السؤال #1
In an assemble-to-order production environment, the master production schedule contains:
A. standard items
B. finished items
C. raw materials
D. subassemblies
عرض الإجابة
اجابة صحيحة: D
السؤال #2
Which of the following is the file that fall in planning category?
A. master file
B. product structure file
C. routing file
D. All of the above
عرض الإجابة
اجابة صحيحة: D
السؤال #3
The capacity required depends on the particular mix of products being built and is difficult to predict is a characteristic of:
A. Intermittent manufacturing
B. process improvement
C. Streamline manufacturing
D. Periodic manufacturing
عرض الإجابة
اجابة صحيحة: A
السؤال #4
Which of the following criteria is used to determine safety stock in a distribution center (DC)?
A. conomic order quantity (EOQ)
B. easonal index value
C. lpha factor level
D. robability of stocking out
عرض الإجابة
اجابة صحيحة: D
السؤال #5
Which of the following is NOT the manufacturing lead time?
A. Queue time
B. Setup time
C. Run time
D. Load time
عرض الإجابة
اجابة صحيحة: D
السؤال #6
Which of the following tools is used to evaluate the impact that a production plan has on capacity?
A. ADemand time fence (DTF)
B. BBill of resources
C. CProduct routing
D. DSafety capacity
عرض الإجابة
اجابة صحيحة: B
السؤال #7
A life cycle assessment (LCA) would be used to determine:
A. Athe length of a long-term agreement
B. Bhow an item should be scheduled
C. Cenvironmental aspects and impacts
D. Dif risk pooling would reduce inventory investment
عرض الإجابة
اجابة صحيحة: C
السؤال #8
A company confirms a customer order based on available capacity and inventory, even though the current production plan does not cover the entire order quantity. This situation is an example of what type of order fulfillment policy?
A. ssemble-to-order (ATO)
B. apable-to-promise (CTP)
C. vailable-to-promise (ATP)
D. onfigure-to-order (CTO)
عرض الإجابة
اجابة صحيحة: B
السؤال #9
The time normally required to produce an item in a typical lot quantity is known as:
A. Manufacturing load time
B. Manufacturing conduct time
C. Manufacturing control time
D. Manufacturing lead time
عرض الإجابة
اجابة صحيحة: D
السؤال #10
When starting an external benchmarking study, a firm must first:
A. etermine the metrics which will be measured and compared
B. dentify the target firms with which to benchmark against
C. nderstand its own processes and document performance
D. etermine its areas of weakness versus the competition’s
عرض الإجابة
اجابة صحيحة: C
السؤال #11
A manufacturer has a primary assembly line supported by output from several subassembly lines. Which of the following scenarios would be the best argument for a multilevel master scheduling process?
A. ow variation in aggregate subassembly demand
B. igh variation in aggregate subassembly demand
C. ow variation in subassembly demand mix
D. igh variation in subassembly demand mix
عرض الإجابة
اجابة صحيحة: D
السؤال #12
What consist of a series of operations required to make the item?
A. routing
B. builds
C. procedures
D. All of the above
عرض الإجابة
اجابة صحيحة: A
السؤال #13
In which of the following phases of the product life cycle is product price most effective in influencing demand?
A. AIntroduction
B. BGrowth
C. CMaturity
D. DDecline
عرض الإجابة
اجابة صحيحة: A
السؤال #14
An effective approach to projecting requirements for materials with long lead times includes which of the following options?
A. nitiate a multilevel master schedule
B. se phantom bills of materials (BOMs)
C. ncrease the level of safety stock
D. ecrease the planning horizon
عرض الإجابة
اجابة صحيحة: A
السؤال #15
Which of the following statements characterizes a pull system in distribution management?
A. ach warehouse makes its own replenishment decisions
B. t uses distribution requirements planning (DRP)
C. t uses uniform performance measures
D. t uses fair-share allocation
عرض الإجابة
اجابة صحيحة: A
السؤال #16
The usual process is to start with the due date and, using the lead times, to work back to find the start date for each operation, this process is known as:
A. Back scheduling
B. Front scheduling
C. Liquidity scheduling
D. Fixed scheduling
عرض الإجابة
اجابة صحيحة: A
السؤال #17
Which of the following circumstances would cause a move from acceptance sampling to 100% inspection?
A. AHistory shows that the quality level has been stable from lot to lot
B. BThe company uses one of its qualified suppliers
C. CDownstream operators encounter recurring defects
D. DThe percent of defects is expected to be greater than 5%
عرض الإجابة
اجابة صحيحة: C
السؤال #18
Return on investment (ROI) is decreased by which of the following activities?
A. AIncreasing prices
B. BIncreasing sales volume
C. CIncreasing cost of sales
D. DReducing inventory levels
عرض الإجابة
اجابة صحيحة: C
السؤال #19
Which of the following measurements indicates there may be bias in the forecast model?
A. ean absolute deviation (MAD)
B. tandard deviation
C. racking signal
D. ariance
عرض الإجابة
اجابة صحيحة: C
السؤال #20
Improvements in an Input/output control (I/O control) system will most likely lead to:
A. Aflattened bills of material (BOMs)
B. Ba change in operation sequencing
C. Creduction in queue size and queue time
D. Dfewer engineering change notifications
عرض الإجابة
اجابة صحيحة: C
السؤال #21
Which of the following criteria is used to determine safety stock in a distribution center (DC)?
A. AEconomic order quantity (EOQ)
B. BSeasonal index value
C. CAlpha factor level
D. DProbability of stocking out
عرض الإجابة
اجابة صحيحة: D
السؤال #22
A particular type of production control system used varies from company to company, but all should perform the preceding functions is called:
A. Mechanizing system
B. Developed system
C. Manufacturing system
D. Master system
عرض الإجابة
اجابة صحيحة: C
السؤال #23
Which of the following activities will enhance a successful supplier customer lean relationship?
A. AThe supplier offers quantity discounts on material purchased
B. BReturnable containers are used for material transport
C. CCommunication between the counterparts at the two companies is studied and improved
D. DConsignment inventories are maintained in anticipation of customer need
عرض الإجابة
اجابة صحيحة: C
السؤال #24
An organization has seen inventory increase every month for the past year and financial performance has net met expectations. Which of the following processes would most appropriately address correcting the problem?
A. Business planning
B. Sales and operations planning (S&OP)
C. Detailed material planning
D. Master scheduling
عرض الإجابة
اجابة صحيحة: B
السؤال #25
Which file contains a list of the single-level components and quantities needed to assemble a parent?
A. master file
B. product structure file
C. routing file
D. work center master file
عرض الإجابة
اجابة صحيحة: B
السؤال #26
One way to mitigate liability risk in the supply chain is to:
A. egotiate lower component cost
B. equire traceability for components
C. ush inventory to supplier locations
D. se less-than-truckload (LTL) shipments more frequently
عرض الإجابة
اجابة صحيحة: B
السؤال #27
Which of the following is NOT categorized modeling approaches in SCM?
A. ASupply Chain Network Design Method:
B. BMIP Optimization Modeling:
C. CHeuristic Methods:
D. DNone of these
عرض الإجابة
اجابة صحيحة: D
السؤال #28
What is characterized by many variations in product design, process requirements and order quantities?
A. Intermittent manufacturing
B. process improvement
C. Streamline manufacturing
D. Periodic manufacturing
عرض الإجابة
اجابة صحيحة: A
السؤال #29
For a company that uses first in, first out (FIFO) inventory accounting, the actual use in production of a recently arrived shipment of more expensive components rather than lower-cost components previously received will have which of the following results?
A. Higher cost of goods sold (COGS)
B. Lower COGS
C. No change to COGS
D. A violation of FIFO rules
عرض الإجابة
اجابة صحيحة: D
السؤال #30
products. is concerned with the production of high-volume standard
A. Continuous manufacturing
B. Flow manufacturing
C. Repetitive manufacturing
D. None of the above
عرض الإجابة
اجابة صحيحة: B

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: