Additional Information Extract from the Communication Management Strategy. The project information in the table below is true, but it may not be recorded under the correct heading or be in the correct document. Using the Project Scenario, select the appropriate response to each of the following 5 questions which have been raised by the Project Board. The project is now at the end of the initiation stage. Having decided that the Calendar project is a relatively simple project, the Project Manager combined th
A. The Daily Log was correctly used to monitor risks during the Starting up a Project proces
B. It will be used to capture all risks, actions, decisions, assumptions
C. It was not appropriate to use the Daily Log to capture all risks and issues during the Starting up a Project proces
D. Separate registers should have been set up for risks, issues and lessons learne
E. This will now be done
F. In a simple project, the Project Initiation Documentation (PID) should contain a register for recording risk information and monitoring project risks throughout the delivery stage G