السؤال #1
What is the Cycle Time, in minutes, for a process having a Throughput of 360 units per hour?
A.
B.
C.
D.
عرض الإجابة
اجابة صحيحة: D
السؤال #2
Significant variation in process performance is a consequence of several causes that can be classified using which of the terminologies shown. (Note: There are 2 correct answers).
A. Common
B. Random
C. Uneducated
D. Special
E. Vital
عرض الإجابة
اجابة صحيحة: AD
السؤال #3
A Belt will occasionally do a quick experiment referred to as an OFAT which stands for ____________________.
A. Only a Few Are Tested
B. Opposite Factors Affect Technique
C. One Factor At a Time
D. Ordinary Fractional Approach Technique
عرض الإجابة
اجابة صحيحة: C
السؤال #4
__________ Distributions occur when data comes from several sources that are supposed to be the same yet are not.
A. Skewed
B. Bimodal
C. Gaussian
D. Tri-peaked
عرض الإجابة
اجابة صحيحة: A
السؤال #5
Select all the statements that are true after reviewing the Capability Analysis shown here. (Note:There are 4 correct answers).
A. The process is out of Control
B. The process is properly assumed to be a Normal process
C. The Mean of the process moving range is 1
D. This Capability Analysis used subgroups
E. Majority of the dimensional values are outside of the tolerance than within
عرض الإجابة
اجابة صحيحة: BCDE
السؤال #6
A primary benefit of using a Multi-Vari Chart is it provides a visual presentation of two-way interactions.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #7
SPC charts typically have the most recent data point on the right hand side.
A. rue
B. alse
عرض الإجابة
اجابة صحيحة: A
السؤال #8
Which statement(s) are correct for the Regression Analysis shown here? (Note: There are 2 correct answers).
A. This Regression is an example of a Multiple Linear Regression
B. This Regression is an example of Cubic Regression
C. %Cu explains the majority of the process variance in heat flux
D. Thickness explains over 80% of the process variance in heat flux
E. The number of Residuals in this Regression Analysis is 26
عرض الإجابة
اجابة صحيحة: AD
السؤال #9
Select all the statements that are true after reviewing the Capability Analysis shown here. (Note:There are 4 correct answers).
A. The process is out of Control
B. The process is properly assumed to be a Normal process
C. The Mean of the process moving range is 1
D. This Capability Analysis used subgroups
E. Majority of the dimensional values are outside of the tolerance than within
عرض الإجابة
اجابة صحيحة: BCDE
السؤال #10
A Six Sigma tool that helps to screen factors by using graphical techniques to logically subgroup multiple discrete X's plotted against a continuous Y is known as a _____________Chart.
A. SIPOC
B. Multi-Vari
C. Box Plot
D. Whisker
عرض الإجابة
اجابة صحيحة: B
السؤال #11
Multiple Linear Regressions (MLR) is best used when which of these are applicable? (Note: There are3 correct answers).
A. on-linear relationships between the inputs X’s and output Y
B. ncertainty in the slope of the linear relationship between an X and a Y
C. elationships between Y (output) and more than one X (Input)
D. reventing the use of a Designed Experiment if unnecessary
E. e assume that the X’s are independent of each other
عرض الإجابة
اجابة صحيحة: CDE
السؤال #12
A Six Sigma tool that helps to screen factors by using graphical techniques to logically subgroup multiple discrete X's plotted against a continuous Y is known as a _____________Chart.
A. SIPOC
B. Multi-Vari
C. Box Plot
D. Whisker
عرض الإجابة
اجابة صحيحة: B
السؤال #13
A primary benefit of using a Multi-Vari Chart is it provides a visual presentation of two-way interactions.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #14
When a Belt applies the practice of Poka-Yoke to a project challenge she is attempting to make certain the activity is _______________ .
A. Well documented
B. Removed from the line
C. Mistake proofed
D. Highly visible
عرض الإجابة
اجابة صحيحة: C
السؤال #15
A primary benefit of using a Multi-Vari Chart is it provides a visual presentation of two-way interactions.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #16
__________ Distributions occur when data comes from several sources that are supposed to be the same yet are not.
A. Skewed
B. Bimodal
C. Gaussian
D. Tri-peaked
عرض الإجابة
اجابة صحيحة: A
السؤال #17
The Standard Deviation for the distribution of Means is called the ___________ and approaches zero as the sample size reaches 30.
A. Standard Error
B. Mean Deviation
C. Mean Spread
D. Mean Error
عرض الإجابة
اجابة صحيحة: A
السؤال #18
A Six Sigma tool that helps to screen factors by using graphical techniques to logically subgroup multiple discrete X's plotted against a continuous Y is known as a _____________Chart.
A. SIPOC
B. Multi-Vari
C. Box Plot
D. Whisker
عرض الإجابة
اجابة صحيحة: B
السؤال #19
Select all the statements that are true after reviewing the Capability Analysis shown here. (Note:There are 4 correct answers).
A. The process is out of Control
B. The process is properly assumed to be a Normal process
C. The Mean of the process moving range is 1
D. This Capability Analysis used subgroups
E. Majority of the dimensional values are outside of the tolerance than within
عرض الإجابة
اجابة صحيحة: BCDE
السؤال #20
A Belt will occasionally do a quick experiment referred to as an OFAT which stands for____________________.
A. nly a Few Are Tested
B. pposite Factors Affect Technique
C. ne Factor At a Time
D. rdinary Fractional Approach Technique
عرض الإجابة
اجابة صحيحة: C
السؤال #21
While management of a company must set the stage for all improvement efforts, which of these 5S’s is primarily driven by management?
A. Straighten
B. Sort
C. Shine
D. Sustain
عرض الإجابة
اجابة صحيحة: D
السؤال #22
A Belt will occasionally do a quick experiment referred to as an OFAT which stands for____________________.
A. nly a Few Are Tested
B. pposite Factors Affect Technique
C. ne Factor At a Time
D. rdinary Fractional Approach Technique
عرض الإجابة
اجابة صحيحة: C
السؤال #23
Bias in Sampling is an error due to lack of independence among random samples or due to systematic sampling procedures.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #24
While management of a company must set the stage for all improvement efforts, which of these 5S’s is primarily driven by management?
A. traighten
B. ort
C. hine
D. ustain
عرض الإجابة
اجابة صحيحة: D
السؤال #25
A periodic time frame can be used to arrange for Control Limit and Center Line calculations withgood SPC implementation in a process.
A. rue
B. alse
عرض الإجابة
اجابة صحيحة: A
السؤال #26
Select all the statements that are true after reviewing the Capability Analysis shown here. (Note:There are 4 correct answers).
A. The process is out of Control
B. The process is properly assumed to be a Normal process
C. The Mean of the process moving range is 1
D. This Capability Analysis used subgroups
E. Majority of the dimensional values are outside of the tolerance than within
عرض الإجابة
اجابة صحيحة: BCDE
السؤال #27
After reviewing the Capability Analysis shown here select the statement(s) that are untrue.
A. The process is properly assumed to be a Normal process
B. The Mean of the process moving range is 1
C. The process is out of Control
D. This Capability Analysis used subgroups
E. Majority of the dimensional values are outside of the tolerance than within
عرض الإجابة
اجابة صحيحة: A
السؤال #28
When analyzing a data set we frequently graph one metric as a function of another. If the slope of the Correlation line is -2.5 we would say the two metrics are ___________ correlated?
A. Positively
B. Not
C. Negatively
D. None
عرض الإجابة
اجابة صحيحة: C
السؤال #29
A periodic time frame can be used to arrange for Control Limit and Center Line calculations with good SPC implementation in a process.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #30
__________ Distributions occur when data comes from several sources that are supposed to be the same yet are not.
A. Skewed
B. Bimodal
C. Gaussian
D. Tri-peaked
عرض الإجابة
اجابة صحيحة: A
السؤال #31
Select all the statements that are true after reviewing the Capability Analysis shown here. (Note:There are 4 correct answers).
A. The process is out of Control
B. The process is properly assumed to be a Normal process
C. The Mean of the process moving range is 1
D. This Capability Analysis used subgroups
E. Majority of the dimensional values are outside of the tolerance than within
عرض الإجابة
اجابة صحيحة: BCDE
السؤال #32
Bias in Sampling is an error due to lack of independence among random samples or due to systematic sampling procedures.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #33
__________ Distributions occur when data comes from several sources that are supposed to be the same yet are not.
A. Skewed
B. Bimodal
C. Gaussian
D. Tri-peaked
عرض الإجابة
اجابة صحيحة: A
السؤال #34
A Six Sigma tool that helps to screen factors by using graphical techniques to logically subgroup multiple discrete X's plotted against a continuous Y is known as a _____________Chart.
A. SIPOC
B. Multi-Vari
C. Box Plot
D. Whisker
عرض الإجابة
اجابة صحيحة: B
السؤال #35
Which of the following tools is used extensively in quality function deployment (QFD)?Please choose the correct answer.
A. Affinity diagram
B. Matrix diagram
C. Cause and effect diagram
D. Activity network diagram
عرض الإجابة
اجابة صحيحة: B
السؤال #36
A Belt concludes a Lean Six Sigma project with the creation of a Control Plan. At what point can theControl Plan be closed?
A. ever, a Control Plan is a living document
B. s soon as the Champion signs off
C. ithin 30 days of the LSS project review team meeting
D. fter the project has been presented at the recognition event
عرض الإجابة
اجابة صحيحة: A
السؤال #37
When it comes to Control one of the most effective means of eliminating defects is to _________________ .
A. Train personnel often and thoroughly
B. Keep a Six Sigma project going on the process at all times
C. Design defect prevention into the product
D. Have each process consist of no more than five steps
عرض الإجابة
اجابة صحيحة: C
السؤال #38
Which of the following is an example of mistake-proofing?Please choose the correct answer.
A. Using x and R chart to prevent errors
B. Using 100% inspection to detect and contain defects
C. Using color coding as an error signal
D. Having the team that created the errors repair them
عرض الإجابة
اجابة صحيحة: C
السؤال #39
The Lean Principle action in the 5S approach that deals with having those items needed regularly at hand and those items need less regularly stored out of the way is known as ___________.
A. AShining
B. BStandardizing
C. CSustaining
D. DSorting
عرض الإجابة
اجابة صحيحة: D
السؤال #40
The Regression Model for an observed value of Y contains the term ?o which represents the Y axis intercept when X = 0.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #41
Typically a person who is trained to the skill level of a Black Belt is nearly 80% dedicated to applying Lean Six Sigma methodologies towards process solutions.
A. True
B. False
عرض الإجابة
اجابة صحيحة: B
السؤال #42
After a Belt has put data through the smoothing process which chart would be used to look for trendsin the data?
A. oving Average Chart
B. ulti-Vari Chart
C. bar Chart
D. areto Chart
عرض الإجابة
اجابة صحيحة: A
السؤال #43
Significant variation in process performance is a consequence of several causes that can be classified using which of the terminologies shown. (Note: There are 2 correct answers).
A. Common
B. Random
C. Uneducated
D. Special
E. Vital
عرض الإجابة
اجابة صحيحة: AD
السؤال #44
__________ Distributions occur when data comes from several sources that are supposed to be the same yet are not.
A. Skewed
B. Bimodal
C. Gaussian
D. Tri-peaked
عرض الإجابة
اجابة صحيحة: A
السؤال #45
According to the definition of Rolled Throughput Yield which of these items best describe the purpose of RTY?
A. A function of Y=f(x)
B. Accounts for losses due to rework and scrap
C. Isolates the increase throughput
D. Determines incremental Growth
عرض الإجابة
اجابة صحيحة: B
السؤال #46
__________ Distributions occur when data comes from several sources that are supposed to be the same yet are not.
A. Skewed
B. Bimodal
C. Gaussian
D. Tri-peaked
عرض الإجابة
اجابة صحيحة: A
السؤال #47
Bias in Sampling is an error due to lack of independence among random samples or due to systematic sampling procedures.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #48
A primary benefit of using a Multi-Vari Chart is it provides a visual presentation of two-way interactions.
A. True
B. False
عرض الإجابة
اجابة صحيحة: A
السؤال #49
The Lean Principle action in the 5S approach that deals with having those items needed regularly at hand and those items need less regularly stored out of the way is known as ___________.
A. Shining
B. Standardizing
C. Sustaining
D. Sorting
عرض الإجابة
اجابة صحيحة: D
السؤال #50
A Lean Principle that addresses efficiency by the process worker is called ____________________?
A. Visual Factory
B. Supervising
C. Training
D. Standardizing
عرض الإجابة
اجابة صحيحة: D

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف:
Contact Us