السؤال #1
A project sponsor asked the PM to provide a summary of the current financial status. The PM uses the following burn up chart for the analysis: Based on the chart, which of the following is the current status of the project?
A. Behind schedule and over budget
B. Behind schedule and under budget
C. Ahead of schedule and over budget
D. Ahead of schedule and under budget
عرض الإجابة
اجابة صحيحة: B
السؤال #2
A project manager has been very diligent in maintaining the version control for the documentation of requirements. Which of the following tools is the project manager using?
A. Multiauthoring software
B. Word processor
C. Real-time polling
D. Conferencing platforms
عرض الإجابة
اجابة صحيحة: B
السؤال #3
During the stabilization phase for recently deployed software, an end user reports a bug that is compromising data integrity. Which of the following tools will the project manager MOST likely use?
A. Issue log
B. Defect log
C. Change log
D. Task board
عرض الإجابة
اجابة صحيحة: A
السؤال #4
A project manager sent equipment to a global project team for testing purposes. Only 70% of the project team received the equipment for testing. Which of the following considerations is impacting the rest of the team?
A. Quality assurance
B. Organizational branding restrictions
C. State privacy acts
D. Country legal regulations
عرض الإجابة
اجابة صحيحة: A
السؤال #5
Which of the following activities would a project manager perform during the closing phase? (Choose three.)
A. Lessons learned
B. Risk analysis
C. Removing resources
D. Acquiring resources
E. Statement of work sign-off
F. Stakeholder analysis G
عرض الإجابة
اجابة صحيحة: AEF
السؤال #6
The project team determines that software installation can only begin after the desktops have been installed and can be powered on. Which of the following dependencies does this represent?
A. External
B. Internal
C. Mandatory
D. Discretionary
عرض الإجابة
اجابة صحيحة: B
السؤال #7
As a result of an approved change, the project manager updates the project plan with the newest project end date. Which of the following change control processes should the project manager complete NEXT?
A. Document the request in the change control log
B. Communicate the change deployment
C. Conduct an impact assessment
D. Implement the change
عرض الإجابة
اجابة صحيحة: C
السؤال #8
Which of the following describes three-tier architecture?
A. Conceptual, design, and implementation stages
B. Presentation, application, and data processing
C. Network, software, and security
D. Development, testing, and production environment
عرض الإجابة
اجابة صحيحة: AB
السؤال #9
A third party needs to perform a short-term task for which the duration cannot be accurately estimated and the cost cannot be calculated in advance. Which of the following should the project manager put in place before work begins?
A. Time and materials contract
B. Master service agreement
C. Fixed-price contract
D. Statement of work
E. Cost-plus agreement
عرض الإجابة
اجابة صحيحة: C
السؤال #10
A visual that displays team progress was created for stand-up meetings. Which of the following BEST describes what is being represented on the visual?
A. Decision board
B. Whiteboard
C. Task board
D. Dashboard
عرض الإجابة
اجابة صحيحة: C
السؤال #11
During a quality analysis review, the causes of several issues have been highlighted. Which of the following should the project manager use to identify the MOST important causes?
A. Ishikawa diagram
B. Scatter diagram
C. Pareto chart
D. Decision tree
عرض الإجابة
اجابة صحيحة: C
السؤال #12
A project team evaluated the performance of a new reporting system and the quantity of queries to be processed during predetermined time stamps. Which of the following is the current status of the process?
A. Based on the rule of seven, the process is under control
B. The amount of data is insufficient to determine if quality is low
C. The process is out of control and should be revised
D. The goal should be adjusted since most of the data points are close to the lower limit
عرض الإجابة
اجابة صحيحة: D
السؤال #13
DRAG DROP - During a gate review meeting, the deliverable was rejected by the customer. Review the dashboard. Part 1: Drag and drop each task, placing them in the correct order based on the project change control process. Part 2: Select the proper document(s) to be updated.
A. Mastered
B. Not Mastered
عرض الإجابة
اجابة صحيحة: A
السؤال #14
A program manager is reviewing the project portfolio and prioritizing each project based on the company’s strategic plan. Which of the following should be considered in this evaluation? (Choose two.)
A. Company vision
B. Global environment
C. Brand value
D. Mission statement
E. Portfolio budget
F. Local legislation
عرض الإجابة
اجابة صحيحة: C
السؤال #15
During a brainstorming session, a project team is elaborating on what caused the unexpected crash of the website that the team was developing. Given the following: Which of the following was the initial cause of the issue?
A. Inadequate memory
B. Incorrect configuration
C. Lack of infrastructure
D. Inadequate instructions
عرض الإجابة
اجابة صحيحة: B

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: