A developer recommends modifying an existing portion of code that is not part of the scope and is causing low performance on the current solution. Which of the following actions should the project manager most likely take? The project manager should ask the developer to create a change request, which is a formal document that describes the proposed change, its benefits, costs, risks, and impacts on the project scope, schedule, budget, and quality. A change request is the first step in the change control pro
A. sk a developer to create a change request
B. o nothing because recommendation is scope creep
C. sk a developer to implement the recommendation
D. ommunicate the change status