Company A recently signed a contract with a strategic business partner, Company B, to jointly roll out a new technology Company B is excited about the joint marketing opportunity Company A's component Quality Assurance team has expressed concerns to you the program manager, Ural the product is being rolled out prematurely and has identified potential issues with backend support systems. QA, however, assures you that a manual work around is possible, but not ideal Company B requests an enhancement to the new
A. Secure funding from another project that was cancelled
B. Use an integrated change control processcorrect
C. Use the available management reserve
D. Advise Company B that funding and resources are not available