Component project managers create project management plans for all component projects in a program. The program manager notices that some project managers prefer one status report template while others prefer another How should the program manager decide which template is appropriate?
A. Review the issue with the program management office (PMO) to determine which template to use
B. Review the issue with the project managers and come to mutual agreement on which template to usecorrect
C. Meet with the program governance board to select an appropriate template
D. Allow the component project managers to use their preferred templates
عرض الإجابة
اجابة صحيحة: B
السؤال #2
Which electrical characteristic is displayed with the correct preferred value?
A. Dielectric constant – high value
B. Dielectric strength – high value
C. Dissipation factor – low value
D. Insulation resistance - high value
عرض الإجابة
اجابة صحيحة: A
السؤال #3
Telecommunications cabling (e.g., voice, data, video, security, audio, control) can be damaged during the construction phases of rough-in, drywall installation, and during the siding of the exterior. For these reasons, telecommunications cabling shall be acceptance tested. Acceptance testing includes visual examination and verification of all cabling and qualification of copper cabling for data cabling or certification of copper or optical fiber cabling for data cabling. Verification testing is generally pe
A. Post the acceptance of the construction contract once the Project Manager has approved this phase
B. Prior to the installation of insulation and drywall
C. Prior to the installation of the cable tray system for spurs, points that would or could damage the cable infrastructure
D. During the trim-out stage of the cabling after painting
E. Post the implementation of the construction
عرض الإجابة
اجابة صحيحة: BD
السؤال #4
What is the FIRST step in quality evolution (focused on physical quality) when developing a quality plan?
A. Qualitative risk analysis
B. Client satisfaction
C. Conformance
D. Client value
E. Quantitative risk analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #5
Using an earth ground resistance tester, what is the recommended MAXIMUM value for resistance between any two points along the entire length of a bonding or grounding conductor (not including the earth electrode system)?
A. 0
B. 2 ohms
C. 1 ohm
D. 0
E. 0
عرض الإجابة
اجابة صحيحة: C
السؤال #6
Exhibit: In this future marina layout, what would be the pre - cabling guideline to follow for the terminal A?
A. Place distribution cable onto the dock and terminate in a suitable cabinet or enclosure
B. Provide one or two pair cables from the boat slips to a distribution terminal on the closest point of land
C. Pre - cable each boat slip during construction
D. For security, each run should be terminated in the patch panel/ cross - connect at the dockmaster or marina office
عرض الإجابة
اجابة صحيحة: A
السؤال #7
Which two of the following items MUST be included in a detailed SoW? (Select two options.)
A. What type of work needs to be performedcorrect
B. A general description of work to be performed
C. Who must approve the Scope of work
D. How the contract performance will be evaluated/judged
E. When the work will startcorrect
عرض الإجابة
اجابة صحيحة: AE
السؤال #8
What is the connector of choice for Series 59, Series 6, and Series 11 applications?
A. -Style
B. ayonet Neill-Conncelman (BNC-Style)
C. -Style
D. MA
E. ltra high frequency (UHF)
عرض الإجابة
اجابة صحيحة: A
السؤال #9
A program is developing a next-gene ration product line, and one component has been delivered. However, due to a change request, expectations for another component are unmet What activity should the program manager perform next?
A. Program delivery management
B. Benefits sustainment and program transition
C. Program performance monitoring and controlling
D. Resource Interdependency management
عرض الإجابة
اجابة صحيحة: D
السؤال #10
A program manager is appointed to manage a new program. The organization's leadership has specified a list of benefits (hat the program should deliver and has requested that the program manager determine when incremental benefits can be realized. What should the program manager do first?
A. Develop the benefits sustainment plan
B. Develop the program management plan
C. Develop the program roadmapcorrect
D. Develop the component project schedules
عرض الإجابة
اجابة صحيحة: C
السؤال #11
When designing cable tray pathways under an access floor, what is the MINIMUM free space that should exist between the top of the cable tray side rails and the underside of the stringers?
A. 51 mm (2 in)
B. 101
C. 71 mm (3 in)
D. 25 mm (1 in)
عرض الإجابة
اجابة صحيحة: D
السؤال #12
Which type of protection for electrical power stations provide isolation against a rise in potential of station ground and also provide drainage protection against longitudinally-induced voltages?
A. Isolating transformers
B. Neutralizing transformerscorrect
C. Mutual drainage reactors
D. Unit-type neutralizing transformers
E. 2-winding neutralizing transformers
عرض الإجابة
اجابة صحيحة: B
السؤال #13
Which of the following is a method that an ICT distribution designer would use for clash detection with other disciplines?
A. ICT pathway design
B. Interference Fit Verification
C. Statistical Quantitative Analysis
D. Building Information Modeling Coordination
عرض الإجابة
اجابة صحيحة: D
السؤال #14
The type of apparatus housed in ERs varies greatly in size, purpose and function. Which two of the following active equipment is included? (Select two options.)
A. Cross-connect facilitiescorrect
B. Telecommunication’s equipmentcorrect
C. Environmental controls
D. Lighting controls
E. Building system equipmentcorrect
عرض الإجابة
اجابة صحيحة: ABE
السؤال #15
The information technology system (ITS) designer should design conduits entering a building from ceiling height to terminate ________ below the finished ceiling.
A. 51 mm (2 in)
B. 100 mm (4 in)
C. 203 mm (8 in)
D. 152 mm (6 in)
E. 254 mm (10 in)
عرض الإجابة
اجابة صحيحة: B
السؤال #16
A software company's program manager is conducting closing procedures for a program. At the last steering committee meeting, realized benefits were presented to the program governance board. What should the program manager do next?
A. Begin transitioning program resources, and update the resource and program management plans to reflect the change in the program's status
B. initiate knowledge transfer with the receiving organization, and establish the program integration management plan
C. Update the financial stakeholder, and contract management plans and archive them in the program information repository
D. Obtain sponsoring organization approval to begin closeout procedures to transition benefits sustainment to the supporting organizationcorrect
عرض الإجابة
اجابة صحيحة: D
السؤال #17
Which characteristic is an advantage of copper based media over optical fiber cable?
A. Weight
B. Corrosion resistance
C. Ability to handle analog signals
D. Susceptibility to EMI
E. Very high data rates
عرض الإجابة
اجابة صحيحة: C
السؤال #18
A project's installation start involves a Kickoff Meeting and the General Contractor's Coordination Meeting. As part of the designer's responsibilities, which two of the following ate key elements of the Kick-off Meeting? (Select two options.)
A. Project submittal approval processcorrect
B. RFI processcorrect
C. Payment procedures
D. Punch List process
E. Project start and completion dates
عرض الإجابة
اجابة صحيحة: AB
السؤال #19
What is the derating factor for a 24 AWG (0.51 mm) stranded cords?
A. 10%
B. 20%correct
C. 30%
D. 50%
E. 60%
عرض الإجابة
اجابة صحيحة: B
السؤال #20
The signal at the input to a balanced twisted pair cable is 10 mW. The cable is 1000 feet long and has an attenuation of 1 dB per 100 feet. This cable is connected to the input of a receiver. The noise level at the input to the receiver is 1 microwatt. What is the signal-to-noise ratio (SNR) (dB) at the receiver input?
A. 10 dB
B. 30 dB
C. 40 dB
D. 60 dB
E. 100 dB
عرض الإجابة
اجابة صحيحة: B
السؤال #21
Several issues are identified on one component project in a program During a meeting with that component's project manager, the program manager offers several suggested resolutions Two weeks later, they meet again to review progress. The project manager had reviewed the issues and suggested resolutions, but delayed a decision. This two-week delay in taking action caused delays in the project schedule What should the program manager do?
