Marian is the Product Owner envisioning a project for a new release of her product. She made a projection of a release date based upon a sustained velocity of 17 completed units of work per Sprint. Over the first 3 Sprints, the average velocity was 13 for work that the Development Team estimated as 90% done. The Development Teams, feeling the need to meet the plan, figured that a velocity of 17 was within their reach. A good way to continue is:
A. The Development Team makes sure that all of the selected scope per Sprint is as “Done” as possible
B. Add enough people to the Development Team for the deadline to be made
C. The opportunity to inspect and adapt is lost
D. The Development Team should remind Marian to find funding for enough Release Sprints in which the remaining work can be done