Which PRINCE2 integrated element includes the good practices which determine whether a project is genuinely being managed using PRINCE2?
A. Principles
B. Processes
C. Tailoring PRINCE2 to the project environment
D. Themes
عرض الإجابة
اجابة صحيحة: C
السؤال #2
Which is a type of issue?
A. An expected dis-benefit
B. An off-specification
C. Aproject outcome
D. A scope tolerance
عرض الإجابة
اجابة صحيحة: A
السؤال #3
Why is the Initiating a Project process used?
A. To decide which project approach is suitable for the project
B. To fully understand how the project objectives will be achieved before committing significant resources
C. To produce the required Work Packages
D. To enable corporate or programme management to give authorization to deliver a project
عرض الإجابة
اجابة صحيحة: C
السؤال #4
Where should a Team Manager look for information on the quality required for a product?
A. Project Initiation Documentation
B. Product Description
C. Team Plan
D. Quality Management Strategy
عرض الإجابة
اجابة صحيحة: B
السؤال #5
Which of the following is NOT a purpose of the Closing a Project process?
A. Plan the activities required to close a project
B. Enable a comparison of the original objectives of a project against what was actually achieved
C. Enable premature closureif the Project Board request that a project should no longer continue
D. Provide a fixed point at which acceptance for the project product is confirmed
عرض الإجابة
اجابة صحيحة: A
السؤال #6
Which describes risk impact?
A. Timeframe within which the risk might occur
B. The trigger that occurred giving rise to the risk
C. The effect of the risk on the delivery of project objectives
D. How likely the risk is to occur in a given project situation
عرض الإجابة
اجابة صحيحة: C
السؤال #7
Upon what environment is PRINCE2 based?
A. Operational
B. Configuration
C. Programme
D. Customer/supplier
عرض الإجابة
اجابة صحيحة: D
السؤال #8
Which is a purpose of the Risk theme?
A. Establish a method for the implementation of continuous improvement during the project
B. Identify, assess and control problemsthat have occurred
C. Provide the Project Board with a time-driven control to capture all project risks
D. Establish a cost-effective procedure to identify, assess and control risks
عرض الإجابة
اجابة صحيحة: C

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: