DON'T WANT TO MISS A THING?

Certification Exam Passing Tips

Latest exam news and discount info

Curated and up-to-date by our experts

Yes, send me the newsletter

Free ASQ CQI Practice Questions & Answers 2026 Part2 | Certified Quality Inspector

Are you preparing for the ASQ CQI certification exam? SPOTO offers the ASQ CQI Premium File; all questions are aligned with the latest exam content and come with expert-provided answers. Our question banks cover the latest question types, core concepts, and detailed explanations, helping you familiarize yourself with the exam format and difficulty level. Whether you are reviewing core concepts or simulating a real exam environment, these resources will rapidly boost your confidence and readiness.
For over two decades, SPOTO has successfully helped numerous IT professionals secure their ideal positions at Fortune 500 companies. Download now to start practicing efficiently and ensure a high score on the actual exam. Don't miss this opportunity to pass your certification exam with ease!
Take other online exams

Question #1
Team progression begins with which stage when members cautiously explore boundaries of acceptable group behavior?Response:
A. torming
B. orming
C. erforming
D. orming
View answer
Correct Answer: B
Question #2
Which of the following activities may, exceptionally, be omitted for an urgent change? 1. Recording that the change has been made 2. Testing the change 3. Holding a CAB meeting 4. Establishing a back - out plan
A. All of them
B. 2 and 4
C. 2 and 3
D. 3 and 4
View answer
Correct Answer: C
Question #3
Which of these statements reflect the activities of IT Financial Management?1. IT Financial Management may calculate the prices to be charged for IT services2. IT Financial Management ensures that the IT department charges those who benefit from IT
A. Only 1
B. Only 2
C. Neither
D. 1 and 2
View answer
Correct Answer: A
Question #4
Which of the following places Problem Management activities in the correct order:
A. Identify and record, classify, investigate and diagnose, raise an RFC, review the change
B. Investigate and diagnose, raise an RFC, classify, identify and record
C. Identify and record, investigate and diagnose, raise an RFC, classify, review the change
D. Review a change, classify, identify and record, investigate and diagnose, raise another RFC
View answer
Correct Answer: A
Question #5
Why is Service Management so important to IT service providers?
A. he success of many businesses depends upon the quality of their IT
B. t's the only way to manage IT in the Internet age
C. t's contained within the IT Infrastructure Library
D. t's the first non-proprietary initiative for the management of IT systems
View answer
Correct Answer: A
Question #6
Why is Service Management so important to IT service providers?
A. The success of many businesses depends upon the quality of their IT
B. It's the only way to manage IT in the Internet age
C. It's contained within the IT Infrastructure Library
D. It's the first non-proprietary initiative for the management of IT systems
View answer
Correct Answer: A
Question #7
Which one of the following is NOT the responsibility of a Service Level Manager?
A. Analysing and reviewing agreed service levels
B. Maintaining the service catalogue
C. Negotiating requests for service
D. Assessing the full impact of proposed changes to services
View answer
Correct Answer: D
Question #8
As part of your IT Continuity Planning you have been asked to undertake a comprehensive Risk Analysis. Which of the following is most likely to be of use to you in drawing up your plan?
A. The Forward Schedule of Change, produced by Change Management
B. A Service Catalogue plus an understanding of the business criticality of each of the services
C. A list of Services and Operational Level Agreements
D. A report produced by Incident Management detailing the incidents affecting IT Services over the last month
View answer
Correct Answer: B
Question #9
Which of the following statements is INCORRECT?
A. rgent and non-urgent changes follow the same Change Management process
B. igh risk, urgent changes should be considered by the CAB Emergency Committee
C. rgent changes need not necessarily be reviewed, unless there is time to do so
D. he justification for urgent changes should always be based on sound business reasons
View answer
Correct Answer: C
Question #10
In what situation would incremental improvement be most appropriate?(Choose Two)
A. When immediate, drastic change is needed
B. When fine-tuning existing processes
C. When minimizing risk is crucial
D. When overhauling the entire system
View answer
Correct Answer: bc
Question #11
A triangle has two sides adjacent to the 90 angle that measure 6 mm and 20 mm. The length of the hypotenuse is Response:
A. 36
B. 0
C.
D. 6
View answer
Correct Answer: B
Question #12
Which of the following is least likely to be a direct benefit of implementing a formal IncidentManagement process
A. mproved user satisfaction
B. ncident volume reduction
C. limination of lost incidents
D. ess disruption to both IT support staff and users
View answer
Correct Answer: B
Question #13
At what point should capacity requirements of a proposed system be first considered?
A. eave it until the system is implemented and see if the system works O
B. s early as possible
C. hen the Development Manager has completed testing and passes the system to Operations for operational testing
D. ust before the system goes live
View answer
Correct Answer: B
Question #14
Who must always authorize a Request for Change before the change is built and tested?
A. The Configuration Manager
B. The Change Initiator
C. The Change Manager
D. Release Management
View answer
Correct Answer: C
Question #15
From a well-informed User's perspective, which of the following is a likely sequence in the management of a service failure?
A. Incident Management, Problem Management, Release Management, Change Management
B. Incident Management, Problem Management, Change Management, Release Management
C. Change Management, Incident Management, Problem Management, Release Management
D. Incident Management, Change Management, Release Management, Problem Management
View answer
Correct Answer: B
Question #16
Which of the following activities may, exceptionally, be omitted for an urgent change:1. Recording that the change has been made2. Testing the change3. Holding a CAB meeting4. Establishing a back-out plan
A. All of them
B. 2 and 4
C. 2 and 3
D. 3 and 4
View answer
Correct Answer: C
Question #17
Which of the following places Problem Management activities in the correct order:
A. Identify and record, classify, investigate and diagnose, raise an RFC, review the change
B. Investigate and diagnose, raise an RFC, classify, identify and record
C. Identify and record, investigate and diagnose, raise an RFC, classify, review the change
D. Review a change, classify, identify and record, investigate and diagnose, raise another RFC
View answer
Correct Answer: A
Question #18
Which of the following activities may, exceptionally, be omitted for an urgent change?1. Recording that the change has been made2. Testing the change3. Holding a CAB meeting4. Establishing a back-out plan
A. All of them
B. 2 and 4
C. 2 and 3
D. 3 and 4
View answer
Correct Answer: C
Question #19
Which of the following is the correct formula to calculate the mean of a data set?
A. Sum of all data points divided by the number of data points
B. The middle value of the sorted data set
C. The most frequently occurring value in the data set
D. The difference between the maximum and minimum values
View answer
Correct Answer: a
Question #20
Typically the decision on what should be the lowest level of CI recorded is influenced mostly by:
A. The reliability of the CIs
B. The level at which components will be independently changed
C. The suitability of the available software to hold the information
D. The availability of spares for CIs
View answer
Correct Answer: B
Question #21
Which of the following statements is TRUE?
A. Physical copies of all CIs are stored in the DSL
B. Release Management is responsible for managing the organisation's rights and obligations regarding software
C. The DSL contains source code only
D. A change may only be developed from non-definitive versions of software in the case of an urgent release
View answer
Correct Answer: B
Question #22
What is the total combined length of these four parts in inches expressed as a decimal 1/64 in., 2/9 in., 7/32 in., and 14/27 in?Response:
A.
B.
C.
D.
View answer
Correct Answer: D
Question #23
Which of the following best describes common cause variation?
A. Variation that is inherent in the process over time
B. Variation caused by identifiable factors
C. Variation that can be eliminated by process improvements
D. Variation due to special circumstances outside the process
View answer
Correct Answer: a
Question #24
Convert 7.85 x 105 from scientific notation to floating point notation.Response:
A. 8
B. 785
C.
D. 85 000
View answer
Correct Answer: D
Question #25
How can customer satisfaction feedback be used to drive continuous improvement?(Choose Two)
A. Ignoring negative feedback
B. Identifying areas of improvement
C. Prioritizing customer needs
D. Reducing product quality
View answer
Correct Answer: bc
Question #26
An overhead would normally be regarded as which of the following?
A. A discounted charge
B. The market price
C. An indirect cost
D. A direct cost
View answer
Correct Answer: C
Question #27
Which of the following is NOT a valid method of tuning?
A. ABalancing disc traffic
B. BMaking more efficient use of processing capacity
C. CInstalling a new server
D. DBalancing workloads
View answer
Correct Answer: C
Question #28
What is Failure Modes and Effects Analysis (FMEA) primarily used for?
A. Increasing production speed
B. Identifying potential failures and their impacts
C. Reducing employee turnover
D. Managing financial resources
View answer
Correct Answer: b
Question #29
How can Corrective Action Requests (CARs) support quality improvement?(Choose Two)
A. By identifying nonconformities and their root causes
B. By eliminating the need for future audits
C. By ensuring that corrective actions are documented and verified
D. By reducing the cost of production
View answer
Correct Answer: ac
Question #30
Which of the following definitions best describes the IT Infrastructure Library (ITIL)?
A. documented framework of proven best practices in Service Management
B. prescriptive process for managing Service Improvement Projects
C. methodology for supporting and delivering IT services
D. quality standard in managing customer relationships
View answer
Correct Answer: A
Question #31
With which of the following processes is Problem Management least likely to interface on a regular basis?
A. IT Financial Management
B. Change Management
C. Incident Management
D. Availability Management
View answer
Correct Answer: A
Question #32
Why is Service Management so important to IT service providers?
A. The success of many businesses depends upon the quality of their IT
B. It's the only way to manage IT in the Internet age
C. It's contained within the IT Infrastructure Library
D. It's the first non - proprietary initiative for the management of IT systems
View answer
Correct Answer: A
Question #33
Which of the following places Problem Management activities in the correct order:
A. dentify and record, classify, investigate and diagnose, raise an RFC, review the change
B. nvestigate and diagnose, raise an RFC, classify, identify and record
C. dentify and record, investigate and diagnose, raise an RFC, classify, review the change
D. eview a change, classify, identify and record, investigate and diagnose, raise another RFC
View answer
Correct Answer: A
Question #34
Which of the following activities may, exceptionally, be omitted for an urgent change:1. Recording that the change has been made2. Testing the change3. Holding a CAB meeting4. Establishing a back-out plan
A. All of them
B. 2 and 4
C. 2 and 3
D. 3 and 4
View answer
Correct Answer: C
Question #35
The major difference between a CMDB and an asset register is that CMDB holds information on:
A. ocumentation
B. oftware
C. he IT environment
D. elationships
View answer
Correct Answer: D
Question #36
Convert 32,000 to scientific notation.Response:
A.
B.
C. 2 x 103
D. 20 x 102
View answer
Correct Answer: A
Question #37
Which of the following activities may, exceptionally, be omitted for an urgent change?1. Recording that the change has been made2. Testing the change3. Holding a CAB meeting4. Establishing a back-out plan
A. ll of them
B. and 4
C. and 3
D. and 4
View answer
Correct Answer: C
Question #38
With which of the following processes is Problem Management least likely to interface on a regular basis?
A. T Financial Management
B. hange Management
C. ncident Management
D. vailability Management
View answer
Correct Answer: A
Question #39
During the planning stage of an audit, which of the following is typically determined?(Choose Two)
A. Audit scope and purpose
B. Corrective actions
C. Audit schedule
D. Audit findings
View answer
Correct Answer: ac
Question #40
Bilateral tolerance refers to:Response:
A. he total amount a specific dimension is permitted to vary
B. tolerance in which variation is permitted in both directions from the specified dimension
C. tolerance in which variation is permitted in one direction from the specified dimension
D. he general term applied to the category of tolerances used to control form, profile, orientation, location, and runout
View answer
Correct Answer: B
Question #41
Why is there sometimes conflict between the goals of Incident Management and those of Problem Management?
A. Because specialist support staff do not properly document the work-arounds they identify which consequently prevents the 1st line support staff from applying them the next time the incident occurs
B. Because Problem Management is often carried out by technical staff who also have operations responsibilities and who cannot allocate enough resources to problem solving
C. Because Problem Management is focusing on identifying permanent solutions and therefore the speed with which these solutions are found is of secondary importance
D. Because Problem Management staff rarely give feedback spontaneously, forcing the 1st line support staff to chase them
View answer
Correct Answer: C
Question #42
With which of the following processes is Problem Management least likely to interface on a regular basis?
A. IT Financial Management
B. Change Management
C. Incident Management
D. Availability Management
View answer
Correct Answer: A
Question #43
Why is it important to have a quality plan?(Choose Two)
A. To ensure consistent product quality
B. To increase the marketing budget
C. To meet regulatory standards
D. To boost employee morale
View answer
Correct Answer: ac
Question #44
Which of the following places Problem Management activities in the correct order:
A. Identify and record, classify, investigate and diagnose, raise an RFC, review the change
B. Investigate and diagnose, raise an RFC, classify, identify and record
C. Identify and record, investigate and diagnose, raise an RFC, classify, review the change
D. Review a change, classify, identify and record, investigate and diagnose, raise another RFC
View answer
Correct Answer: A

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number:
Contact Us