Linda is the business analyst for her organization and she's working with Joe, a new business analyst, to prioritize requirements. Joe doesn't understand why requirements need to be prioritized; as all requirements are required, they should carry equal weight in the analysis. What should Linda tell Joe as to why requirements must be prioritized?
A. rioritization ranks the requirements according to the cost and schedule
B. rioritization ranks the requirements on a weighted scale of key performance indicators, such as cost, schedule, risk, and experience
C. rioritization ensures that the most important stakeholders are considered first
D. rioritization of requirements focuses on the most critical requirements first