Scenario A photographer from Portraits Ltd, a professional photographic company, has taken on the role of Team Manager after taking some time to understand the requirements of the project. A contract for their services has been set up and is being monitored by the Purchasing Manager and a Work Package has been agreed. This contract specifies that the photographer must arrange a meeting with the Engineering Manager to establish a schedule for the photo sessions to minimize the impact on the Engineering staff
A. Proximity categories for this project are: Imminent; Within the stage; Within the project; Beyond the project
B. The risk of MFH having no outsourcing experience will be categorized as Stage 4 proximity
C. Imminent risks are those which may occur within two weeks
D. Any risk with a proximity category of imminent will be estimated as having a very high impact
E. The risk of staff leaving the organization will be categorized as beyond the project proximity