السؤال #1
A meeting agenda included the following items: . Review the goals of the project. . Review the progress of the project. . Discuss if the project is ready to move forward. Which of the following best describes this type of meeting?
A. Stand-up
B. Monthly status
C. Gap analysis
D. Gate review
عرض الإجابة
اجابة صحيحة: A
السؤال #2
During a staff meeting, a project manager voices a concern about the client billing rate for a particular engineer. Which of the following documents would the project manager need in order to find this information?
A. SLA
B. TOR
C. SOW
D. NDA
عرض الإجابة
اجابة صحيحة: AC
السؤال #3
A project team participates in a brainstorming session to define the guidance, direction, and approach for monitoring established procedures for developed products. Which of the following plans is the team creating?
A. Project transition
B. Project management
C. Project communications
D. Project quality assurance
عرض الإجابة
اجابة صحيحة: D
السؤال #4
Which of the following is required to provide a hardware installation with a Tier 5 redundancy level?
A. Storage project
B. Computer services project
C. Database project
D. Multitiered architecture project
عرض الإجابة
اجابة صحيحة: A
السؤال #5
A project team gathers weekly to review its progress. Which of the following is the project manager MOST likely to have prepared to ensure team members who are absent remain informed about assignments?
A. Status report
B. Project plan
C. Change log
D. Meeting minutes
عرض الإجابة
اجابة صحيحة: D
السؤال #6
Which of the following is a reason to use a SOW on a project?
A. To find out the contact information for the vendors
B. To review the list of stakeholders
C. To ensure the team stays within the scope of the contract
D. To give explicit instruction on how to execute the work
عرض الإجابة
اجابة صحيحة: A
السؤال #7
How does data discovery assist with data classification'?
A. It shows where specific data is stored
B. It automatically classifies data by keywords
C. It helps to identify the data owner
D. It provides assurance of data integrity
عرض الإجابة
اجابة صحيحة: B
السؤال #8
A stakeholder raises a concern with a project manager because of the number of emails that have been received before a coding release. Which of the following actions should the project manager take next?
A. Inform the CCB to stop communication
B. Establish a RACI matrix
C. Escalate the communication issues
D. Revise the communication plan
عرض الإجابة
اجابة صحيحة: C
السؤال #9
In order to complete a major project deliverable, very specialized resources are required for some tasks. The PM failed to take into consideration during planning that the required resources would be available for fewer hours than required. Which of the following should the PM do first to make schedule changes?
A. Add a new risk
B. Perform an impact analysis
C. Escalate to the sponsor
D. Raise a change request
عرض الإجابة
اجابة صحيحة: D
السؤال #10
As a part of a project, structured cabling activities have been outsourced to another company. The agreement is that work will take six weeks to complete and will be performed at different locations. Which of the following should the project manager do? (Select two).
A. Purchase the materials
B. Assign the resources
C. Accept delays in the work
D. Approve the deliverables
E. Monitor the performance
F. Negotiate with the vendors
عرض الإجابة
اجابة صحيحة: C
السؤال #11
Which of the following is a consideration when determining a project's ESG factors?
A. Project management methodology
B. IT infrastructure security
C. Proper accounting practices
D. Corporate values compliance
عرض الإجابة
اجابة صحيحة: B
السؤال #12
Which of the following can be used to determine whether a sample product is within an acceptable range?
A. Scatter diagram
B. Velocity chart
C. Control chart
D. Fishbone diagram
عرض الإجابة
اجابة صحيحة: D
السؤال #13
Which of the following best represents the project impact to a company's brand value?
A. The project is compliant with local and state laws and becomes the standard for new projects
B. The project promotes new initiatives to expand its benefit to other communities
C. The project exceeds the sales quota for the third quarter and raises the bar for next periods
عرض الإجابة
اجابة صحيحة: D
السؤال #14
Which of the following PRINCE2 processes includes creating the project plan?
A. Starting up a project
B. Initiating a project
C. Managing product delivery
D. Directing a project
عرض الإجابة
اجابة صحيحة: D
السؤال #15
A company needs to have structured cabling installed in one of its buildings. Which of the following would be the best document for the company to use to obtain and compare information on cabling services and costs from various vendors?
A. RFB
B. RFQ
C. RF
D. RFP
عرض الإجابة
اجابة صحيحة: D
السؤال #16
During the project initiation phase, a project team has been identified. Which of the following is the NEXT step for the project manager?
A. Determine budget constraints
B. Validate the business case
C. Update the project charter
D. Create a project schedule
عرض الإجابة
اجابة صحيحة: C

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: