لا تريد أن تفوت شيئا؟

نصائح اجتياز امتحان الشهادة

آخر أخبار الامتحانات ومعلومات الخصم

برعاية وحديثة من قبل خبرائنا

نعم، أرسل لي النشرة الإخبارية

خذ اختبارات أخرى عبر الإنترنت

السؤال #1
True or False: The Sprint Goal is a result of Sprint Planning, as is the Sprint Backlog.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #2
Every Development Team should have: (Choose the best answer.)
A. At least one representative from each major software engineering discipline (like QA, Dev, UX)
B. The competencies and skills needed to deliver a Done Increment in a Sprint
C. One Lead Developer and no more than 8 other members
عرض الإجابة
اجابة صحيحة: B
السؤال #3
Who owns the Sprint Backlog? (Choose the best answer.)
A. The Scrum Team
B. The Product Owner
C. The Scrum Master
D. The Development Team
عرض الإجابة
اجابة صحيحة: D
السؤال #4
True or False: Every Scrum team must have a Product Owner and Scrum Master.
A. True
B. False
C. False
D. True
عرض الإجابة
اجابة صحيحة: A
السؤال #5
When can a Development Team cancel a Sprint?
A. It can’t
B. When functional expectations are not well understood
C. When the Product Owner is absent too often
D. When the selected Product Backlog items for the Sprint become unachievable
E. When a technical dependency cannot be resolved
عرض الإجابة
اجابة صحيحة: A
السؤال #6
What enhances the transparency of an increment? (Choose the best answer.)
A. Doing all work needed to meet the definition of “Done”
B. Reporting Sprint progress to the stakeholders daily
C. Keeping track of and estimating all undone work to be completed in a separate Sprint
D. Updating Sprint tasks properly in the electronic tracking tool
عرض الإجابة
اجابة صحيحة: A
السؤال #7
When should a Sprint Goal be created? (Choose the best answer.)
A. It should have been created in the previous Sprint during Product Backlog refinement
B. It must be established before Sprint Planning in order to begin planning
C. A Sprint Goal is not mandatory in Scrum
D. At any time during the Sprint
E. During Sprint Planning
عرض الإجابة
اجابة صحيحة: E
السؤال #8
When might a Sprint be abnormally cancelled? (Choose the best answer.)
A. When the Development Team feels that the work is too hard
B. When the Sprint Goal becomes obsolete
C. When the sales department has an important new opportunity
D. When it becomes clear that not everything will be finished by the end of the Sprint
عرض الإجابة
اجابة صحيحة: B
السؤال #9
Who determines when it is appropriate to update the Sprint Backlog during a Sprint?
A. The Project Manager
B. The Development Team
C. The Scrum Team
D. The Product Owner
عرض الإجابة
اجابة صحيحة: B
السؤال #10
When does the second Sprint start? (Choose the best answer.)
A. Once the architectural changes for the second Sprint have been approved by the senior architect
B. After the Product Backlog for the second Sprint has been selected
C. Immediately after the first Sprint
D. After the customer completes acceptance testing of the first Sprint
عرض الإجابة
اجابة صحيحة: C
السؤال #11
Why should the Product Owner be present at the Daily Scrum? (Choose the best answer.)
A. He/She doesn’t need to be there
B. To hear about impediments in functionality
C. To represent the stakeholder’s point of view
D. To participate as a Scrum Team member
عرض الإجابة
اجابة صحيحة: A
السؤال #12
Who can abnormally terminate a Sprint? (Choose the best answer.)
A. The Scrum Master
B. The Development Team or its members
C. The Product Owner
D. The Stakeholders
عرض الإجابة
اجابة صحيحة: C
السؤال #13
The Development Team should have all the skills needed to: (Choose the best answer.)
A. Turn Product Backlog items into an Increment of potentially releasable product functionality
B. Do all of the development work, except for specialized testing that requires additional tools and environments
C. Complete the project within the date and cost as calculated by the Product Owner
عرض الإجابة
اجابة صحيحة: A
السؤال #14
Five new Scrum Teams have been created to build one product. A few of the developers on one of the Development Teams ask the Scrum Master how to coordinate their work with the order teams. What should the Scrum Master do?
A. Teach the Product Owner to work with the lead developers on ordering Product Backlog in a way to avoid too much technical and development overlap during a Sprint
B. Teach them that it is their responsibility to work with the other teams to create an integrated Increment
C. Collect the Sprint tasks from the teams at the end of their Sprint Planning and merge that into a consolidated plan for the entire Sprint
D. Visit the five teams each day to inspect that their Sprint Backlogs are aligned
عرض الإجابة
اجابة صحيحة: C
السؤال #15
What are three ways Scrum promotes self-organization? (Choose three.)
A. By not allowing documentation
B. By the Development Team deciding what work to do in a Sprint
C. By preventing stakeholders from entering the development room
D. By removing titles for Development Team members
E. By being a lightweight framework
عرض الإجابة
اجابة صحيحة: BDE
السؤال #16
Which of the following is required by Scrum? (Choose all that apply.)
A. Sprint Retrospective
B. Members must be stand up at the Daily Scrum
C. Sprint Burndown Chart
D. Release planning
E. All of the above
عرض الإجابة
اجابة صحيحة: A
السؤال #17
In the Sprint Planning meeting, the Product Owner and the Development Team were unable to reach a clear understanding about the highest order Product Backlog items. Because of this, the Development Team couldn’t figure out how many Product Backlog items it could forecast for the upcoming Sprint. They were able to agree on a Sprint Goal, however. Which of the following two actions should the Scrum Master support? (Choose two.)
A. Cancel the Sprint
B. Forecast the most likely Product Backlog items to meet the goal and create a Sprint Backlog based on a likely initial design and plan
C. Continue the Sprint Planning meeting past its time-box until an adequate number of Product Backlog items are well enough understood for the Development Team to make a complete forecast
D. Discuss in the upcoming Sprint Retrospective why this happened and what changes will make it less likely to recur
E. Ask everyone to take as much time as needed to analyze the Product Backlog first, and then reconvene another Sprint Planning meeting
عرض الإجابة
اجابة صحيحة: BD
السؤال #18
Which two of the following are appropriate topics for discussion during a Sprint Retrospective? (Choose the best two answers.)
A. Identifying high priority process improvements for the next Sprint
B. The order of items in the Product Backlog
C. How the team collaborates
D. Documenting acceptance criteria for items in the next Sprint
عرض الإجابة
اجابة صحيحة: AC
السؤال #19
Which answer best describes the topics covered in Sprint Planning?
A. What to do and who will do it
B. How conditions have changed and how the Product Backlog should evolve
C. What can be done and how to do it
D. What went wrong in the last Sprint and what to do differently this Sprint
E. Who is on the team and what team member roles will be
عرض الإجابة
اجابة صحيحة: C
السؤال #20
Scrum has a role called “Project Manager”.
A. True
B. False
عرض الإجابة
اجابة صحيحة: B
السؤال #21
Why does the Product Owner want the Development Team to adhere to its definition of “Done”? (Choose the best answer.)
A. To have complete transparency into what has been done at the end of each Sprint
B. To be able to reprimand the team when they don’t meet their velocity goal for the Sprint
C. To know what the team will deliver over the next three Sprints
D. To predict the team’s productivity over time
عرض الإجابة
اجابة صحيحة: A
السؤال #22
What is included in the Sprint Backlog? (Choose the best answer.)
A. User Stories
B. Tasks
C. Use Cases
D. Tests
E. Any of the above (or others) which are a decomposition of the selected Product Backlog items
عرض الإجابة
اجابة صحيحة: E
السؤال #23
How should a Development Team deal with non-functional requirements?
A. Ensure every Increment meets them
B. Make sure the release department understands these requirements, but it is not the Development Team’s responsibility
C. Handle them during the Integration Sprint preceding the Release Sprint
D. Assign them to the lead developers on the team
عرض الإجابة
اجابة صحيحة: A
السؤال #24
During a Sprint Retrospective, for what is the Scrum Master responsible? (Choose the best answer.)
A. Prioritizing the resulting action items
B. Participating as a Scrum team member and facilitating as requested or needed
C. Acting as a scribe to capture the Development Team’s answers
D. Summarizing and reporting the discussions to management
عرض الإجابة
اجابة صحيحة: B

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: