A project sponsor has requested that the project manager reprioritize the team's tasks to include a featurethat is not part of the minimum viable product (MVP) for the project. Although the project sponsor is verykeen on the feature, adding it has the potential of causing team burnout and/or delaying the release.How should the project manager address this situation?
A. Ensure the feature is included in the iteration backlog, ask the team to work on the current tasks first, and include the new tasks after those tasks are completed
B. Ensure the feature has been included in the product backlog, explain to the sponsor the consequence of the request, and ask the team to include the feature's tasks in the next iteration
C. Ensure the feature's tasks are included in the iteration backlog, explain to the sponsor the consequences of the request, and ask the team to deliver the feature in the current iteration
D. Ensure the feature has been included in the product backlog, then hold a meeting with the team and sponsor to determine how to deliver the feature within the current iteration