A. Join project-level issue resolution meetings to accelerate the decision-making process
B. Initiate discussions with the program governance board about assigning a more experienced project manager to the project
C. Emphasize that the project manager needs to address the issues and follow up at the next scheduled meeting
D. Develop an immediate corrective action plan with the project manager and coach them on decision-making responsibilitiescorrect
عرض الإجابة
اجابة صحيحة: D
السؤال #22
A fire ________ is a contained area that is completely enclosed by fire resistant walls, floors, and ceilings.
A. Rated system
B. Wall
C. Stop system
D. Zone
عرض الإجابة
اجابة صحيحة: D
السؤال #23
An ICT distribution designer working for the owner receives a submitted product that differs from the product specified in the contract documents. The original product is unavailable due to shipping or manufacturing delay. Which action should the ICT distribution designer take?
A. Reject the submittal after verifying compliance with applicable standards
B. Approve the submittal after asking about additional compensating warranty offerings
C. Approve the submittal after verifying code compliance
D. Approve the submittal after verifying all significant features of the originally specified product are met
عرض الإجابة
اجابة صحيحة: C
السؤال #24
The distance a CCTV signal may be run is determined by the strength of the signal at the source, required signal strength at the receiver, and:
A. Video format
B. Recorded image
C. Signal loss of the cable
D. Power requirement of the receiving device
عرض الإجابة
اجابة صحيحة: C
السؤال #25
A program manager joins a learn to fix a troubled enterprise-wide customer relationship management (CHM) system Analysis indicates that duplicate customer information data is resulting in redundant client information. The program manager accesses the knowledge repository tor similar programs to gather historical data and trends. A corrective action is identified, and a change in process is implemented to regain data integrity What should the program manager do with the knowledge gained from this activity?
A. Include the lessons learned in the weekly program report
B. Update the communications management plan
C. Update the lessons learned database
D. Communicate the corrective action to the program sponsor
عرض الإجابة
اجابة صحيحة: C
السؤال #26
Which of the following is used to create an electronic signal that can be sent to the central nurse call equipment?
A. Initiation device
B. Headend module
C. Notification device
D. Two tone device
عرض الإجابة
اجابة صحيحة: A
السؤال #27
What is a simplified cone of protection for lightning strikes as it pertains to a structure (building, pole, etc.)?
A. 43 m (140 ft)
B. A base diameter equal to the height of the structure
C. A base radius equal to the height of the structure
D. 50% of the height of the structure in any direction
عرض الإجابة
اجابة صحيحة: C
السؤال #28
Which stakeholder of a project team is responsible to provide closeout documentation to the client? Architect
A. Authority
B. Having Jurisdiction (AHJ)
C. Construction Managercorrect
D. ICT Distribution Designer/Project Manager
عرض الإجابة
اجابة صحيحة: C
السؤال #29
A company's marketing department Tails an internal compliance audit. To comply with the auditor's remediation plan the legal department mandates that a content management system (CMS) be implemented After initiating the program for CMS implementation the program manager discovers that the marketing department has already preselected which CMS technology will be implemented. What should the program manager do to ensure the success of the program?
A. Host a kick-off meeting, request preliminary requirements from the marketing department, conduct a design session present the steering committee with a solution that meets the requirements: and meet with interested vendors
B. Initiate the program and begin a formal request for proposal (RFP) to validate the chosen solution and gam the confidence of the legal department
C. Meet with the vice president of purchasing to discuss the risks associated with preselecting a solution before the requirements have been gathered
D. Ask a senior marketing executive to act as the program sponsor and participate on the steering committee: require steering committee representation from the IT legal, and other key departments, validate that the chosen solution meets the requirements
عرض الإجابة
اجابة صحيحة: D
السؤال #30
A 24 port layer 2 switch can perform all of the following functions EXCEPT:
A. Bridge
B. Route
C. Link aggregation
D. Full duplex operation
عرض الإجابة
اجابة صحيحة: B

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: