السؤال #1
What is the most important factor to consider when revising acceptance criteria based on insights from periodic quality reports?
A. Ensuring the revisions meet the preferences of the project management team
B. Ensuring the revised criteria align with identified quality trends and project objectivescorrect
C. The frequency with which the criteria have been revised during the project
D. The level of stakeholder agreement with the proposed revisions
عرض الإجابة
اجابة صحيحة: B
السؤال #2
How should a construction quality manager create a system to manage NCRs and CARs effectively within a large-scale infrastructure project?
A. Implement a manual tracking system using paper forms and distribute to senior management
B. Use an email-based system for submitting and tracking all NCRs and CARs
C. Develop an integrated digital tracking system that allows for real-time updatescorrect
D. Limit access to NCR and CAR submissions to senior management only
عرض الإجابة
اجابة صحيحة: C
السؤال #3
ow should CoQ data be interpreted to derive meaningful insights?
A. ASummarize the data into high-level categories to simplify reporting
B. BAnalyze trends over time and correlations with project outcomes
C. CFocus interpretation on the highest cost areas
D. DInterpret data in isolation from other project metrics
عرض الإجابة
اجابة صحيحة: B
السؤال #4
Which of the following approaches would best assess the alignment of permanent work specifications with a project's quality plan?
A. Evaluating the integration of technology in the construction processes
B. Conducting periodic inspections of work progress for adherence to specifications
C. Reviewing compliance reports against the quality plancorrect
D. Reviewing corrective actions implemented from previous quality audits
عرض الإجابة
اجابة صحيحة: C
السؤال #5
What is a key benefit of outsourcing quality control processes to third - party services?
A. Reducing the need for internal training
B. Gaining access to specialized expertise
C. Reducing the responsibilities of the internal quality team
D. Streamlining processes by minimizing oversight from internal quality teams
عرض الإجابة
اجابة صحيحة: B
السؤال #6
When evaluating the implementation of a warranty program, what is the most critical factor to confirm regarding stakeholder engagement?
A. Stakeholders can modify the warranty terms
B. Stakeholders are regularly surveyed for their satisfaction with the warranty
C. Stakeholders are informed of their rights and responsibilities under the warranty
D. Stakeholders can receive a survey regarding the warranty
عرض الإجابة
اجابة صحيحة: C
السؤال #7
It is important to document all quality control (QC) activities and results to
A. provide content for marketing materials
B. enhance external communication
C. maintain a record of conformancecorrect
D. simplify the project closure process
عرض الإجابة
اجابة صحيحة: C
السؤال #8
Which of the following criteria is essential when evaluating the completeness of quality deliverables at project closeout?
A. The deliverables include feedback from all stakeholders
B. The deliverables are approved by the project manager
C. The deliverables meet the specified quality standards
D. The deliverables have been submitted on time
عرض الإجابة
اجابة صحيحة: C
السؤال #9
How does the prequalification process impact the project's risk management strategy?
A. It provides a framework for emergency responses
B. It increases the likelihood of contractor preparedness in supporting project outcomes
C. It enables faster implementation of change orders and continuous assessment of project risks
D. It facilitates the allocation of resources across project phases
عرض الإجابة
اجابة صحيحة: B
السؤال #10
How should a quality manager address conflicting feedback from different disciplines during the design process?
A. By choosing the feedback from the most technically advanced discipline
B. By avoiding conflicting feedback to prevent delays in the design process
C. By considering feedback from the highest authority in the project hierarchy
D. By facilitating a consensus-building session to align feedback with project quality objectives
عرض الإجابة
اجابة صحيحة: D
السؤال #11
When designing a system to ensure all subcontractors and vendors comply with specific standards relevant to a high-stakes construction project, what elements are crucial to include to guarantee continuous adherence to these standards?
A. APeriodically update compliance standards and inform subcontractors and vendors if major changes occur
B. BFocus on internal compliance, trusting subcontractors and vendors to manage their adherence independently
C. CAssume compliance is maintained if no major changes occur throughout the project
D. DImplement a continuous monitoring system that includes scheduled audits and real-time compliance tracking
عرض الإجابة
اجابة صحيحة: D
السؤال #12
When conducting an authority having jurisdiction (AHJ) review, what should be the primary focus to effectively analyze the project's adherence to established criteria?
A. The number of past successful projects completed without AHJ interventions
B. General industry standards associated with the project
C. The specific requirements set by the AHJcorrect
D. The experience of the construction team with AHJ personnel
عرض الإجابة
اجابة صحيحة: C

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: