Free PRINCE2 Agile Foundation Practice Questions & Answers 2026 Part3

Are you preparing for the PRINCE2 PRINCE2 Agile Foundation certification exam? SPOTO offers the PRINCE2 PRINCE2 Agile Foundation Premium File; all questions are aligned with the latest exam content and come with expert-provided answers. Our question banks cover the latest question types, core concepts, and detailed explanations, helping you familiarize yourself with the exam format and difficulty level. Whether you are reviewing core concepts or simulating a real exam environment, these resources will rapidly boost your confidence and readiness.
For over two decades, SPOTO has successfully helped numerous IT professionals secure their ideal positions at Fortune 500 companies. Download now to start practicing efficiently and ensure a high score on the actual exam. Don't miss this opportunity to pass your certification exam with ease!
Take other online exams

Question #1
What should the business case state about the minimum viable product (MVP)?
A. When the MVP will be defined
B. That the MVP must go into operational use
C. What the MVP is
D. That the MVP is the same as project viability
View answer
Correct Answer: B
Question #2
When tracking progress, which term describes using agile techniques at the delivery level, and traditional techniques at the direction and management levels?
A. referable
B. ypical
C. ffective
View answer
Correct Answer: C
Question #3
Which two statements about tailoring the business case in an agile environment are CORRECT?1. It should be unnecessary because products of the highest value will be delivered first.2. It should identify the minimum viable product and when it will be delivered.3. It should take into account that the scope may be reduced during the course of the project.4. It should show the features, the order in which they will be delivered and any dependencies.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
View answer
Correct Answer: B
Question #4
What should the business case state about the minimum viable product (MVP)?
A. When the MVP will be defined
B. That the MVP must go into operational use
C. What the MVP is
D. That the MVP is the same as project viability
View answer
Correct Answer: B
Question #5
How are user inputs FIRST gathered in the 'quality' practice?
A. As user stories in the product backlog
B. As epic user stories in the project backlog
C. As the project Definition of Done in the quality management approach
D. As a quality control activity in the quality register
View answer
Correct Answer: A
Question #6
Which statement about the `keep teams stable' target is CORRECT?
A. It applies primarily to the long term, such as a project or a program
B. It is the primary reason why the tolerance for cost is set to zero
C. It prevents compromising the overall quality level of the product
D. It results in the early delivery of a minimum viable product
View answer
Correct Answer: B
Question #7
How does the change theme regard change in PRINCE2 Agile?
A. As disruptive
B. As something to be avoided
C. As a necessity
D. As inevitable
View answer
Correct Answer: D
Question #8
Which two statements are key responsibilities of supplier representative?1. They highlight areas that the project may impact from a technical perspective.2. They are partially assigned to the delivery team.3. They create the project's specialist products.4. They prioritize requirements.
A. and 2
B. and 3
C. and 4
D. and 4
View answer
Correct Answer: D
Question #9
When tailoring PRINCE2, what does PRINCE2 Agile guidance cover?
A. How to select the Agile method
B. How to decide which themes can be ignored
C. How to map the common Agile roles to the PRINCE2 project management team structure
D. How to decide which principles are relevant
View answer
Correct Answer: C
Question #10
Which TWO are the purposes of a highlight report?1. To describe the MoSCoW priority of user stories.2. To summarize the status of a work package.3. To summarize the stage status.4. To report any potential issues and risks
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
View answer
Correct Answer: C
Question #11
Whose interests are specifically represented by the senior supplier?1. Those ensuring the project is value for money.2. Those who will use the project's products.3. Those who will be developing the project's products.4. Those responsible for the project's technical integrity.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
View answer
Correct Answer: C
Question #12
What describes essential aspects of project management that must be applied consistently and throughout the project lifecycle?
A. he project context
B. he PRINCE2 processes
C. he PRINCE2 practices
D. he people element
View answer
Correct Answer: C
Question #13
Which statement describes the Kanban approach?
A. It is used to make system improvements using visualization and by controlling work in progress
B. It is an iterative timeboxed approach that helps teams generate value
C. It was originally focused in creating new companies and is now used to speed up product delivery
D. It has defined processes, products and roles used to iteratively deliver outputs using timeboxing
View answer
Correct Answer: A
Question #14
What should be decided when configuring PRINCE2 effectively?
A. hat to remove and where to add guidance
B. here to put the emphasis and where to add guidance
C. hat to significantly change to create the right blend
D. hich areas are not enabled to work with agile
View answer
Correct Answer: C
Question #15
Which two statements about tailoring the business case in an agile environment are CORRECT?1. It should be unnecessary because products of the highest value will be delivered first.2. It should identify the minimum viable product and when it will be delivered.3. It should take into account that the scope may be reduced during the course of the project.4. It should show the features, the order in which they will be delivered and any dependencies.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
View answer
Correct Answer: B
Question #16
What should the business case state about the minimum viable product (MVP)?
A. When the MVP will be defined
B. That the MVP must go into operational use
C. What the MVP is
D. That the MVP is the same as project viability
View answer
Correct Answer: B
Question #17
Which statement explains the PRINCE2 Agile behavior of 'exploration'?
A. t empowers the project management team at the delivery level
B. t uses the most effective channel to communicate information
C. t displays the progress rate to everyone using burn-down charts
D. t seeks out feedback collaboratively from project stakeholders
View answer
Correct Answer: D
Question #18
According to PRINCE2 Agile, which form of communication shows that a team is vibrant and interactive?
A. sing visualization to display information
B. sing meeting minutes to share decisions
C. sing social media to reach more people
D. sing email to document discussions
View answer
Correct Answer: A
Question #19
To help with prioritization, what is MOST important when understanding the difference between scope and quality?
A. Combining functional and non-functional requirements
B. Creating non-functional requirements with user stories
C. Differentiating functional from non-functional requirements
D. Defining non-functional requirements before functional requirements
View answer
Correct Answer: C
Question #20
Which two statements about tailoring the business case in an agile environment are CORRECT?1. It should be unnecessary because products of the highest value will be delivered first.2. It should identify the minimum viable product and when it will be delivered.3. It should take into account that the scope may be reduced during the course of the project.4. It should show the features, the order in which they will be delivered and any dependencies.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
View answer
Correct Answer: B
Question #21
What should the business case state about the minimum viable product (MVP)?
A. When the MVP will be defined
B. That the MVP must go into operational use
C. What the MVP is
D. That the MVP is the same as project viability
View answer
Correct Answer: B
Question #22
What term is used to describe boards that display what work needs to be completed for people working on a project?
A. Work in progress limit
B. Information radiator
C. Highlight report
D. Glad! Sad! Mad!
View answer
Correct Answer: C
Question #23
Which two statements about tailoring the business case in an agile environment are CORRECT?1. It should be unnecessary because products of the highest value will be delivered first.2. It should identify the minimum viable product and when it will be delivered.3. It should take into account that the scope may be reduced during the course of the project.4. It should show the features, the order in which they will be delivered and any dependencies.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
View answer
Correct Answer: B
Question #24
Which statement about the `keep teams stable' target is CORRECT?
A. It applies primarily to the long term, such as a project or a program
B. It is the primary reason why the tolerance for cost is set to zero
C. It prevents compromising the overall quality level of the product
D. It results in the early delivery of a minimum viable product
View answer
Correct Answer: B
Question #25
During which process should release planning be done for the FIRST time?
A. nitiating a project
B. anaging a stage boundary
C. anaging product delivery
D. ontrolling a stage
View answer
Correct Answer: B
Question #26
Where there is only one delivery team involved, which statement BEST describes the synchronization of PRINCE2 and agile roles?
A. The alignment of common agile roles is less obvious
B. The alignment of common agile roles should be easy
C. The alignment of common agile roles should be avoided
D. The alignment of common agile roles is impossible
View answer
Correct Answer: B
Question #27
Which is the BEST method of communication to gather feedback?
A. eceiving emailed diagrams to encourage discussion
B. iscussing over the telephone to gather feedback quickly from stakeholders
C. eeting face-to-face to encourage an exchange of views
D. onducting online surveys to obtain a range of opinions
View answer
Correct Answer: C
Question #28
Which statement about the `keep teams stable' target is CORRECT?
A. It applies primarily to the long term, such as a project or a program
B. It is the primary reason why the tolerance for cost is set to zero
C. It prevents compromising the overall quality level of the product
D. It results in the early delivery of a minimum viable product
View answer
Correct Answer: B
Question #29
Which statement about the waterfall methodology definition is CORRECT?
A. It states that deadlines should not be moved
B. It has distinct goals for each stage of development
C. It is a behavior that involves making things transparent
D. It promotes the use of experiments carried out in a scientific way
View answer
Correct Answer: B
Question #30
Which is a benefit of the Lean Startup approach to releasing a product?
A. t provide a technique to reduce the testing of a product before release
B. t enables the release plans to be synchronized with the PRINCE2 plans
C. t reduces the number of people needed to manage a release of a product
D. t provides quick feedback that can be responded to at the earliest opportunity
View answer
Correct Answer: B
Question #31
What term is used to describe boards that display what work needs to be completed for people working on a project?
A. Work in progress limit
B. Information radiator
C. Highlight report
D. Glad! Sad! Mad!
View answer
Correct Answer: C
Question #32
Which statement about the waterfall methodology definition is CORRECT?
A. t states that deadlines should not be moved
B. t has distinct goals for each stage of development
C. t is a behavior that involves making things transparent
D. t promotes the use of experiments carried out in a scientific way
View answer
Correct Answer: B
Question #33
How are requirements typically documented during the initiation stage of the project?
A. As several hundred detailed user stories relating to product descriptions
B. Within the range of ten to a hundred product descriptions or epics
C. In a maximum of ten outline bullet points in the project product description
D. As ten very detailed user stories relating to project vision objectives
View answer
Correct Answer: B
Question #34
How does the change theme regard change in PRINCE2 Agile?
A. As disruptive
B. As something to be avoided
C. As a necessity
D. As inevitable
View answer
Correct Answer: D
Question #35
What is a purpose of the 'project closure' workshop?
A. efine the release map for the next stage
B. reate benefits management approach
C. lign teams with project vision
D. pdate the project documentation
View answer
Correct Answer: D
Question #36
In which workshop are the project role descriptions created?
A. tarting-up workshop
B. roject kickoff workshop
C. roject initiation workshop
D. roject canvas workshop
View answer
Correct Answer: A
Question #37
Which of the following is an example of 'being agile' rather than just ‘doing agile’?
A. A team of developers is working together in a common room and readily communicating with each other
B. A full Scrum team is working together on a product’s development with multiple large dashboards
C. A product owner is gathering requirements from customers and coaching them on how to write user stories
D. A customer has embraced the new iterative approach and now focuses on the requirements that add value
View answer
Correct Answer: D
Question #38
Which process can take place during a release review workshop?
A. Controlling a stage
B. Managing product delivery
C. Managing a stage boundary
D. Directing a project
View answer
Correct Answer: B

View The Updated Prince2 Exam Questions

SPOTO Provides 100% Real Prince2 Exam Questions for You to Pass Your Prince2 Exam!

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number:
Contact Us