السؤال #1
Identification
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3 ,4
D. 2, 3, 4
عرض الإجابة
اجابة صحيحة: D
السؤال #2
Which is a purpose of the Initiating a Project process?
A. Decide if it is worthwhile to initiate a project
B. Decide on the project approach
C. Establish solid foundations for a project
D. Identify the number of Work Packages required
عرض الإجابة
اجابة صحيحة: A
السؤال #3
- (Topic 4) Why is it crucial that the Project Product Description clearly defines acceptance methods?
A. Enables Project Assurance to authorize quality activities
B. Defines how all project products will be reviewed and approved
C. Defines how it will be proven that the completed project product meets the customer's expectations
D. Provides confirmation that all project products have met their quality criteria
عرض الإجابة
اجابة صحيحة: A
السؤال #4
A product can NOT be supplied to meet all of the requirements in its baselined Product Description. What first action should be taken?
A. Raise a request for change
B. Raise an off-specification
C. Write an Exception Report
D. Amend the Work Package
عرض الإجابة
اجابة صحيحة: B
السؤال #5
What product identifies the management stages and other major control points in a project?
A. Business Case
B. Project Plan
C. Work Package
D. Project Brief
عرض الإجابة
اجابة صحيحة: C
السؤال #6
Identify the missing word(s) in the following sentence. Quality assurance provides assurance to the [?] that the project is being conducted appropriately whilst Project Assurance provides the same assurance to all the project's stakeholders.
A. Project Manager
B. Executive
C. corporate or programme management organization
D. Suppliergroups
عرض الإجابة
اجابة صحيحة: C
السؤال #7
Which aspect of project performance must be managed to avoid misunderstandings on what the project is to deliver?
A. Timescale
B. Scope
C. Risk
D. Costs
عرض الإجابة
اجابة صحيحة: B
السؤال #8
Identify the missing words in the following sentence. The Team Manager should check the [ ? ] for any interfaces that must be maintained while developing products.
A. Project Product Description
B. Project Plan
C. Checkpoint Report
D. Work Package
عرض الإجابة
اجابة صحيحة: A
السؤال #9
Created in the Starting up a Project process
A. Mastered
B. Not Mastered
عرض الإجابة
اجابة صحيحة: B
السؤال #10
Which is NOT undertaken during the Initiating a Project process?
A. Review why the project is needed
B. Identify if the project is sufficiently aligned with corporate objectives
C. Show how the outcome is to be achieved
D. Appoint an Executive and Project Manager
عرض الإجابة
اجابة صحيحة: B
السؤال #11
Ensure corporate or programme management has an interface to a project
A. Mastered
B. Not Mastered
عرض الإجابة
اجابة صحيحة: A
السؤال #12
Which product is used by the Project Manager to authorize work?
A. Team Plan
B. Stage Plan
C. Work Package
D. Product Description
عرض الإجابة
اجابة صحيحة: C
السؤال #13
Which is performed as part of the recommended risk management procedure?
A. Allocation of a budget to investigate issues facing the project
B. Review of risk management practices to ensure that they are performed effectively
C. Sending of information about risks tothe project to project stakeholders
D. Resolution of conflicts between the project and the programme board
عرض الإجابة
اجابة صحيحة: C
السؤال #14
Which does the Executive need to ensure is in place before the project is initiated?
A. All Work Packages are authorized
B. An understanding of how the project will contribute to corporate objectives
C. The Project Plan has been approved
D. The Project Initiation Documentation is complete
عرض الإجابة
اجابة صحيحة: A
السؤال #15
Which is part of quality control?
A. Document the project's acceptance criteria in the Project Product Description
B. Define the quality responsibilities of those involved in the production of the products
C. Produce quality records to show that the planned quality activities have been carried out
D. Maintain the corporate organization's quality management system
عرض الإجابة
اجابة صحيحة: B
السؤال #16
In which product does a Project Manager define the time and cost tolerances for the work to be done by a Team Manager?
A. Product Description
B. Team Plan
C. Work Package
D. Stage Plan
عرض الإجابة
اجابة صحيحة: B
السؤال #17
What do acceptance criteria identify?
A. The approach that will be used to prove whether the project's products have been completed
B. A measureable improvement resulting from a project outcome
C. The measureable definitions of the attributes for a set of products to be acceptable to key stakeholders
D. The project controls set up during the process Initiating a Project
عرض الإجابة
اجابة صحيحة: C
السؤال #18
What theme provides the justification for the project?
A. Quality
B. Plans
C. Progress
D. Business Case
عرض الإجابة
اجابة صحيحة: A
السؤال #19
Which is NOT a recommended quality review team role?
A. Administrator
B. Chair
C. Producer
D. Reviewer
عرض الإجابة
اجابة صحيحة: A
السؤال #20
Which is an objective of the Closing a Project process?
A. Review and approve the plan for project closure
B. Review the performance of the project against its baseline
C. Perform any post-project reviews
D. Create a Benefits Review Plan
عرض الإجابة
اجابة صحيحة: C
السؤال #21
What theme estimates the cost of delivering the project?
A. Business Case
B. Change
C. Plans
D. Progress
عرض الإجابة
اجابة صحيحة: B
السؤال #22
Verification and audit
A. Mastered
B. Not Mastered
عرض الإجابة
اجابة صحيحة: D
السؤال #23
How is a Benefits Review Plan used in the Closing a Project process?
A. Checked for inclusion of activities to confirm those benefits which cannot be measured until after project closure
B. To capture the baseline measures against which to assess benefits
C. To capture side-effects (beneficial or adverse) identified during post-project benefits reviews
D. To gain approval for the post-project activities and transferresponsibility to corporate or programme management
عرض الإجابة
اجابة صحيحة: A
السؤال #24
- (Topic 4) Which is a task of product-based planning?
A. Identify activities and dependencies
B. Write the Project Product Description
C. Prepare the Work Packages
D. Produce Product Status Accounts
عرض الإجابة
اجابة صحيحة: C
السؤال #25
Identify the missing word in the following sentence. The PRINCE2 method addresses project management with four integrated elements: principles, themes, [ ? ] and tailoring PRINCE2 to the project environment.
A. activities
B. processes
C. products
D. quality
عرض الإجابة
اجابة صحيحة: C
السؤال #26
Which statement is true for ALL project stakeholders?
A. Internal to the corporate organization
B. May either affect or be affected by the project
C. Review the Communication Management Strategy
D. Support the project
عرض الإجابة
اجابة صحيحة: B
السؤال #27
What process provides the information required to decide whether to authorize the delivery of a project?
A. Directing a Project
B. Initiating a Project
C. Managing Product Delivery
D. Starting up a Project
عرض الإجابة
اجابة صحيحة: C
السؤال #28
Which is an objective of the Managing a Stage Boundary process?
A. Understand what has gone well and what can help the next stage
B. Review and approve the next Stage Plan
C. Assure the Project Board that all project products have been completed and approved
D. Prepare an Exception Report to advise the Project Board of aforecast deviation from tolerance
عرض الإجابة
اجابة صحيحة: C
السؤال #29
What product records any time tolerances agreed between the Project Manager and Team Manager?
A. Product Description
B. Work Package
C. Project Initiation Documentation
D. Stage Plan
عرض الإجابة
اجابة صحيحة: B
السؤال #30
Identify the missing word(s) in the following sentence. Following initiation, the Controlling a Stage process is used to manage and control each [ ? ] of a project.
A. technical stage
B. benefit
C. management stage
D. Team Plan
عرض الإجابة
اجابة صحيحة: B
السؤال #31
Which product describes the roles and responsibilities for achieving the effective management of anticipated threats and opportunities in a project?
A. Quality Management Strategy
B. Risk Management Strategy
C. Communication Management Strategy
D. Configuration Management Strategy
عرض الإجابة
اجابة صحيحة: B
السؤال #32
When considering how long the project stages should be, which might be a reason for one stage to be longer than others?
A. A substantial amount of the project budget is to be spent
B. More human resources are required than in other stages
C. The risk is lower
D. No changes to the project management team are envisaged
عرض الإجابة
اجابة صحيحة: C
السؤال #33
Which is a PRINCE2 time-driven control?
A. End Stage Report
B. Project Brief
C. Project Initiation Documentation
D. Checkpoint Report
عرض الإجابة
اجابة صحيحة: A
السؤال #34
Which is an objective of the Initiating a Project process?
A. Develop the corporate quality management system as part of the Project InitiationDocumentation
B. Prepare the plans for the subsequentstages
C. Summarize how the organization's project management method will be tailored for the project
D. Request authority from corporate management to deliver the project
عرض الإجابة
اجابة صحيحة: A
السؤال #35
Which of the following are true statements about a Project Brief?
A. Mastered
B. Not Mastered
عرض الإجابة
اجابة صحيحة: D
السؤال #36
Identify the missing word(s) in the following sentence, PRINCE2 recommends three levels of [?] to reflect the needs of the different levels of management involved in a project,
A. Management strategies
B. Plan
C. Stakeholder interests
D. Time-driven controls
عرض الإجابة
اجابة صحيحة: C

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: