Midway through an iteration, an agile team learns that a team member will be unavailable for the next two iterations. As a high-performance team, what should the team do? The correct answer is D -- Assume the team member's tasks to meet iteration goals and notify the Product Owner. Agile teams are self-organizing and accountable. High-performing teams take ownership of shared goals and redistribute work as needed to maintain commitment. From the PMI Agile Practice Guide: ''High-performing agile teams collaborate to deliver sprint goals, adapting to changes such as unavailability of team members. They adjust workload and communicate impacts transparently.'' (PMI Agile Practice Guide, Section 4.3 -- Team Performance and Self-Organization) Mike Griffiths explains: ''When team composition changes, the team must redistribute work to ensure delivery. Ownership, trust, and flexibility are core traits of high-performing agile teams.'' (Mike Griffiths, PMI-ACP Exam Prep, Chapter 4 -- Team Performance) Incorrect options: A signals dysfunction and abdicates team responsibility. B implies external management of team staffing. C violates the principle of self-organization.
A. Raise an impediment that resource tasks will be blocked and notify the Product Owner
B. Ask the delivery manager for a temporary resource
C. Ask the Scrum Master to assign that team member's tasks to the next available resource
D. Assume the team member's tasks to meet iteration goals and notify the Product Owner