SPOTO's latest exam dumps on the homepage, with a 100% pass rate! SPOTO delivers authentic Cisco CCNA, CCNP study materials, CCIE Lab solutions, PMP, CISA, CISM, AWS, and Palo Alto exam dumps. Our comprehensive study materials are meticulously aligned with the latest exam objectives. With a proven track record, we have enabled thousands of candidates worldwide to pass their IT certifications on their first attempt. Over the past 20+ years, SPOTO has successfully placed numerous IT professionals in Fortune 500 companies.
Take other online exams

Question #1
The production plan relates to a firm’s financial planning because it is used to:
A. alculate standard product costs
B. etermine variable costs
C. roject payroll costs
D. dentify future cash needs
View answer
Correct Answer: D
Question #2
What have most of the values clustered near a central point with progressively fewer results occurring away from the cluster?
A. ANormal distribution
B. BFrequent distribution
C. CAverage distribution
D. DRelevant distribution
View answer
Correct Answer: A
Question #3
A work center is to process 150 units of gear shaft SG 123 on work order 333.the setup time is 1.5 hours, and the run time is 0.2 hours per piece. What is the standard time needed or run the order?
A. A31
B. B30 standard hours
C. C29
D. D28 standard hours
View answer
Correct Answer: A
Question #4
Which of the following is the characteristic to flow manufacturing?
A. Routings are variable
B. work centers are dedicated to produce a limited range of similar products
C. Materials flows from one workstation to another using some form of realistic transfer
D. Capacity is variable by the line
View answer
Correct Answer: B
Question #5
Long lead-time items with stable demand would best be supported by a supply chain:
A. Ausing a pull system
B. Blinked through an enterprise resources planning (ERP) system
C. Cdesigned to be responsive
D. Dpositioning inventory close to the consumer
View answer
Correct Answer: D
Question #6
Each active manufacturing order has a record in which file?
A. work center master file
B. work center detail file
C. shop order master file
D. shop order detail file
View answer
Correct Answer: C
Question #7
What is responsible for executing the master production schedule and the material requirements plan?
A. Production activity control
B. Production requirement plan
C. Standard production
D. Master production plan
View answer
Correct Answer: A
Question #8
An online retailer moves from delivering hard copy books to offering digital downloads only. This action may result in an increased possibility of:
A. supply delays
B. forecast inaccuracy
C. supply disruptions
D. loss of intellectual property
View answer
Correct Answer: D
Question #9
Which of the following capacity planning methods uses the master production schedule (MPS) as its primary input?
A. AResource planning
B. BRough-cut capacity planning (RCCP)
C. CFinite loading
D. DInput/output analysis
View answer
Correct Answer: B
Question #10
The overall objective of an integrated supply chain can best be described as the achievement of:
A. decreased lead time
B. increased supplier partnerships
C. an efficient flow of materials and information
D. an efficient flow of production
View answer
Correct Answer: C
Question #11
Which one of the following tools that cannot be used to evaluate feasibility of a strategy?
A. ACash flow analysis and forecasting
B. BBreak-Even analysis
C. CResource deployment analysis
D. DNone of these
View answer
Correct Answer: D
Question #12
The planning horizon is usually and is reviewed perhaps .
A. A8-12 months, each month
B. B5-8 months, each quarter
C. C6-8 months, each month or quarter
D. DNone of these
View answer
Correct Answer: C
Question #13
According to quality function deployment (QFD), customer needs are gathered through:
A. mployee suggestions
B. echnical specifications
C. urveys
D. istorical data
View answer
Correct Answer: C
Question #14
Ergonomic workstation design should incorporate:
A. an andon board
B. reduction of repetitive motion
C. bending so as to reduce monotony of work
D. visual systems
View answer
Correct Answer: B
Question #15
How would a master production schedule (MPS) be used in an assemble-to-order (ATO) manufacturing environment?
A. The MPS is used to plan subassemblies and components; end items are only scheduled when a customer order is received
B. Subassemblies are scheduled in the MPS when the customer order is received, and production can start
C. Typically, the MPS is not used in companies using an ATO manufacturing strategy
D. Often in an ATO environment, the MPS is created once a year and only revised if a product is discontinued
View answer
Correct Answer: A
Question #16
Which of the following types of operational strategies typically would result in the lowest inventory cost?
A. Mixed - model
B. Level
C. Chase
D. Hybrid
View answer
Correct Answer: C
Question #17
What is the shortest manufacturing lead time required for 10 units of Item A assuming that it must complete Operations 10, 20, and 30 in a work cell, and these operations require no set up time''?
A. A10 hours
B. B12 hours
C. C13 hours
D. D30 hours
View answer
Correct Answer: B
Question #18
What is the main negative effect of changing the due dates of open orders?
A. The schedule information becomes inaccurate
B. The customer service level decreases
C. It leads to “nervousness” in the schedule
D. The schedule does not support demand
View answer
Correct Answer: C
Question #19
Annual cost of pacing orders and annual cost of carrying inventory, together forms:
A. AAnnual cost
B. BDetermined cost
C. CPermanent cost
D. DRelevant cost
View answer
Correct Answer: D
Question #20
Manufacturing processes can be conveniently organized into which of the following three categories?
A. Flow manufacturing, intermittent manufacturing, and project manufacturing
B. Material manufacturing, control manufacturing, and project manufacturing
C. Flow manufacturing, alternating manufacturing, and control manufacturing
D. Material manufacturing, Regular manufacturing, and project manufacturing
View answer
Correct Answer: A
Question #21
Price negotiation is most appropriate when purchasing which of the following product categories?
A. Commodities
B. Standard products
C. Items of small value
D. Made-to-order (MTO) items
View answer
Correct Answer: D
Question #22
Analyzing capital investments by estimating future cash flows and translating them into equivalent amounts in today's terms is called:
A. AAverage return on investment analysis
B. Bpayback analysis
C. Cinternal rate of return analysis
D. Ddiscounted cash flow analysis
View answer
Correct Answer: D
Question #23
A part is sold as a service part, and it is also used as a component in another part. Which of the following statements about the planning for this part is true?
A. Its low-level code is zero
B. The material requirements for the part will be understated
C. The service part demand can be included in the gross requirements
D. It shouldn’t have any safety stock
View answer
Correct Answer: C
Question #24
Which of the following techniques would a group use to prioritize problems?
A. ritical path analysis
B. areto analysis
C. catter charts
D. ause-and-effect diagrams
View answer
Correct Answer: B
Question #25
Which of the following methods would be appropriate for forecasting the demand for a product family when there is a significant trend and seasonality in the demand history?
A. conometric models
B. omputer simulation
C. ime series decomposition
D. eighted moving average
View answer
Correct Answer: C
Question #26
A technique to manage load variability would be to:
A. Aapply capacity planning using overall factors (CPOF) to identify priority items at the work center
B. Bplan additional safety capacity as a part of total available capacity to meet unplanned demand
C. Cdesign the shop floor with machines that sit idle until additional demand requires their use
D. Duse capacity bills to provide a rough-cut method of planning total-time-per-unit value
View answer
Correct Answer: B
Question #27
The files contained in the database are of two types which are:
A. planning and control
B. planning and procedural
C. fixed and variable
D. absolute and relative
View answer
Correct Answer: A
Question #28
Risk pooling would work best for items with:
A. ow demand uncertainty and short lead times
B. ow demand uncertainty and long lead times
C. igh demand uncertainty and short lead times
D. igh demand uncertainty and long lead times
View answer
Correct Answer: D
Question #29
The time spent in queue by a specific manufacturing job is determined by which of the following factors related to the order?
A. ot size
B. riority
C. etup time
D. un time
View answer
Correct Answer: B
Question #30
Exhibit: A company has prioritized customers A, B, and C, filling orders in that sequence. What are the impacts to customer service levels for customers B and C?
A. A100% service levels for B and C
B. BCustomer B has higher service level
C. CCustomer C has higher service level
D. DCustomer B and C have same service level
View answer
Correct Answer: B

View Answers after Submission

Please submit your email and WhatsApp to get the answers of questions.

Note: Please make sure your email ID and Whatsapp are valid so that you can get the correct exam results.

Email:
Whatsapp/phone number: