لا تريد أن تفوت شيئا؟

نصائح اجتياز امتحان الشهادة

آخر أخبار الامتحانات ومعلومات الخصم

برعاية وحديثة من قبل خبرائنا

نعم، أرسل لي النشرة الإخبارية

خذ اختبارات أخرى عبر الإنترنت

السؤال #1
A company is implementing Dynamics 365 Supply Chain Management in their manufacturing environment. The manufacturing process uses formulas to direct material consumption on the batch orders.During production some items in the formula must be consumed automatically from the production area, while some must be picked with their actual consumption reported on a pick list.You need to determine which setup method is used for formula lines to allow for the desired mixed method picking processes.What are two possi
A. Leave the flushing principle blank on formula lines and set resource consumption to direct flushing principle of materials based on consumption method for the line
B. Leave the flushing principle blank on formula lines and set the default start value to Always for Automatic Bill of Material Consumption
C. Leave the flushing principle blank on formula lines and set default flushing principle on the items based on consumption method for the item
D. Set the flushing principle on each formula line based on consumption method for the line
عرض الإجابة
اجابة صحيحة: AD
السؤال #2
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution, while others might not have a correct solution.After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.A company implements Dynamics 365 Supply Chain Management for their Lean manufa
A. Yes
B. No
عرض الإجابة
اجابة صحيحة: A
السؤال #3
Note: This question is part of a series of questions that present the same scenario. Each question in the series contains a unique solution that might meet the stated goals. Some questions sets might have more than one correct solution, while others might not have a correct solution.After you answer a question in this section, you will NOT be able to return to it. As a result, these questions will not appear in the review screen.A manufacturing plant uses Lean processes. You plan to outsource a painting ope
A. Yes
B. No
عرض الإجابة
اجابة صحيحة: A
السؤال #4
A company produces rubber hose using Discreet orders accounts for raw material scrap after report as finished through inventory movement journals.The company has noticed that most of the scrap that is recorded is due to start up that feeds the hose to the finishing process. In addition, the amount of scrap that is recorded is consistent regardless of the amount of hose being produced.You need to account for material cost during startup.What should you do?
A. Do a case study for the scrap items and enter the average amount of scrap as a separate line items on the Bill of materials
B. Enter the amount of scrap that is consumed as constant scrap in the Bill of materials
C. Enter the amount of scrap that is consumed as variable scrap in the Bill of materials
D. Enter the consumption amount on the line to match the actual amount used
عرض الإجابة
اجابة صحيحة: B
السؤال #5
A Discrete manufacturing company produces speakers. The high-end speaker model uses protective rubber strips on the edges.Approximately five inches of rubber is consistently scrapped in the production process, regardless of production quantity. Workers manually consume the extra material on the picking list or scrap it in an inventory journal.You need configure the system to automatically account for this scrap on the Bill of materials (BOM).What should you do?
A. Increase the required quantity of the rubber component by five on the BOM
B. Set a variable scrap of five percent for the rubber BOM line
C. Add an additional BOM line for five inches and set consumption to Variable
D. Set a Constant scrap of five on the BOM line for rubber
عرض الإجابة
اجابة صحيحة: D
السؤال #6
A company implements Dynamics 365 Supply Chain Management.Due to increased demand and limited space in the work cell area for product L0050, you must subcontract overflow work to another company. You have the following requirements:-> Locate a warehouse at the subcontractor building.-> Support picking and shipping activity tracking.-> Associate costs of transporting materials between the locations in the cost of the finished product.You need to modify the production flow.Which three actions should you perfo
A. Modify the overflow work activity and assign it to subcontractor
B. Create transfer activities and assign them to the subcontractor
C. Create a resource and work cell resource group for the subcontractor
D. Create a new production flow version
E. Modify the overflow work operation and associate it with the subcontractor
عرض الإجابة
اجابة صحيحة: ABC
السؤال #7
You are a production manager at a company that has implemented lean manufacturing using Dynamics 365 Supply Chain Management.You have created a new Kanban rule to replace one that is expiring.You need to determine the impact to the existing process jobs.How are the active Kanbans of the expired rule handled?
A. The active Kanbans are set to add to the requested period and distribute for the replacement rule time fence
B. The active Kanban handling units are registered as empty and new Kanbans are created
C. The active Kanbans are cancelled
D. The active Kanbans are counted as Kanbans of the replaced rule
عرض الإجابة
اجابة صحيحة: A
السؤال #8
A manufacturing plant uses Lean manufacturing. Operators process Kanban consumption manually by using a mobile device.The production team must use automatic empty registration for some of the event Kanbans. Registration must occur when the last job of a Kanban is completed.You need to update the Kanban rule to meet this requirement.What Kanban setting should you update?
A. Select to register as empty when the source requirement is registered
B. Select to register as empty when handling units are received
C. Select to manually register as empty
D. Set a fixed Kanban quantity
عرض الإجابة
اجابة صحيحة: B
السؤال #9
You are the production planner for a manufacturing company.After running operations scheduling for a production order, the following error message displays:
A. Navigate to the work calendar and view working times
B. Review the calendar for the resource to determine if it is expired
C. Review the available resources for Operation 10
D. Review the resource group assigned to Operation 10
عرض الإجابة
اجابة صحيحة: BC
السؤال #10
You have a product that can be manufactured on two different production lines in the same warehouse. You create resources and then create individual input locations for the resources. You create two routes. Each route uses different resources.Materials are staged for consumption in different locations based on the resources being utilized for production.You need to set up the formula to consume the goods from the correct line-side location.What should you do?
A. Select a warehouse and consumption operation for each line
B. Select resource consumption and the operation for each line
C. Select the plan group and consumption operation for each line
D. Specify a site in the formula header
عرض الإجابة
اجابة صحيحة: B

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: