السؤال #1
What is a Product Owner typically responsible for during a Sprint? (choose the best two answers)
A. rue
B. alse
عرض الإجابة
اجابة صحيحة: B,D
السؤال #2
Adaptation requires regular inspection. In what ways does the Product Owner contribute to the results achieved by inspection?(choose the best two answers)
A. The Product Owner verifies the Sprint Backlog for completeness at the end of Sprint Planning in order to allow the Sprint to start
B. The Product Owner shares the current state of Product Backlog at the Sprint Review, which, combined with the inspection of the Increment, leads to an updated Product Backlog
C. The Product Owner invites stakeholders to the Sprint Review to learn how the current state of the marketplace influences what is the most valuable thing to do next
D. The Product Owner inspects the Sprint burn-down at the Daily Scrum for progress towards a complete Increment and re-planning the team's work
عرض الإجابة
اجابة صحيحة: B, C
السؤال #3
What should Developers do if the Product Owner is unavailable?(choose the best answer)
A. Management should assign a substitute Product Owner to fill in when the Product Owner cannot be there
B. Wait until the Product Owner is available again
C. Ask the Product Owner’s manager to decide in the Product Owner’s absence
D. Within the Sprint, the Developers make the best decisions possible to assure progress toward the Sprint Goal, re-aligning with the Product Owner once they are available again
عرض الإجابة
اجابة صحيحة: D
السؤال #4
Which is NOT a valid consideration when ordering a Product Backlog? (choose the best answer)
A. ependencies on other Product Backlog items
B. mportance to customers
C. lignment with business strategy and goals
D. ools and techniques
E. isk
عرض الإجابة
اجابة صحيحة: D
السؤال #5
How do timeboxes help the Product Owner and the other members of the Scrum Team validate assumptions, adapt, and maximize the value of their product?
A. At the end of each Sprint when the timebox expires a detailed report with all test cases and test results is available
B. Timeboxes assure the Product Owner that the Developers will finish all work on the Sprint Backlog by the end of the Sprint
C. Timeboxes help by making sure a Sprint does not stop until all testing is done, and the work is verified by the Product Owner
D. Timeboxes help minimize risk by creating the opportunity to validate assumptions using feedback from users and the market; allowing Scrum Teams to inspect progress toward the Product Goal and decide whether to pivot or persevere
عرض الإجابة
اجابة صحيحة: D
السؤال #6
Who starts the Daily Scrum?(choose the best answer)
A. he Scrum Master
B. he person coming in last
C. he Product Owner
D. hoever the Developers decide should start
E. he person who has the token
عرض الإجابة
اجابة صحيحة: D
السؤال #7
True or False: Multiple Scrum Teams working on the same product or system all select work from the same Product Backlog.
A. rue
B. alse
عرض الإجابة
اجابة صحيحة: A
السؤال #8
How does an organization know that a product built using Scrum is successful?(choose the best answer)
A. By the Product Owner and stakeholders accepting the Increment at the Sprint Review
B. By measuring the actual time spent on development versus the time estimated for development
C. By releasing frequently, and measuring the value customers/users experience
D. By measuring that velocity has increased since the last release
عرض الإجابة
اجابة صحيحة: C
السؤال #9
A Scrum Team has been working on a product for 9 Sprints. A new Product Owner who is new to Scrum joins the team and understands she is accountable for the Product Backlog. However, she is unsure about the purpose of the Product Backlog. She has read that the Product Backlog should be a list of all user features for the product. She goes to the Scrum Master asking where to put the other types of requirements that are going to be taken into account. Are all of the following types of requirements acceptable o
A. es, they all belong on the Product Backlog
B. o
عرض الإجابة
اجابة صحيحة: A
السؤال #10
07.?What are typical activities for a Product Owner in a Sprint?(choose the best two answers)
A. Create financial reporting upon the spent hours reported by the Scrum Team
B. Collaborate with stakeholders, user communities, and subject matter experts
C. Work with the Developers on Product Backlog refinement
D. Update the work plan for the Developers on a daily basis
عرض الإجابة
اجابة صحيحة: B, C
السؤال #11
Which of the following are criteria to order Product Backlog items? (choose all that apply)
A. rue
B. alse
عرض الإجابة
اجابة صحيحة: A,B,C
السؤال #12
Why is the Daily Scrum held at the same time and same place? (choose the best answer)
A. he Product Owner demands it
B. ooms are hard to book and must be booked in advance
C. he place can be named
D. he consistency reduces complexity
عرض الإجابة
اجابة صحيحة: D
السؤال #13
True or False: When there are multiple teams working on one product, each Scrum Team should have a separate Product Owner.
A. he Product Owner should select the Sprint Goal for the Scrum Team so that work can begin
B. he Developers will find it difficult to create a Sprint forecast they are confident they can meet
C. othing in particular
D. he Scrum Master should not allow this to happen
E. print Planning is canceled so refinement can be done first
عرض الإجابة
اجابة صحيحة: B
السؤال #14
When does the next Sprint begin?(choose the best answer)
A. he Monday following the Sprint Review
B. mmediately after the conclusion of the previous Sprint
C. mmediately following the next Sprint Planning
D. hen the Product Owner is ready
عرض الإجابة
اجابة صحيحة: B
السؤال #15
The length of a Sprint should be:(choose the best answer)
A. hort enough to keep the business risk acceptable to the Product Owner
B. hort enough to be able to synchronize the development work with other business events
C. o more than one calendar month
D. ll of the above
عرض الإجابة
اجابة صحيحة: D
السؤال #16
True or False: The value delivered by a product can only be determined by revenue.
A. es, in order to accurately inspect what is done
B. es, but only for Scrum Teams whose work has dependencies
C. o, each Scrum Team stands alone
D. o, that is far too hard and must be done in a hardening Sprint
عرض الإجابة
اجابة صحيحة: B
السؤال #17
By which method an organization maximize the value that realize from the product over time?(choose the best option)
A. Current Value Goal
B. Unrealized Value goal
C. Ability to Innovate
D. Time to Market Goal
عرض الإجابة
اجابة صحيحة: B
السؤال #18
When does a Sprint conclude?(choose the best answer)
A. hen all the tasks are completed by the Developers
B. hen the Sprint Retrospective is complete
C. hen all Product Backlog items meet their Definition of Done
D. hen the Product Owner decides enough has been delivered to meet the Sprint Goal
عرض الإجابة
اجابة صحيحة: D
السؤال #19
All Scrum artifacts must be transparent to ensure sufficient accuracy of inspection. Which two measures ensure that the Product Backlog is transparent? (choose the best two answers)
A. rue
B. alse
عرض الإجابة
اجابة صحيحة: A,B
السؤال #20
A product's success is measured by:(choose the best three answers)
A. es, the Product Owner decides the Definition of Done
B. o, the Scrum Team decides the Definition of Done, if it is not a standard of the organization
عرض الإجابة
اجابة صحيحة: A,B,F

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: