السؤال #1
What describes essential aspects of project management that must be applied consistently andthroughout the project lifecycle?
A. he project context
B. he PRINCE2 practices
C. he PRINCE2 processes
D. he people element
عرض الإجابة
اجابة صحيحة: B
السؤال #2
Which of the following uses a flow-based approach to control work in progress?
A. gilometer
B. ean
C. anban
D. crum
عرض الإجابة
اجابة صحيحة: C
السؤال #3
Which workshop is used to assess the project's status and address any challenges?
A. roject retrospective workshop
B. eam retrospective workshop
C. eam planning workshop
D. rogress review workshop
عرض الإجابة
اجابة صحيحة: D
السؤال #4
How is the 'tailor to suit the project' principle applied in an agile context?
A. y flexing what is produced to stay in control and deliver value
B. y emphasizing tolerances on what is being delivered
C. y using the Agilometer to assess the project environment
D. y fitting releases into planned management stages
عرض الإجابة
اجابة صحيحة: A
السؤال #5
How is the `tailor to suit the project' principle applied in an agile context?
A. By flexing what is produced to stay in control and deliver value
B. By emphasizing tolerances on what is being delivered
C. By using the Agilometer to assess the project environment
D. By fitting releases into planned management stages
عرض الإجابة
اجابة صحيحة: A
السؤال #6
Which of the following BEST describes stakeholders in a project?
A. Those who have a formal role in the project team
B. Those who will use project products
C. Those who can affect or be affected by the project
D. Those who can impact the project
عرض الإجابة
اجابة صحيحة: C
السؤال #7
Which BEST describes the senior user role when tailoring the organization theme?
A. An `agile sponsor'
B. An `executive sponsor'
C. A `coach'
D. A `super product owner'
عرض الإجابة
اجابة صحيحة: D
السؤال #8
What should the business case state about the minimum viable product (MVP)?
A. When the MVP will be defined
B. That the MVP must go into operational use
C. What the MVP is
D. That the MVP is the same as project viability
عرض الإجابة
اجابة صحيحة: B
السؤال #9
What term is used to describe boards that display what work needs to be completed for people working on a project?
A. Work in progress limit
B. Information radiator
C. Highlight report
D. Glad! Sad! Mad!
عرض الإجابة
اجابة صحيحة: C
السؤال #10
How should product-based planning be used as part of PRINCE2 Agile?
A. To track progress against the team plan
B. To create the project plan using empiricism
C. To enable team planning to be predictive
D. To plan by focusing on the features required
عرض الإجابة
اجابة صحيحة: D
السؤال #11
Which statement about the `keep teams stable' target is CORRECT?
A. It applies primarily to the long term, such as a project or a program
B. It is the primary reason why the tolerance for cost is set to zero
C. It prevents compromising the overall quality level of the product
D. It results in the early delivery of a minimum viable product
عرض الإجابة
اجابة صحيحة: B
السؤال #12
Which statement about the `keep teams stable' target is CORRECT?
A. It applies primarily to the long term, such as a project or a program
B. It is the primary reason why the tolerance for cost is set to zero
C. It prevents compromising the overall quality level of the product
D. It results in the early delivery of a minimum viable product
عرض الإجابة
اجابة صحيحة: B
السؤال #13
What is an epic?
A. A detailed user story with high business value
B. The set of products handed over to the users
C. A high-level user story that is quite broad or vague
D. A prioritized list of requirements to be delivered in a sprint
عرض الإجابة
اجابة صحيحة: C
السؤال #14
What is an epic?
A. high-level requirement
B. fine-grained user story
C. low-level requirement
D. detailed feature
عرض الإجابة
اجابة صحيحة: A
السؤال #15
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?
A. Defined roles and responsibilities
B. Continued business justification
C. Learn from experience
D. Tailor to suit the project
عرض الإجابة
اجابة صحيحة: A
السؤال #16
What are the concepts of refactoring and technical debt usually associated with?
A. Economics
B. Manufacturing
C. Software
D. Mathematics
عرض الإجابة
اجابة صحيحة: C
السؤال #17
Which statement about the 'embrace change' target is CORRECT?
A. t minimizes the time needed to train a new team member
B. t reduces the planning of dependencies between projects
C. t reduces testing in order to meet deadlines
D. t encourages the customer to raise new ideas
عرض الإجابة
اجابة صحيحة: D
السؤال #18
What is the purpose of the ‘agile enablement’ workshop?
A. o identify, assess, and plan for risks associated with transitioning products into operations
B. o identify, assess, and plan for risks associated with agile adoption
C. o identify, assess, and plan for risks associated with project delivery
D. o identify, assess, and plan for risks associated with business as usual
عرض الإجابة
اجابة صحيحة: B
السؤال #19
Which two statements about the supplier representative are CORRECT?1. They communicate guidance on areas of technical compliance.2. They perform initial technical assurance.3. They consolidate and communicate the views of the customer.4. They provide support on releasing into operational use when needed.
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
عرض الإجابة
اجابة صحيحة: D
السؤال #20
What term is used to describe boards that display what work needs to be completed for people working on a project?
A. Work in progress limit
B. Information radiator
C. Highlight report
D. Glad! Sad! Mad!
عرض الإجابة
اجابة صحيحة: C
السؤال #21
Why are team working agreement produced?
A. o create structure so that the team manager can assess individual performance
B. o evolve the effectiveness and behaviors of the self-organizing team by agreeing values
C. o make the team rules visible to the project manager for monitoring purposes
D. o ensure that the delivery team members comply with company policy
عرض الإجابة
اجابة صحيحة: B
السؤال #22
How does the change theme regard change in PRINCE2 Agile?
A. As disruptive
B. As something to be avoided
C. As a necessity
D. As inevitable
عرض الإجابة
اجابة صحيحة: D
السؤال #23
Which TWO are the purposes of a highlight report?
A. 1 and 2
B. 2 and 3
C. 3 and 4
D. 1 and 4
عرض الإجابة
اجابة صحيحة: C
السؤال #24
How does the change theme regard change in PRINCE2 Agile?
A. As disruptive
B. As something to be avoided
C. As a necessity
D. As inevitable
عرض الإجابة
اجابة صحيحة: D
السؤال #25
What term is used to describe boards that display what work needs to be completed for people working on a project?
A. Work in progress limit
B. Information radiator
C. Highlight report
D. Glad! Sad! Mad!
عرض الإجابة
اجابة صحيحة: C
السؤال #26
In which step of the approach to issue management are options to resolve an issue evaluated?
A. apture
B. mplement
C. ecide
D. ecommend
عرض الإجابة
اجابة صحيحة: D
السؤال #27
How does the change theme regard change in PRINCE2 Agile?
A. As disruptive
B. As something to be avoided
C. As a necessity
D. As inevitable
عرض الإجابة
اجابة صحيحة: D
السؤال #28
In which step of the risk management technique do teams consider probability and impact of a risk?
A. lan
B. ssess
C. dentify
D. mplement
عرض الإجابة
اجابة صحيحة: B
السؤال #29
How is the 'tailor to suit the project' principle applied in an agile context?
A. y using the Agilometer to assess the project environment
B. y emphasizing tolerances on what is being delivered
C. y flexing what is produced to stay in control and deliver value
D. y fitting releases into planned management stages
عرض الإجابة
اجابة صحيحة: C
السؤال #30
In an agile context, who is accountable for managing risks at the delivery level?
A. The team manager
B. The project manager
C. The project board
D. The project team
عرض الإجابة
اجابة صحيحة: A
السؤال #31
Whose interests are specifically represented by the senior supplier?1. Those ensuring the project is value for money.2. Those who will use the project's products.3. Those who will be developing the project's products.4. Those responsible for the project's technical integrity.
A. and 2
B. and 3
C. and 4
D. and 4
عرض الإجابة
اجابة صحيحة: B
السؤال #32
In which process should the project manager FIRST assess the suitability of using agile?
A. Controlling a stage
B. Initiating a project
C. Starting up a project
D. Managing a stage boundary
عرض الإجابة
اجابة صحيحة: C
السؤال #33
Why is Lean Startup included in the `starting up a project' process in PRINCE2 Agile?
A. Because it explains how a small company can grow using traditional technologies
B. Because it is designed to manage projects, delivering products in timeboxes
C. Because it enables agile to be used in challenging and uncertain situations
D. Because running a project and setting up a new business are the same
عرض الإجابة
اجابة صحيحة: C

View The Updated Prince2 Exam Questions

SPOTO Provides 100% Real Prince2 Exam Questions for You to Pass Your Prince2 Exam!

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف:
Contact Us