsible for the City’s IT strategy. Her department will be providing the specialists to ensure that the latest technology is used in the LouisShopping centre to promote shoppers as well as visitors to the centre’s restaurants and bars in the evenings.The CEO of BuildyBrick, the major contractor who will be doing much of the demolition and construction work for the LouisShopping Project.The Inspector employed by the City Council to provide an independent view that the BuildyBrick is complying with environmental and sustainability targets as well as City building regulations.The Portfolio Director for the Louistown is Open for Business (LOB) portfolio sees the LouisShopping Project as a key project in the portfolio. They believe that the success of the entire portfolio is dependent on the on-time delivery of this project, while achieving its sustainability targets.The Head of the Portfolio Office reports to the Portfolio Director and is responsible for reviewing the business cases and project plans of all projects in the Louistown is Open for Business (LOB) portfolio.PROCESSES -The project is in the ‘starting up a project’ process. BuildyBrick has been appointed as the main contractor to do the demolition and construction work and it has been decided that they will be represented on the project board.Which practice is being applied in the ‘starting up a project’ process when making this decision?
A. ssues
B. rganizing
C. usiness case
D. uality
View answer
Correct Answer: B
Question #41
ScenarioAdditional InformationDuring the initiation stage the Project Manager met with the Marketing Director to find out more about the requirements of the promotional calendar and recorded the following notes:There has been a reduction in the order numbers at the MNO Manufacturing due in part to the increased marketing activities of its competitors. 10% of customers have not re-ordered in this financial year and staff morale is poor. A number of skilled staff have left as a result and replacement staff have not been recruited due to the reduced operation. If the project is successful, a recruitment campaign will be required to fill the existing staff vacancies and there may be a requirement for additional staff. Operational costs are likely to increase because skilled staff are expensive and difficult to find.In financial terms, there were a total of 1, 500 orders in the last financial year, each with an average profit of £2k. The Marketing department believes that sending a promotional calendar to our current and prospective customers would increase orders by at least 10% with a minimum of 10 further orders from the list of prospective customers within 12 months from the date of distribution.The Marketing Director will be funding the project from the business marketing budget. She believes that the effect of a good company image portrayed by a successful calendar would last into a second year. She has forecast the same increase in orders for a second year and predicts that the annual employee satisfaction survey will show a measurable improvement in staff morale.A number of alternatives were explored, including:20% discount for all repeat customers - not cost-effective and very short termA promotional calendar as a free Christmas gift - would target current and prospective customers and the benefits would last into a second yearA series of television and press advertisements was too expensiveA direct mail shot to all customers - benefit would be short termCreation of an internet website - would not suit all customersThe calendar is seen as the favored option, as long as the company's competitors do not increase their marketing activity.Whilst the Marketing department wants a very high quality, glossy product, the project management team must be aware of the cost this will incur.Using the Project Scenario and the additional Information provided for this question In the Scenario Booklet, answer the following question.Which 2 statements should be recorded under the Business options heading?
A. Produce a promotional calendar as a free Christmas gift to current and prospective customers
B. Use a professional photographer to create the photographs for the calendar
C. Create the photographs for the calendar internally
D. Outsource the creation of the calendar to a professional marketing company
E. Do nothing
View answer
Correct Answer: AE
Question #42
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard.He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.The external team manager for the `e-learning course' has reviewed the quality register to ensure all quality activities have been completed. The `e-learning course' has been approved and accreditation has been achieved. As a result, the team manager updated the work package to notify the project manager that it is complete, and updated the team plan.Is this appropriate, and why?
A. Yes, because the project manager needs to receive confirmation that work has been completed and approved
B. Yes, because a team plan to gain accreditation of the `e-learning course' is required to be part of the work package
C. No, because it is the configuration item record of the relevant product description that is updated, not the work package
D. No, because the work package should be checked to confirm the reporting arrangements of the `e- learning course'
View answer
Correct Answer: A
Question #43
Project Scenario – Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to developtraining materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in governmentlegislation relating to health and safety on construction sites. The project will deliver“capability to provide health and safety training”, including the materials needed forclassroom-based training and e-learning. The expected benefits for construction companiesinclude a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materialsfor classroom-based training will be delivered by ABC Company’s development team. Allcourse materials will be piloted before they are used. ABC Company will deliver training toits customers and also hopes to sell the course materials to other training companies as part oftheir operational business. ABC Company will use their own sales and marketingdepartments to promote the courses.The legislation requires construction companies to comply with the new legislation withintwo years. The course materials and trainers have to be accredited by a government agencybefore courses can be delivered. ABC Company is planning to deliver pilot courses withinfive months of starting the project.The ABC Company standard development model for new courses recommends the followingstages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under herleadership, ABC Company has grown quickly into a successful training company. It deliversa range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible forauthorizing budgets for the Operations and Development Teams. She authorizes all largecontracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing andmonitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the trainingdevelopment budget. His department organizes courses, venues and trainers. They work withthe Product and the Sales teams to provide a comprehensive training schedule. ABCCompany’s IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new trainingneeds and propose new products. She will work with the Operations. Director to ensure acost-conscious approach and that appropriate development technologies are used for thehealth and safety course.The Training Development Manager reports to the Business Development Director and isresponsible for developing training materials and gaining accreditation, in accordance withthe standard course development model. Course developers in his team have skills in a rangeof development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible forensuring that internal and external trainers deliver ABC Company training courses to therequired standard. He also checks course materials to ensure they are fit for purpose and ofthe required quality.The Central Services Director has responsibility for corporate communications, facilitiesmanagement and configuration management. He recently led a project to consolidate allcompany quality systems into one quality management system and set up a corporate qualitydepartment, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helpedestablish the company’s document management system and now operates it across thebusiness. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself bysuggesting new markets for the courses and material. All account managers and themarketing team report to him. They promote existing training courses to other trainingcompanies and existing customers.End of the additional information.MANAGING PRODUCT DELIVERYThe team manager for the production of the ‘marketing materials’ has identified that theywill not be ready within the timescale agreed in the work package. The team manager hassufficient tolerance to take corrective action. As a result, additional resources have beenassigned to this work package.Which theme is being applied?
A. isk
B. rganization
C. rogress
D. hange
View answer
Correct Answer: A
Question #44
Scenario 2: Louistown City CouncilLouistown is a historical town which is home to over 40,000 residents and attracts over 20,000 visitors per year. The city council has been criticized for the lack of investment and modernization of the town centre.They have recently decided to improve the vibrancy of the area and offer increased opportunities for business by approving the funds for the ‘Louistown is Open for Business’ (LOB) portfolio. This is an ambitious portfolio of projects covering the next five-year plan cycle.A new shopping centre, provisionally named ‘LouisShopping’, is seen as a key project within this portfolio. This is a complex infrastructure project due to the: location of the building and historical nature of the surrounding buildings requirement for the design to be consistent with the environment while offering modern facilities supported by the latest technology need to include underground parking space importance of minimizing disruption to residents and businesses during the construction works recent award of ‘green town’ status to Louistown, and the sustainability requirements this will impose on the development.Due to the nature of the work, in which just the construction element is likely to span over two financial years, the council has approved the strategic business case, the initial high-level project plan and has appointed BuildyBrick as the main contractor. They have established a requirement for a traditional delivery approach in line with their standard approach to projects. The general view is that this project is long overdue, and the council would like ‘LouisShopping’ to be open to the public by the end of financial year three.The project has just completed the initiation stage and commenced the first delivery stage (stage 2). The high-level project plan is as follows:Stage 1 (initiation)strategic business case and high-level project plan approvalappoint contractorStage 2 -designStage 3 -site preparationutilities and systemsconstructionStage 4 -testinginspectionsStage 5 -demobilization.The main output from the project is a shopping centre constructed and ready to open to the public.Additional Information -The Mayor of Louistown has worked at the city council for 20 years. She was elected mayor one year ago as she is a firm believer in the need for modernization, while preserving the city’s historic buildings. She is very busy with commitments to the city’s 40,000 residents.The Heritage Director has worked at several historical sites and he has been brought in to the City Council to ensure a focus on preserving the city’s history and tourist revenue from the 20,000 annual visitors to its historic sites.The Heritage Manager reports to the Heritage Director and is responsible for monitoring whether the City is retaining its important historic buildings and any impacts modernization is having on this.The Business Opportunities Director has recently been promoted to provide a focus on improving business opportunities in Louistown. She has worked on several modernization projects at a senior level and understands the need to improve the vibrancy of the area, while meeting sustainability targets. She is keen to be involved in the LouisShopping Project in support of her role in promoting business opportunities.The members of the City Council, which has made the major planning decision to improve the vibrancy of the area and to offer increased opportunities for businesses by approving funds for the ‘Louistown is Open for Business’ (LOB) portfolio.The City Planning Officer will need to approve the design of the new LouisShopping, shopping centre. She is uncertain whether it will be possible for this major construction project to achieve its diverse goals relating to sustainability, developing business opportunities.The Regeneration Manager has led several regeneration projects in Louistown and has proved their ability to manage major construction projects. They are PRINCE2 qualified.The Regeneration Officer provides administrative services to the Regeneration Manager including maintaining a list of the department’s key stakeholders and maintaining the risk register for the department.The Sustainability Officer assisted the Sustainability Manager in collecting data to support the development of the City’s sustainability targets. She collects performance data to identify whether the City is on track to meet its sustainability targets.The Sustainability Manager has been on several courses on city modernization and has helped develop the City’s sustainability targets. They have managed several sustainability projects and are keen for the LouisShopping Project to be managed in a way that does not risk the City losing its ‘green town’ award.The Chief Technology Officer is responsible for the City’s IT strategy. Her department will be providing the specialists to ensure that the latest technology is used in the LouisShopping centre to promote shoppers as well as visitors to the centre’s restaurants and bars in the evenings.The CEO of BuildyBrick, the major contractor who will be doing much of the demolition and construction work for the LouisShopping Project.The Inspector employed by the City Council to provide an independent view that the BuildyBrick is complying with environmental and sustainability targets as well as City building regulations.The Portfolio Director for the Louistown is Open for Business (LOB) portfolio sees the LouisShopping Project as a key project in the portfolio. They believe that the success of the entire portfolio is dependent on the on-time delivery of this project, while achieving its sustainability targets.The Head of the Portfolio Office reports to the Portfolio Director and is responsible for reviewing the business cases and project plans of all projects in the Louistown is Open for Business (LOB) portfolio.During excavation for the underground parking space, a water pipe was damaged. The City Council repaired the pipe, however some rework of the parking space will be required, but this will have no impact on the schedule and cost of the stage and other work packages within the stage. This rework will take an extra 3 days. The plan needs to be updated to include the rework, which will still finish within the timescales defined in the work package.According to the ‘plans’ practice, which role should update the plan?
A. roject executive
B. enior user
C. roject manager
D. eam manager
View answer
Correct Answer: D
Question #45
Scenario 2: Louistown City CouncilLouistown is a historical town which is home to over 40,000 residents and attracts over 20,000 visitors per year. The city council has been criticized for the lack of investment and modernization of the town centre.They have recently decided to improve the vibrancy of the area and offer increased opportunities for business by approving the funds for the ‘Louistown is Open for Business’ (LOB) portfolio. This is an ambitious portfolio of projects covering the next five-year plan cycle.A new shopping centre, provisionally named ‘LouisShopping’, is seen as a key project within this portfolio. This is a complex infrastructure project due to the: location of the building and historical nature of the surrounding buildings requirement for the design to be consistent with the environment while offering modern facilities supported by the latest technology need to include underground parking space importance of minimizing disruption to residents and businesses during the construction works recent award of ‘green town’ status to Louistown, and the sustainability requirements this will impose on the development.Due to the nature of the work, in which just the construction element is likely to span over two financial years, the council has approved the strategic business case, the initial high-level project plan and has appointed BuildyBrick as the main contractor. They have established a requirement for a traditional delivery approach in line with their standard approach to projects. The general view is that this project is long overdue, and the council would like ‘LouisShopping’ to be open to the public by the end of financial year three.The project has just completed the initiation stage and commenced the first delivery stage (stage 2). The high-level project plan is as follows:Stage 1 (initiation)strategic business case and high-level project plan approvalappoint contractorStage 2 -designStage 3 -site preparationutilities and systemsconstructionStage 4 -testinginspectionsStage 5 -demobilization.The main output from the project is a shopping centre constructed and ready to open to the public.Additional Information -The Mayor of Louistown has worked at the city council for 20 years. She was elected mayor one year ago as she is a firm believer in the need for modernization, while preserving the city’s historic buildings. She is very busy with commitments to the city’s 40,000 residents.The Heritage Director has worked at several historical sites and he has been brought in to the City Council to ensure a focus on preserving the city’s history and tourist revenue from the 20,000 annual visitors to its historic sites.The Heritage Manager reports to the Heritage Director and is responsible for monitoring whether the City is retaining its important historic buildings and any impacts modernization is having on this.The Business Opportunities Director has recently been promoted to provide a focus on improving business opportunities in Louistown. She has worked on several modernization projects at a senior level and understands the need to improve the vibrancy of the area, while meeting sustainability targets. She is keen to be involved in the LouisShopping Project in support of her role in promoting business opportunities.The members of the City Council, which has made the major planning decision to improve the vibrancy of the area and to offer increased opportunities for businesses by approving funds for the ‘Louistown is Open for Business’ (LOB) portfolio.The City Planning Officer will need to approve the design of the new LouisShopping, shopping centre. She is uncertain whether it will be possible for this major construction project to achieve its diverse goals relating to sustainability, developing business opportunities.The Regeneration Manager has led several regeneration projects in Louistown and has proved their ability to manage major construction projects. They are PRINCE2 qualified.The Regeneration Officer provides administrative services to the Regeneration Manager including maintaining a list of the department’s key stakeholders and maintaining the risk register for the department.The Sustainability Officer assisted the Sustainability Manager in collecting data to support the development of the City’s sustainability targets. She collects performance data to identify whether the City is on track to meet its sustainability targets.The Sustainability Manager has been on several courses on city modernization and has helped develop the City’s sustainability targets. They have managed several sustainability projects and are keen for the LouisShopping Project to be managed in a way that does not risk the City losing its ‘green town’ award.The Chief Technology Officer is responsible for the City’s IT strategy. Her department will be providing the specialists to ensure that the latest technology is used in the LouisShopping centre to promote shoppers as well as visitors to the centre’s restaurants and bars in the evenings.The CEO of BuildyBrick, the major contractor who will be doing much of the demolition and construction work for the LouisShopping Project.The Inspector employed by the City Council to provide an independent view that the BuildyBrick is complying with environmental and sustainability targets as well as City building regulations.The Portfolio Director for the Louistown is Open for Business (LOB) portfolio sees the LouisShopping Project as a key project in the portfolio. They believe that the success of the entire portfolio is dependent on the on-time delivery of this project, while achieving its sustainability targets.The Head of the Portfolio Office reports to the Portfolio Director and is responsible for reviewing the business cases and project plans of all projects in the Louistown is Open for Business (LOB) portfolio.The project is in the ‘initiating a project’ process. The LouisShopping Project is part of the ‘Louistown Open for Business’ (LOB) portfolio. The LouisShopping Project needs to comply with the portfolio’s information strategy. As a result, the project manager has recommended that the project’s digital and data management approach should be based on the portfolios information strategy with a few adaptations to suit the project’s needs.In which activity of the ‘initiating a project’ process should this recommendation be approved?
A. equest project authorization
B. gree the management approaches
C. stablish project controls
D. repare the project plan
View answer
Correct Answer: B
Question #46
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with theProduct and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 3, the operational staff that handle course bookings asked for the project scope to be increased for an online booking function. The additional product has been as it will enable them to process bookings more quickly and accurately.Is this an appropriate application of the `focus on products' principle, and why?
A. Yes, because the goal is to seek opportunities to implement improvements after the life of the project
B. Yes, because the project needs to fulfill stakeholder expectations by delivering the products required
C. No, because there needs to be an understanding of the products from the start of the project
D. No, because existing product descriptions provide a means to estimate effort to planning
View answer
Correct Answer: B
Question #47
Scenario 2: Louistown City CouncilLouistown is a historical town which is home to over 40,000 residents and attracts over 20,000 visitors per year. The city council has been criticized for the lack of investment and modernization of the town centre.They have recently decided to improve the vibrancy of the area and offer increased opportunities for business by approving the funds for the ‘Louistown is Open for Business’ (LOB) portfolio. This is an ambitious portfolio of projects covering the next five-year plan cycle.A new shopping centre, provisionally named ‘LouisShopping’, is seen as a key project within this portfolio. This is a complex infrastructure project due to the: location of the building and historical nature of the surrounding buildings requirement for the design to be consistent with the environment while offering modern facilities supported by the latest technology need to include underground parking space importance of minimizing disruption to residents and businesses during the construction works recent award of ‘green town’ status to Louistown, and the sustainability requirements this will impose on the development.Due to the nature of the work, in which just the construction element is likely to span over two financial years, the council has approved the strategic business case, the initial high-level project plan and has appointed BuildyBrick as the main contractor. They have established a requirement for a traditional delivery approach in line with their standard approach to projects. The general view is that this project is long overdue, and the council would like ‘LouisShopping’ to be open to the public by the end of financial year three.The project has just completed the initiation stage and commenced the first delivery stage (stage 2). The high-level project plan is as follows:Stage 1 (initiation)strategic business case and high-level project plan approvalappoint contractorStage 2 -designStage 3 -site preparationutilities and systemsconstructionStage 4 -testinginspectionsStage 5 -demobilization.The main output from the project is a shopping centre constructed and ready to open to the public.Additional Information -The Mayor of Louistown has worked at the city council for 20 years. She was elected mayor one year ago as she is a firm believer in the need for modernization, while preserving the city’s historic buildings. She is very busy with commitments to the city’s 40,000 residents.The Heritage Director has worked at several historical sites and he has been brought in to the City Council to ensure a focus on preserving the city’s history and tourist revenue from the 20,000 annual visitors to its historic sites.The Heritage Manager reports to the Heritage Director and is responsible for monitoring whether the City is retaining its important historic buildings and any impacts modernization is having on this.The Business Opportunities Director has recently been promoted to provide a focus on improving business opportunities in Louistown. She has worked on several modernization projects at a senior level and understands the need to improve the vibrancy of the area, while meeting sustainability targets. She is keen to be involved in the LouisShopping Project in support of her role in promoting business opportunities.The members of the City Council, which has made the major planning decision to improve the vibrancy of the area and to offer increased opportunities for businesses by approving funds for the ‘Louistown is Open for Business’ (LOB) portfolio.The City Planning Officer will need to approve the design of the new LouisShopping, shopping centre. She is uncertain whether it will be possible for this major construction project to achieve its diverse goals relating to sustainability, developing business opportunities.The Regeneration Manager has led several regeneration projects in Louistown and has proved their ability to manage major construction projects. They are PRINCE2 qualified.The Regeneration Officer provides administrative services to the Regeneration Manager including maintaining a list of the department’s key stakeholders and maintaining the risk register for the department.The Sustainability Officer assisted the Sustainability Manager in collecting data to support the development of the City’s sustainability targets. She collects performance data to identify whether the City is on track to meet its sustainability targets.The Sustainability Manager has been on several courses on city modernization and has helped develop the City’s sustainability targets. They have managed several sustainability projects and are keen for the LouisShopping Project to be managed in a way that does not risk the City losing its ‘green town’ award.The Chief Technology Officer is responsible for the City’s IT strategy. Her department will be providing the specialists to ensure that the latest technology is used in the LouisShopping centre to promote shoppers as well as visitors to the centre’s restaurants and bars in the evenings.The CEO of BuildyBrick, the major contractor who will be doing much of the demolition and construction work for the LouisShopping Project.The Inspector employed by the City Council to provide an independent view that the BuildyBrick is complying with environmental and sustainability targets as well as City building regulations.The Portfolio Director for the Louistown is Open for Business (LOB) portfolio sees the LouisShopping Project as a key project in the portfolio. They believe that the success of the entire portfolio is dependent on the on-time delivery of this project, while achieving its sustainability targets.The Head of the Portfolio Office reports to the Portfolio Director and is responsible for reviewing the business cases and project plans of all projects in the Louistown is Open for Business (LOB) portfolio.PRINCIPLES -BuildyBrick was pleased to be appointed as the main contractor for the shopping centre because it anticipates making a profit on the contract. BuildyBrick was appointed by the Council because it had been awarded with a number of industry awards for sustainability. As a result, the project manager worked closely with BuildyBrick’s sustainability consultant to incorporate some of their standards and procedures into the project’s quality management approach during the ‘initiating a project’ process. This is to ensure that the Counsil’s sustainability targets are met during the shopping centre build.Why is this action by the project manager a good application of the ‘tailor to suit the project’ principle?
A. ecause the project manager should monitor sustainability tolerance to ensure the Council’s sustainability targets are met
B. ecause BuildyBrick’s sustainability standards and procedures need to work with the projects approach to quality management
C. ecause BuildyBrick should ensure that the project is justified from their perspective and that they will make a profit
D. ecause the project manager should agree with the BuildyBrick how they will both assess the impact of requests for change on business justification
View answer
Correct Answer: B
Question #48
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with the Product and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.ABC Company has a standard course development model with four defined stages that the company manages using PRINCE2. The project manager for the Health and Safety Training Project has recommended the stage 2 of the standard model be split into two separate stages. As a result, there will now be five management stages in the project.Is this an appropriate application of the `tailor to suit the project' principle, and why?
A. Yes, because the project manager can adapt or combine PRINCE2 process to suit the project
B. Yes, because the standard course development structure should be tailored to suit the project
C. No, because a simple project should have no more than two management stages
D. No, because the standard course development structure should be applied to the project
View answer
Correct Answer: B
Question #49
Project Scenario ­ Health and Safety Training Project:ABC Company is a well-established training company that uses a standard model to develop training materials and deliver courses to customers.ABC Company has commissioned a project in response to recent changes in government legislation relating to health and safety on construction sites. The project will deliver "capability to provide health and safety training", including the materials needed for classroom-based training and e- learning. The expected benefits for construction companies include a reduction in lost days and legal costs due to accidents.The e-learning course will be developed by a specialist external consultancy. The materials for classroom-based training will be delivered by ABC Company's development team. All course materials will be piloted before they are used. ABC Company will deliver training to its customers and also hopes to sell the course materials to other training companies as part of their operational business. ABC Company will use their own sales and marketing departments to promote the courses.The legislation requires construction companies to comply with the new legislation within two years. The course materials and trainers have to be accredited by a government agency before courses can be delivered. ABC Company is planning to deliver pilot courses within five months of starting the project.The ABC Company standard development model for new courses recommends the following stages:End of the Project scenario.Additional Information:The Chief Executive Officer (CEO) founded the company five years ago. Under her leadership, ABC Company has grown quickly into a successful training company. It delivers a range of accredited professional training.The Finance Director is also a founder member of ABC Company and is responsible for authorizing budgets for the Operations and Development Teams. She authorizes all large contracts personally.The Purchasing Manager reports to the Finance Director and is responsible for managing and monitoring supplier contracts.The Operations Director is responsible for the delivery off all training and for the training development budget. His department organizes courses, venues and trainers. They work with theProduct and the Sales teams to provide a comprehensive training schedule. ABC Company's IT manager reports to the Operations Director.The Business Development Director has recently been appointed to identify new training needs and propose new products. She will work with the Operations. Director to ensure a cost-conscious approach and that appropriate development technologies are used for the health and safety course.The Training Development Manager reports to the Business Development Director and is responsible for developing training materials and gaining accreditation, in accordance with the standard course development model. Course developers in his team have skills in a range of development technologies and are allocated to projects as needed.The Training Delivery Manager, who reports to the Operations Director, is responsible for ensuring that internal and external trainers deliver ABC Company training courses to the required standard. He also checks course materials to ensure they are fit for purpose and of the required quality.The Central Services Director has responsibility for corporate communications, facilities management and configuration management. He recently led a project to consolidate all company quality systems into one quality management system and set up a corporate quality department, now managed by the Corporate Quality Manager.The Corporate Document Manager reports to the Central Services Director. She helped establish the company's document management system and now operates it across the business. She manages a team of administrators and contracts staff when workload is high.The Sales Director joined ABC Company two months ago and is keen to establish himself by suggesting new markets for the courses and material. All account managers and the marketing team report to him. They promote existing training courses to other training companies and existing customers.End of the additional information.During stage 3, project costs are increasing but there will still be a positive return on investment, as documented in the business case. However, corporate management has recently revised its targets for return on investment and has decided to stop the project as it will not meet the new targets.Is this an appropriate application of the `continued business justification' principle?
A. Yes, because changes in corporate strategy may impact a project's justification
B. Yes, because a change in a project's justification should trigger premature closure
C. No, because the project business case still justifies a project
D. No, because changes in corporate strategy should not impact a project once authorized
View answer
Correct Answer: C
Question #50
Scenario -Additional Information -Further information on some resources who could be involved in the project:Outcome Account Manager: He represents Outcome which is a recruitment agency that provides specialist outsourcing resources. Outcome provided the consultants who carried out the feasibility study and the same consultants will be providing support and guidance to the Information Technology and Facilities teams during the project.Director of Finance Division: She was transferred from the Information Technology Division 12 months ago. She is responsible for ensuring a cost-conscious approach is adopted in all operational and project activities across the Ministry of Food Hygiene.Hardware Manager: Reports to the Director of Information Technology. He provides computer hardware to all business functions but has little awareness of the needs of his colleagues working in software.Payroll Manager: Reports to the Director of Finance. He is a very experienced and efficient qualified accountant who has much of the responsibility of running theFinance Division on behalf of the Director of Finance. He has been involved in drafting the Ministry's business strategy and assisting in a full business risk assessment. He also drafted the corporate Business Case standards.Which 2 alternative actions apply to the proposed Senior User for this project?
A. etain because he provides the outsourcing resources required to support the project
B. eplace with 'Director of Research and Development' because she deals with both the Information Technology and the Facilities Divisions and can make sure her division's needs are specified
C. emove because he has no authority to commit user resources
D. dd 'Hardware Manager' because he provides computer hardware to all business functions and will be impacted by the outcome
E. etain because he will be providing support to the Information Technology and Facilities teams during the project
View answer
Correct Answer: BC

View The Updated Prince2 Exam Questions

SPOTO Provides 100% Real Prince2 Exam Questions for You to Pass Your Prince2 Exam!

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number:
Contact Us