Free Sample: PMP Exam Questions and Answers for 2023

CCNA 200-301

CCNA 200-301

CCNP Enterprise

CCNP Enterprise

CCNP Security

CCNP Security

CCIE Enterprise Lab

CCIE Enterprise Lab

CCIE Security Lab

CCIE Security Lab

CCNP Service Provider

CCNP Service Provider

CCNP Data Center

CCNP Data Center

CCNP Collaboration

CCNP Collaboration

CCIE DC Lab

CCIE DC Lab

ic_r
ic_l
Free Sample: PMP Exam Questions and Answers for 2023
images

Overview of PMP Exam

The PMP, called Project Management Professional, is the exam conducted by the Project Management Institute (PMI). As we all know that PMP exam consists of 200 multiple choice questions that outline the five process groups (Initiation, Planning, Executing, Monitoring and Controlling, and Closing) and nine knowledge areas (Integration, Scope, Time, Cost, Quality, Human Resource, Communication, Risk, and Procurement).

Today, we will share some free samples of PMP exam questions and answers If  to help you understand the exam. Or you want to know more info about PMP practice tests can contact us directly. 

1. A project has a 60% chance of a $100,000 profit and a 40 percent of a US $100,000 loss. The Expected Monetary Value for the project is:

$100,000 profit

$60,000 loss

$ 20,000 profit

$40,000 loss

Answer:

Expected Monitory Value (EMV) is computed by EMV = Probability × Impact.

Compute both positive and negative values and then add them:

0.6 × $100,000 = $60,000 0.4 × $100,000 = $40,000 EMV = $60,000 - $40,000 = $20,000 profit

2. Assuming that the ends of a range of estimates are +/- 3 sigma from the mean, which of the following range estimates involves the LEAST risk?

Answer:

30 days, plus or minus 5 days

22 – 30 days

Optimistic = 26 days, most likely = 30 days, pessimistic = 33 days

Mean of 28 days

The estimate with the smallest range is less risky.

3. If a risk has a 20 percent chance of happening in a given month, and the project is expected to last five months, what is the probability that the risk event will occur during the fourth month of the project?

Answer:

Less than 1 percent

20 percent

60 percent

80 percent

4. An accepted deadline for project approaches. However, the project manager realizes only 75% percent of the work has been completed. The project manager then issues a change request. What should the change request authorize? 

Answer:

Additional resources using the contingency fund

Escalation approval to use contingency funding

Team overtime to meet schedule

Corrective action based on causes

5. The risk will be identified during which risk management process(es)?

Answer:

Perform Quantitative Risk Analysis and Identify Risks

Identify Risks and Monitor and Control Risks

Perform Qualitative Risk Analysis and Monitor and Control Risks

Identify Risks

Reference: The PMBOK® Guide, 5th Edition, Page 312, Figure 11.1

6. What is meant by RACI?

Answer:

Responsible, Accountable, Confirm, Inform

Recommended, Accountable, Consulted, Inform

Responsible, Accountant, Consulted, Inform

Responsible, Accountable, Consulted, Inform

The RACI chart is an example of the Responsibility Assignment Matrix (RAM), which shows the relationship between activities and the team members.

7. Which of the following statement is true about a Program?

Answer:

A Program is a group of related projects

A Program is a group of unrelated projects

A Program is a part of a big project

None of the above

8. The project manager meets with the project team to review lessons learned from previous projects. In what activity is the team involved?

Answer:

Performance management

Scope identification

Risk identification

Project team status meeting

9. During a bidder conference, you see that one bidder is your close friend. What should your next step be?

Answer:

You will pass some confidential info to him

You will disclose this relationship to your management

You will resign immediately from the bidding process

You will try not to give the contract to him to prove your integrity

There is a conflict of interest in this situation. You must inform your boss about this relationship.

10. If a risk event has a 90 percent chance of occurring, and the consequences will be the US $ 10,000, what does the US $9,000 represent?

Answer:

Risk value

Present value

Expected monetary value

Contingency budget

EMV = .9 X $ 10,000 = $ 9,000

11. Your construction project was damaged by an earthquake. Your contractor says that he cannot fulfill the terms of the contract due to a specific clause you both had signed the contract. He is referring to the:

Answer:

Force majeure clause

Fixed price clause

Contract obligation terms

None of the above

12. All of the following are ALWAYS inputs to the risk management process EXCEPT:

Answer:

Historical information

Lessons learned

Work breakdown structure

Project status reports

Project Status report can be an input to risk management. However, when completing risk management for the first time, you wouldn’t have the project status report yet. Therefore, the project status report is not always an input to risk management.

13. When estimating time for activities, a Project Manager should:

Answer:

Use the best guess and estimate all activities since there will be changes as the project progresses and more information becomes available

Involve people who will be doing the work to get estimates

Estimate for what the cost will allow and include buffers

None of the above

14. Risk tolerance is determined in order to help:

Answer:

The team ranks the project risks.

The project manager estimates the project.

The team schedules the project.

Management knows how other managers will act on the project.

If you know the tolerance of the stakeholders, you can predict how they might react to different situations and risk events. This information can help assign levels of risk on each work package activity.

15. You are running a project to engineer and implement a set of business processes and a software solution for customer relationship management. The project involves a large number of organizations―a major corporation and many suppliers of different sizes. During the project, you observe the effects of the differences between the companies’ corporate cultures. This leads to different expectations on how the project should be handled—as well as to frequent misunderstandings between stakeholders. Another effect is a growing degree of distrust and skepticism. What should you try first to integrate the diverse stakeholder groups?

Answer:

Focus on project work. As a project manager, you should not get distracted by big egos.

Let the problems grow further until they are obvious for all. Then escalate them.

Develop a joint quality policy for the project and seek a commitment by all organizations.

Analyze the probability and impact of the risks linked with the situation and plan how to respond to them.

SPOTO focus on online IT certification training for 17 years. We offer Cisco, CISSP, CISA, CISM, AWS, Microsoft, PMP, NPDP, Aruba and other IT exam practice tests to help candidates to prepare and pass the exam fast and easily. Hurry up to contact us to get certified now.