Free PRINCE2 Agile Practitioner Practice Questions & Answers 2026 Part2

Are you preparing for the PRINCE2 PRINCE2 Agile Practitioner certification exam? SPOTO offers the PRINCE2 PRINCE2 Agile Practitioner Premium File; all questions are aligned with the latest exam content and come with expert-provided answers. Our question banks cover the latest question types, core concepts, and detailed explanations, helping you familiarize yourself with the exam format and difficulty level. Whether you are reviewing core concepts or simulating a real exam environment, these resources will rapidly boost your confidence and readiness.
For over two decades, SPOTO has successfully helped numerous IT professionals secure their ideal positions at Fortune 500 companies. Download now to start practicing efficiently and ensure a high score on the actual exam. Don't miss this opportunity to pass your certification exam with ease!
Take other online exams

Question #1
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:As a: Footballer participating in the eventI want to: Have a private cubicle to change in before my football match, without having to wait for more than 5 minutesSo that: I can be ready for the gameWhich statement explains whether the 'function' in this user story is appropriate?
A. he function is good because it contains a solution for the requirement
B. he function is good because it contains a time element that can be measured
C. he function is poor because it contains a performance element that is better suited to a technical story
D. he function is poor because it does NOT contain any prioritization of the requirement
View answer
Correct Answer: C
Question #2
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Staff Training - Additional informationThe event will be supervised primarily by LGA staff volunteers. They will need to be trained in various skills so that:- the event is carried out safely and professionally;- staff members are able to give advice on health and fitness.This is covered by four work packages:1. Training syllabus:High-level design of the manual.Content of each module.2. Course content for safety and professionalism:Detailed design of two modules:Health and Safety including basic first aid.Customer relations to look after people attending the event.Piloting the modules with a group of volunteers.3. Course content tor giving advice on health and fitness:Detailed design of two modules:Exercise fundamentals including how to warm up and cool down.Healthy eating including what types of food are good for you.Piloting the modules with a group of volunteers.4. Training delivery:Production of the training manual;Delivery of the training to the rest of the volunteers.The Staff Training Team is staffed by in-house training staff members that have been involved in several waterfall projects but have not had any exposure to agile.Using the Project Scenario and Staff Training Additional information, answer the following question:The Stall Training Team has developed the following user story:'As the LGA, I want all volunteers to have received mandatory health and safety training so that we can ensure that the event takes place in a safe environment for the public.'There is a high probability that a suitable trainer may not be available to deliver this mandatory training before the football tournament.How should this risk be managed by the Staff Training Team in accordance with the five targets?
A. et its risk tolerance to zero and agree with the project board to immediately find a suitable a trainer in order to meet the deadline
B. lex the tolerance for this risk to enable the risk to be accepted by the project board at the current level of probability
C. et a high risk tolerance in relation to this risk and monitor the situation in order to deliver on time and hit the deadline
D. emove the delivery of health and safety training from the product backlog in order to deliver on time and within the budget
View answer
Correct Answer: B
Question #3
Project scenario - Get fit with football!
A. Refer to a cumulative flow diagram to identify the status of the remaining work
B. Identify the effect of delaying the delivery of a web page in a daily stand-up
C. Visualize the status of the work using a 'ticket' board with 'swim lanes'
D. Carry out a safe-to-fail experiment to identify a better way of working
View answer
Correct Answer: C
Question #4
Which is a benefit that can be realized by a PRINCE2 organization seeking to adopt PRINCE2 Agile?
A. Comprehensive documentation is reduced as working software is a priority
B. Reduced number of roles by combining project manager with team manager
C. Lower cost of ownership throughout the life of the project's delivered product(s)
D. Improved maintenance of a business case throughout the project
View answer
Correct Answer: A
Question #5
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:A requirement for the changing room facilities in the Event Village has been defined as a technical story as follows:'Changing room facilities should have water pressure between 1.5 - 3 bar and must have a water pressure of at least between 0.1 - 0.5 bar.'Has this requirement been recorded correctly?
A. es, because a product's performance range should only appear as a technical story
B. es, because non-functional requirements may apply to more than one user story
C. o, because non-functional requirements should always be part of the user stories
D. o, because non-functional requirements should only be documented as quality criteria
View answer
Correct Answer: C
Question #6
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Website - Additional informationA new website will be built for the event. There are five work packages within this product:1. Initial homepage:2. Team Registration functionality:3. Social media promoting the event and its aims.4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.5. Health Park:The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.Using the Project Scenario and Website Additional information, answer the following question:The project has been set up with multiple teams - one for each area of delivery. Each team has its own team manager.The LGA employee who is an expert in health has been appointed to act as customer representative to all four of the delivery teams.What BEST explains how this approach tailors the organization theme?
A. It tailors the theme well because the customer representative should work full time on the project
B. It tailors the theme well because the customer representative provides specialist information to the teams
C. It tailors the theme poorly because a customer subject matter expert should provide expert knowledge on health
D. It tailors the theme poorly because each delivery team should have dedicated resources and a stable team
View answer
Correct Answer: B
Question #7
Which describes a characteristic of business as usual (BAU) work?
A. Lists of routine modifications, received regularly during the life of existing products
B. A new team selected to address a specific problem or opportunity
C. A collection of difficult tasks that are managed together
D. A delivery which is part of a larger programme of work
View answer
Correct Answer: A
Question #8
What does PRINCE2 Agile identify as a 'concept'?
A. Prioritizing what needs to be delivered
B. Trusting and not blaming others
C. Setting tolerances for each project objective to establish limits of authority
D. Using daily stand-up meetings and user stories
View answer
Correct Answer: D
Question #9
Which BEST describes an agile method or approach that can be integrated with PRINCE2 Agile?
A. Encouraging system improvement through visualization and controlling work in progress
B. Providing guidance on tailoring any applicable principles, themes and processes
C. Reducing quality testing in order to deliver within agreed deadlines
D. Favoring processes and tools over individuals and interactions
View answer
Correct Answer: A
Question #10
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Marketing - Additional informationThe marketing campaign has two key areas to promote:1. The event itself including the football tournament, event village and fundraising activities.2. The LGA's long term aim to improve the fitness of children under the age of 16.The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work.The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it.They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims.The Marketing Team is not clear on the priority to assign to the two aims for the event.The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date.Nine releases are scheduled at the end of each of the nine week-long timeboxes.The nine timeboxes within the marketing work stream are scheduled to include:Using the Project Scenario and Marketing Additional information, answer the following question:The project manager recommends that Stage 2 should be broken down further with more stage boundaries linked to the weekly publication of a newspaper advertisement.Using the Timeline, which statement BEST evaluates this proposal in relation to the 'manage by stages' principle?
A. It applies the principle well because short stage boundaries provide more opportunity for inter-team collaboration
B. It applies the principle well because short stage boundaries will enable the project to fail-fast and learn-fast
C. It applies the principle poorly because stage boundaries should be set at the beginning of each new timebox
D. It applies the principle poorly because the stage boundaries should typically be monthly on a three-month project
View answer
Correct Answer: B
Question #11
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Website - Additional informationA new website will be built for the event. There are five work packages within this product:1. Initial homepage:2. Team Registration functionality:3. Social media promoting the event and its aims.4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.5. Health Park:The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.Using the Project Scenario and Website Additional information, answer the following question:The Apps and Social Media work package includes the following requirements:1. Fitness app - Must Have2. Healthy eating app - Should HaveThe burn-down chart is showing an ever-increasing negative gap between the ideal rate of progress and what has actually been delivered. The team manager decided not to deliver the healthy eating app. However, it is still forecast that requirement 1 cannot be completed within the current timebox.The team manager escalated the issue to the project manager who instructed the team manager to immediately remove the burn-down chart from the information radiator.What BEST explains how this approach applies the 'manage by exception' principle while taking into account the PRINCE2 Agile behaviours?
A. It applies the principle well because the project manager will now decide how to proceed with the issue
B. It applies the principle well because the project manager's decision helps the Website Team self-organize within the constraints of the work package
C. It applies the principle poorly because the Website Team should be empowered to deal with issues relating to the work package
D. It applies the principle poorly because everyone in the Website Team should be aware that the work package is outside of tolerance
View answer
Correct Answer: C
Question #12
Which is consistent with the eight guidance points of PRINCE2 Agile?
A. The project manager role is NOT required when incorporating IT-only frameworks
B. The project manager role is NOT defined by Scrum or Kanban
C. Working in an agile way removes the need for a project manager
D. A project manager is indicative of a 'command and control' culture
View answer
Correct Answer: B
Question #13
Which BEST describes an agile method or approach that can be integrated with PRINCE2 Agile? This approach aligns with Agile principles, emphasizing continuous improvement and effective workflow management, which can complement the structured framework of PRINCE2 Agile.
A. Encouraging system improvement through visualization and controlling work in progress
B. Providing guidance on tailoring any applicable principles, themes and processes
C. Reducing quality testing in order to deliver within agreed deadlines
D. Favoring processes and tools over individuals and interactions
View answer
Correct Answer: A
Question #14
Which describes a characteristic of business as usual (BAU) work?
A. Lists of routine modifications, received regularly during the life of existing products
B. A new team selected to address a specific problem or opportunity
C. A collection of difficult tasks that are managed together
D. A delivery which is part of a larger programme of work
View answer
Correct Answer: A
Question #15
Project scenario - Get fit with football!
A. The AC should be delivered as a minimum viable product
B. The AC should be made transparent for maintenance by the training department
C. The AC should be met so that the cost of ownership of the materials is acceptable
D. The AC should be tested using spikes to trial the maintenance procedures
View answer
Correct Answer: C
Question #16
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Website - Additional informationA new website will be built for the event. There are five work packages within this product:1. Initial homepage:2. Team Registration functionality:3. Social media promoting the event and its aims.4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.5. Health Park:The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.Using the Project Scenario and Website Additional information, answer the following question:The project manager is creating the stage plan for Stage 3. The project manager is trying to incorporate the Team Registration work package into the stage plan.How should the stage plan be produced?
A. Using the velocity from the previous stage, working together with the Scrum Master and team members
B. By the project manager, after discussing which website user stories should be delivered
C. Using rationalism to estimate the effort to deliver the website sprints during the stage
D. By pulling website tasks from the backlog dynamically into the work package as soon as there is capacity
View answer
Correct Answer: A
Question #17
Which describes a characteristic of business as usual (BAU) work?
A. Lists of routine modifications, received regularly during the life of existing products
B. A new team selected to address a specific problem or opportunity
C. A collection of difficult tasks that are managed together
D. A delivery which is part of a larger programme of work
View answer
Correct Answer: A
Question #18
What does PRINCE2 Agile identify as a 'concept'?
A. Prioritizing what needs to be delivered
B. Trusting and not blaming others
C. Setting tolerances for each project objective to establish limits of authority
D. Using daily stand-up meetings and user stories
View answer
Correct Answer: D
Question #19
Which is a benefit that can be realized by a PRINCE2 organization seeking to adopt PRINCE2 Agile?
A. Comprehensive documentation is reduced as working software is a priority
B. Reduced number of roles by combining project manager with team manager
C. Lower cost of ownership throughout the life of the project's delivered product(s)
D. Improved maintenance of a business case throughout the project
View answer
Correct Answer: A
Question #20
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Website - Additional informationA new website will be built for the event. There are five work packages within this product:1. Initial homepage:2. Team Registration functionality:3. Social media promoting the event and its aims.4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.5. Health Park:The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.Using the Project Scenario and Website Additional information, answer the following question:The project manager has asked the Scrum Master who will be leading the website work stream to act as team manager. The team manager will act as a single point of contact for the project manager, taking on the responsibilities of a team manager. The team manager will continue to coach and lead the Website Team.Which BEST describes how this tailors the organization theme?
A. The Scrum Master should serve the Scrum team while taking on the responsibilities of a team manager
B. The project manager wants the Website Team to use fewer agile behaviours than they are currently using
C. Each person in the Website Team, including the Scrum Master, should be capable of performing multiple tasks
D. There should only be one team in a small scale project with the Website Team taking on all of the delivery roles
View answer
Correct Answer: A
Question #21
Which is a benefit that can be realized by a PRINCE2 organization seeking to adopt PRINCE2 Agile?
A. Comprehensive documentation is reduced as working software is a priority
B. Reduced number of roles by combining project manager with team manager
C. Lower cost of ownership throughout the life of the project's delivered product(s)
D. Improved maintenance of a business case throughout the project
View answer
Correct Answer: A
Question #22
Which is consistent with the eight guidance points of PRINCE2 Agile?
A. The project manager role is NOT required when incorporating IT-only frameworks
B. The project manager role is NOT defined by Scrum or Kanban
C. Working in an agile way removes the need for a project manager
D. A project manager is indicative of a 'command and control' culture
View answer
Correct Answer: B
Question #23
Project scenario - Get fit with football!
A. It applies the target well because the team manager should remove obstacles to delivery
B. It applies the target well because the relevant skills should be available for each timebox
C. It applies the target poorly because the LGA will NOT have access to the health and safety expert during Stage 3
D. It applies the target poorly because the CSME should have been added during Stage 2 to improve progress
View answer
Correct Answer: D
Question #24
Which is a benefit that can be realized by a PRINCE2 organization seeking to adopt PRINCE2 Agile?
A. Comprehensive documentation is reduced as working software is a priority
B. Reduced number of roles by combining project manager with team manager
C. Lower cost of ownership throughout the life of the project's delivered product(s)
D. Improved maintenance of a business case throughout the project
View answer
Correct Answer: A
Question #25
Project scenario - Get fit with football!
A. Handle it at the detailed level using the quality criteria in the product description for the banner
B. Treat it as an item NOT meeting the specification which the banner supplier should rectify
C. Escalate it to the project board as a request to change the detail of an existing product
D. Address it when planning and prioritizing the work in the current or next timebox
View answer
Correct Answer: D
Question #26
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:There is limited space in the Event Village to accommodate all of the equipment, e.g. the trampolines, 'kidz-zone', food tent, car park and changing rooms.It is difficult to assess whether there is sufficient space from the design drawings. One of the team has suggested physically drawing out the actual space occupied by each facility at the site.Which statement BEST describes whether this approach is a good application of the frequent releases focus area?
A. It is a good approach because a physical representation will deliver something of use to the project
B. It is a good approach because a design should be an interim stage of the Event Village work package
C. It is a poor approach because releases need to be put into operational use to receive any feedback
D. It is a poor approach because visiting the site of the Event Village is NOT classed as a sub-product
View answer
Correct Answer: A
Question #27
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:In order to assess the prevailing agile environment, the project manager made use of the Agilometer. A summary of the results from canvassing the views of key stakeholders involved in the Event Village is provided below:SliderFlexibility on what is delivered:Score 5Level of Collaboration:Score 2Ease of Communication:Score 3Ability to work iteratively and deliver incrementally:Score 4Advantageous Environmental Conditions:Score 5Acceptance of Agile:Score 3Which observation is appropriate at this point?
A. here is a need to evolve the Agilometer to better suit the needs of the project manager
B. here are likely to be too many requirements that are 'Musts Haves' to be able to use PRINCE2 Agile
C. here is a need to investigate if team members have been disappointed by working in teams before
D. he average score supports adopting Agile behaviours, concepts and techniques
View answer
Correct Answer: D
Question #28
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:It has been agreed that supervised access to the vendor stalls will only be allowed between 16:00 and 20:00 on the day before the event to allow set-up.Which is the BEST means of communicating these arrangements to all of the vendors?
A. sing visualizations in the form of diagrams and pictures
B. y e-mailing everyone and asking for confirmation of receipt
C. y telephone to discuss the arrangements with each stall holder
D. ace to face in a workshop to enable discussion
View answer
Correct Answer: B
Question #29
Which is a reason for 'blending and weaving' PRINCE2 with agile at all levels within a project?
A. rojects should be established with the intention of NOT delivering everything
B. o allow teams to self-organize whilst staying in control
C. o adjust a 'command and control' culture for product delivery
D. RINCE2 Agile is NOT a substitute for PRINCE2
View answer
Correct Answer: B
Question #30
Project scenario - Get fit with football! (Note: The companies and people within the scenario are fictional) Introduction A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres. Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support. This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited. Scope The initial scope of the project includes: The project has been set up with four work streams to deliver this work: 1. Marketing 2. Website 3. Event Village 4. Staff Training Project Background The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'. Timeline An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes. Marketing - Additional information The marketing campaign has two key areas to promote: 1. The event itself including the football tournament, event village and fundraising activities. 2. The LGA's long term aim to improve the fitness of children under the age of 16. The Marketing Team has received some initial Scrum training but is unsure how it can be applied to their marketing work. The Marketing Team is keen that the project manager provides them with a clear brief for the campaign before they spend too much time on it. They have experience of working with a variety of marketing channels, although they are not sure which channel(s) will work most effectively to promote this type of event, and in particular to promote the LGA's longer term health aims. The Marketing Team is not clear on the priority to assign to the two aims for the event. The Marketing Team will publish advertisements and/or promotional material every week, with more information in each issue to keep the message up to date. Nine releases are scheduled at the end of each of the nine week-long timeboxes. The nine timeboxes within the marketing work stream are scheduled to include: Using the Project Scenario and Marketing Additional information, answer the following question: The Marketing Team has created a plan of 9 timeboxes that always end on a Friday. The senior user has decided to visit the Marketing Team every Friday in order to attend their regular reviews. Which reason BEST explains whether this is a suitable approach for the 'directing a project' process? Regular reviews conducted by the senior user allow for continuous assessment of the project's progress, ensuring that the project remains aligned with its objectives and can adapt to any necessary changes. This ongoing engagement is vital for maintaining project viability and stakeholder involvement.
A. It is a good approach because regular reviews will provide rich information to assess project viability
B. It is a good approach because the senior user will be able to oversee the performance of the team
C. It is a poor approach because the senior user should focus on looking at the information radiator instead
D. It is a poor approach because the reviews should be scheduled as needed, when products are developed
View answer
Correct Answer: A
Question #31
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:The car park must have space for the following:30 vendor stall vehicles8 VIP visitors10 officials2 Emergency Services vehiclesWhich statement is most likely to be included in the project product description under the heading Customer's Quality Expectations?
A. here will be sufficient car parking for all event visitors and officials
B. here are 50 parking spaces available for pre-allocated parking
C. 8 'standard' parking spaces and 2 larger spaces for emergency services vehicles
D. ar parking spaces need to be 2
View answer
Correct Answer: A
Question #32
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:The Event Village Team is holding a workshop to decide how to meet the varied and often conflicting requirements for culturally diverse, healthy and quick food because several days have already been spent trying to establish the way forward. The workshop involves only the Event Village Team without the use of an independent facilitator.Which reason BEST explains why this workshop is a good application of the 'rich communication' focus area?
A. workshop can help improve team dynamics and bonding
B. workshop enables problems to be solved quickly
C. workshop will use fewer resources to resolve problems
D. workshop is run informally to enable effective face-to-face communication
View answer
Correct Answer: D
Question #33
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Website - Additional informationA new website will be built for the event. There are five work packages within this product:1. Initial homepage:2. Team Registration functionality:3. Social media promoting the event and its aims.4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.5. Health Park:The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.Using the Project Scenario and Website Additional information, answer the following question:The Scrum Master has been advised by the supplier subject matter expert that the five day task of building the social media website is now almost complete - there is just one more day's work to do.How should this be shown on the burn-down chart?
A. The work remaining should be the difference between work completed and work left to be done
B. The task should be shown as 80% complete as there is only one day's worth of effort left
C. The task should be marked as almost complete as there is less than one day's worth of effort left
D. The task should NOT be updated until the task has been completed
View answer
Correct Answer: B
Question #34
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)Introduction -A Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.Scope -The initial scope of the project includes:a marketing campaign to promote the event;a celebrity to open the event;a website to provide information about the event and handle applications; an event village to support the 'family day out'; the training of LGA staff as volunteers to run and support the event; back-office processes to handle the applications; fundraising to cover the cost of the event.The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject Background -The LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.Timeline -An initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:Refreshment stalls within a large food tent. The LGA is keen to promote the culinary diversity of the town whilst adhering to the objective of eating healthily.There are 30 vendor stalls selling products related to the event.The LGA has five stalls to promote their longer term aims and to demonstrate current and future initiatives.4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:All public events supported by the LGA must be fully accessible to all visitors.How should this requirement be recorded?
A. nder the composition heading of project product description as a Must Have requirement
B. n the project product description for the tournament as a Customer Quality Expectation
C. n a burn chart as a feature to be delivered by the team within the current timebox
D. n a user story: 'As the LGA, I want to allow access to all visitors so that everyone can attend the tournament'
View answer
Correct Answer: B
Question #35
Which is consistent with the eight guidance points of PRINCE2 Agile?
A. he project manager role is NOT required when incorporating IT-only frameworks
B. he project manager role is NOT defined by Scrum or Kanban
C. orking in an agile way removes the need for a project manager
D. project manager is indicative of a 'command and control' culture
View answer
Correct Answer: B
Question #36
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Event Village - Additional informationThe aim of the event village is to provide a range of services and activities for anyone attending the football tournament.The event village will comprise a number of work packages:1. Event village design2. A 'kids-zone' which includes trampolines and swings, as well as the opportunity to try out other sporting activities3. Stalls which will be sold to local businesses to raise funds for the event:4. A car park for 200 cars.5. Temporary facilities including changing rooms, toilets and shower facilities.6. Dismantling of the event village and clean up.The Event Village Team is assembled using staff from various LGA departments who have no experience of working with agile.Using the Project Scenario and Event Village Additional information, answer the following question:As a: Footballer participating in the eventI want to: Have a private cubicle to change in before my football match, without having to wait for more than 5 minutesSo that: I can be ready for the gameWhich statement explains whether the 'function' in this user story is appropriate?
A. The function is good because it contains a solution for the requirement
B. The function is good because it contains a time element that can be measured
C. The function is poor because it contains a performance element that is better suited to a technical story
D. The function is poor because it does NOT contain any prioritization of the requirement
View answer
Correct Answer: C
Question #37
Which is consistent with the eight guidance points of PRINCE2 Agile?
A. The project manager role is NOT required when incorporating IT-only frameworks
B. The project manager role is NOT defined by Scrum or Kanban
C. Working in an agile way removes the need for a project manager
D. A project manager is indicative of a 'command and control' culture
View answer
Correct Answer: B
Question #38
Project scenario - Get fit with football!(Note: The companies and people within the scenario are fictional)IntroductionA Local Government Authority (LGA) has decided to organize a six-a-side football tournament. The tournament will contribute towards achieving the targets set by a national initiative to improve the fitness of children under the age of 16. As part of the LGA's policy of self-funding, this has to be achieved at zero cost to the LGA (and therefore the local tax payer). The cost of the event will be covered through fees paid by teams registered to take part in the tournament, sponsorship and monies raised during the day. Any surplus would be used for the maintenance of local sports centres.Teams can register under one of several age groups for both boys and girls. In addition, family members are asked to attend to provide support.This sports event is designed to be a family day out. The football tournament will have an event village including a kidz'-zone, catering, car parking, mobile changing rooms and toilets. The tournament will take place on the LGA-owned football pitches near the centre of the town, although space is somewhat limited.ScopeThe initial scope of the project includes:The project has been set up with four work streams to deliver this work:1. Marketing2. Website3. Event Village4. Staff TrainingProject BackgroundThe LGA have extensive experience in using PRINCE2 and will run the event as a single project. The project manager is fully conversant with PRINCE2 Agile. One office in the LGA building in the centre of town has been given to the project for the entire duration. The office is across the corridor from the Marketing Department and the project manager has already put a sign on the door that says 'Mission Control'.TimelineAn initial timeline has been suggested and is shown in the following diagram. The timeline may evolve due to the agile ways of working. The timeline shows how work streams are broken down into work packages and/or timeboxes.Website - Additional informationA new website will be built for the event. There are five work packages within this product:1. Initial homepage:2. Team Registration functionality:3. Social media promoting the event and its aims.4. Applications (apps) to promote healthy lifestyles including fitness and healthy eating apps.5. Health Park:The Website Team have a lot of experience in IT and have been using agile for several years. They are delivering the website through five two-week timeboxes. The team uses a Scrum Master to facilitate and the Scrum process and coach people accordingly.The Website Team are very good at Scrum. They have created a set of tasks to assess more difficult work and they refer to this as sprint zero.Using the Project Scenario and Website Additional information, answer the following question:The Scrum Master has been advised by the supplier subject matter expert that the five day task of building the social media website is now almost complete - there is just one more day's work to do.How should this be shown on the burn-down chart?
A. The work remaining should be the difference between work completed and work left to be done
B. The task should be shown as 80% complete as there is only one day's worth of effort left
C. The task should be marked as almost complete as there is less than one day's worth of effort left
D. The task should NOT be updated until the task has been completed
View answer
Correct Answer: B
Question #39
Project scenario - Get fit with football!
A. The newspaper advertisements
B. The banners for the Event Village
C. The text and links for the website
D. The radio interview
View answer
Correct Answer: C
Question #40
Which describes a characteristic of business as usual (BAU) work?
A. Lists of routine modifications, received regularly during the life of existing products
B. A new team selected to address a specific problem or opportunity
C. A collection of difficult tasks that are managed together
D. A delivery which is part of a larger programme of work
View answer
Correct Answer: A
Question #41
Which describes a characteristic of business as usual (BAU) work?
A. ists of routine modifications, received regularly during the life of existing products
B. new team selected to address a specific problem or opportunity
C. collection of difficult tasks that are managed together
D. delivery which is part of a larger programme of work
View answer
Correct Answer: A

View The Updated Prince2 Exam Questions

SPOTO Provides 100% Real Prince2 Exam Questions for You to Pass Your Prince2 Exam!

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number:
Contact Us