السؤال #1
Which of the following project characteristics would suggest using the PERT technique, rather than the critical path method?
A. stimates of individual task times are probabilistic
B. roject tasks are backward scheduled
C. ue dates are needed to identify critical tasks
D. roject management can determine the critical path
عرض الإجابة
اجابة صحيحة: A
السؤال #2
The implementation of a program designed to reduce changeover times will result in a temporary capacity shortage. This shortage will be handled by using some older equipment and by subcontracting some work. Which of the following methods should the company use to control capacity during this period?
A. anban
B. emand management
C. low control
D. nput/output control
عرض الإجابة
اجابة صحيحة: D
السؤال #3
Throughput for a family of parts can be increased by use of which of the following approaches?
A. Cell layout
B. Functional layout
C. High utilization
D. Batch processing
عرض الإجابة
اجابة صحيحة: A
السؤال #4
Which of the following outcomes are objectives of statistical process control?
A. To reduce product returns
B. To stabilize a process
C. To verify a DMAIC project
D. To identify control limits
عرض الإجابة
اجابة صحيحة: B
السؤال #5
The primary reason for using an empty conveyance container as a triggering signal is to:
A. communicate the need for material
B. keep the original container filled with material
C. pull material downstream
D. push material downstream
عرض الإجابة
اجابة صحيحة: A

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: