السؤال #1
What is the probability of occurrence if the risk rating is 0.56 and the impact if the risk does occur is very high (0.80)?
A. 0
B. 0
C. 0
D. 1
عرض الإجابة
اجابة صحيحة: A
السؤال #2
Which of the seven basic quality tools is especially useful for gathering attributes data while performing inspections to identify defects?
A. Histograms
B. Scatter diagrams
C. Flowcharts
D. Checksheets
عرض الإجابة
اجابة صحيحة: B
السؤال #3
The most commonly used type of precedence relationship in the precedence diagramming method (PDM) is:
A. start-to-start (SS)
B. start-to-finish (SF)
C. finish-to-start (FS)
D. finish-to-finish (FF)
عرض الإجابة
اجابة صحيحة: B
السؤال #4
Work performance information and cost forecasts are outputs of which Project Cost Management process?
A. Estimate Costs
B. Plan Cost Management
C. Determine Budget
D. Control Costs
عرض الإجابة
اجابة صحيحة: B
السؤال #5
Which technique should a project manager use in a situation in which a collaborative approach to conflict management is not possible?
A. Coaching
B. Avoidance
C. Consensus
D. Influencing
عرض الإجابة
اجابة صحيحة: A
السؤال #6
The procurement process that documents agreements and related documentation for future reference is known as:
A. Plan Procurements
B. Control Procurements
C. Close Procurements
D. Conduct Procurements
عرض الإجابة
اجابة صحيحة: C
السؤال #7
The links between the processes in the Process Groups are often:
A. Intuitive
B. Iterative
C. Measured
D. Monitored
عرض الإجابة
اجابة صحيحة: D
السؤال #8
The scope of a project cannot be defined without some basic understanding of how to create the specified:
A. objectives
B. schedule
C. product
D. approach
عرض الإجابة
اجابة صحيحة: A
السؤال #9
The creation of an internet site to engage stakeholders on a project is an example of which type of communication?
A. Push
B. Pull
C. Interactive
D. Iterative
عرض الإجابة
اجابة صحيحة: A
السؤال #10
Which component of the human resource management plan describes when and how project team members are acquired and how long they will be needed?
A. Resource breakdown structure
B. Staffing management plan
C. Project organizational chart
D. Scope management plan
عرض الإجابة
اجابة صحيحة: D
السؤال #11
The process of formalizing acceptance of the completed project deliverables is known as:
A. Validate Scope
B. Close Project or Phase
C. Control Quality
D. Verify Scope
عرض الإجابة
اجابة صحيحة: D
السؤال #12
An output of Control Schedule is:
A. A project schedule network diagram
B. A schedule management plan
C. Schedule data
D. Schedule forecasts
عرض الإجابة
اجابة صحيحة: A
السؤال #13
What is the name of the statistical method that helps identify which factors may influence specific variables of a product or process under development or in production?
A. Failure modes and effects analysis
B. Design of experiments
C. Quality checklist
D. Risk analysis
عرض الإجابة
اجابة صحيحة: B
السؤال #14
Which is the Define Scope technique used to generate different approaches to execute and perform the work of the project?
A. Build vs
B. Expert judgment
C. Alternatives identification
D. Product analysis
عرض الإجابة
اجابة صحيحة: A
السؤال #15
Most experienced project managers know that:
A. every project requires the use of all processes in the PMBOK? Guide
B. there is no single way to manage a project
C. project management techniques are risk free
D. there is only one way to manage projects successfully
عرض الإجابة
اجابة صحيحة: D
السؤال #16
What is an objective of the Develop Project Team process?
A. Feelings of trust and improved cohesiveness
B. Ground rules for interaction
C. Enhanced resource availability
D. Functional managers becoming more involved
عرض الإجابة
اجابة صحيحة: A
السؤال #17
The product scope description is used to:
A. Gain stakeholders' support for the project
B. Progressively elaborate the characteristics of the product, service, or result
C. Describe the project in great detail
D. Define the process and criteria for accepting a completed product, service, or result
عرض الإجابة
اجابة صحيحة: B
السؤال #18
Which technique is used in Perform Quantitative Risk Analysis?
A. Sensitivity analysis
B. Probability and impact matrix
C. Risk data quality assessment
D. Risk categorization
عرض الإجابة
اجابة صحيحة: A
السؤال #19
Which illustrates the connection between work that needs to be done and its project team members?
A. Work breakdown structure (WBS)
B. Network diagrams
C. Staffing management plan
D. Responsibility assignment matrix (RAM)
عرض الإجابة
اجابة صحيحة: A
السؤال #20
Which tools or techniques will a project manager use for Develop Project Team?
A. Negotiation
B. Roles and responsibilities
C. Recognition and rewards
D. Prizing and promoting
عرض الإجابة
اجابة صحيحة: D
السؤال #21
Which of the following is an input to Direct and Manage Project Execution?
A. Requested changes
B. Approved change requests
C. Work performance information
D. Implemented defect repair
عرض الإجابة
اجابة صحيحة: C
السؤال #22
Which of the following is TRUE about most project life cycles?
A. Staffing level is highest at the start
B. The stakeholders' influence is highest at the start
C. The level of uncertainty is lowest at the start
D. The cost of changes is highest at the start
عرض الإجابة
اجابة صحيحة: D
السؤال #23
An input required in Define Scope is an organizational:
A. structure
B. process asset
C. matrix
D. breakdown structure
عرض الإجابة
اجابة صحيحة: C
السؤال #24
What cost control technique is used to compare actual project performance to planned or expected performance?
A. Cost aggregation
B. Trend analysis
C. Forecasting
D. Variance analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #25
What is the term assigned to products or services having the same functional use but different technical characteristics?
A. Scope
B. Quality
C. Specification
D. Grade
عرض الإجابة
اجابة صحيحة: B
السؤال #26
When is a Salience Model used?
A. In a work breakdown structure (WBS)
B. During quality assurance
C. In stakeholder analysis
D. During quality control (QC)
عرض الإجابة
اجابة صحيحة: C
السؤال #27
Which of the following is contained within the communications management plan?
A. An organizational chart
B. Glossary of common terminology
C. Organizational process assets
D. Enterprise environmental factors
عرض الإجابة
اجابة صحيحة: B
السؤال #28
Which of the following is a tool and technique for Estimate Activity Durations?
A. Parametric estimating
B. Monte Carlo analysis
C. Alternatives analysis
D. Bottom-up estimating
عرض الإجابة
اجابة صحيحة: C
السؤال #29
Projects can be divided into phases to provide better management control. Collectively, what are these phases known as?
A. Complete project phase
B. Project life
C. The project life cycle
D. Project cycle
عرض الإجابة
اجابة صحيحة: B
السؤال #30
Which schedule network analysis technique modifies the project schedule to account for limited resources?
A. Human resource planning
B. Fast tracking
C. Critical chain method
D. Rolling wave planning
عرض الإجابة
اجابة صحيحة: B
السؤال #31
Which of the following is an output of the Monitor and Control Project Work process?
A. Change requests
B. Performance reports
C. Organizational process assets
D. Project management plan
عرض الإجابة
اجابة صحيحة: A
السؤال #32
Which of the following statements correctly characterizes pull communication?
A. It includes letters, memos, reports, emails, and faxes
B. It requires recipients to access communication content at their own discretion
C. It is the most efficient way to ensure a common understanding among all participants
D. It is primarily used when the volume of information to be transferred is minimal
عرض الإجابة
اجابة صحيحة: D
السؤال #33
When would resource leveling be applied to a schedule model?
A. Before constraints have been identified
B. Before it has been analyzed by the critical path method
C. After it has been analyzed by the critical path method
D. After critical activities have been removed from the critical path
عرض الإجابة
اجابة صحيحة: B
السؤال #34
Which Knowledge Area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project information?
A. Project Integration Management
B. Project Communications Management
C. Project Information Management System (PIMS)
D. Project Scope Management
عرض الإجابة
اجابة صحيحة: C
السؤال #35
Which of the following tools or techniques is used for Estimate Activity Durations?
A. Critical path method
B. Rolling wave planning
C. Precedence diagramming method
D. Parametric estimating
عرض الإجابة
اجابة صحيحة: B
السؤال #36
What is the number of stakeholders, if the project has 28 potential communication channels?
A. 7
B. 8
C. 14
D. 16
عرض الإجابة
اجابة صحيحة: A
السؤال #37
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
A. Mitigate
B. Transfer
C. Share
D. Avoid
عرض الإجابة
اجابة صحيحة: B
السؤال #38
Which activity is an input to the Conduct Procurements process?
A. Organizational process assets
B. Resource availability
C. Perform Integrated Change Control
D. Team performance assessment
عرض الإجابة
اجابة صحيحة: A
السؤال #39
Which of the following investigates the likelihood that each specific risk will occur?
A. Risk register
B. Risk audits
C. Risk urgency assessment
D. Risk probability and impact assessment
عرض الإجابة
اجابة صحيحة: D
السؤال #40
What is a hierarchically organized depiction of the identified project risks arranged by risk category?
A. Risk register
B. Risk breakdown structure (RBS)
C. Risk management plan
D. Risk category
عرض الإجابة
اجابة صحيحة: C
السؤال #41
Which tool or technique of Plan Quality involves comparing actual or planned practices to those of other projects to generate ideas for improvement and provide a basis by which to measure performance?
A. Histogram
B. Quality audits
C. Benchmarking
D. Performance measurement analysis
عرض الإجابة
اجابة صحيحة: B
السؤال #42
Taking out insurance in relation to risk management is called what?
A. Transference
B. Avoidance
C. Exploring
D. Mitigation
عرض الإجابة
اجابة صحيحة: B
السؤال #43
Which estimating technique uses the actual costs of previous similar projects as a basis for estimating the costs of the current project?
A. Analogous
B. Parametric
C. Bottom-up
D. Top-down
عرض الإجابة
اجابة صحيحة: B
السؤال #44
What is the difference between the critical path and the critical chain?
A. Scope changes
B. Resource limitations
C. Risk analysis
D. Quality audits
عرض الإجابة
اجابة صحيحة: D
السؤال #45
Which of the following is an enterprise environmental factor that can influence the Develop Project Charter process?
A. Organizational standard processes
B. Marketplace conditions
C. Historical information
D. Templates
عرض الإجابة
اجابة صحيحة: D
السؤال #46
The Define Scope process is in which of the following Process Groups?
A. Initiating
B. Planning
C. Monitoring and Controlling
D. Executing
عرض الإجابة
اجابة صحيحة: C
السؤال #47
Organizations perceive risks as:
A. events that will inevitably impact project and organizational objectives
B. the effect of uncertainty on their project and organizational objectives
C. events which could have a negative impact on project and organizational objectives
D. the negative impact of undesired events on their project and organizational objectives
عرض الإجابة
اجابة صحيحة: B
السؤال #48
In an organization with a projectized organizational structure, who controls the project budget?
A. Functional manager
B. Project manager
C. Program manager
D. Project management office
عرض الإجابة
اجابة صحيحة: A
السؤال #49
Who, along with the project manager, is supposed to direct the performance of the planned project activities and manage the various technical and organizational interfaces that exist within the project?
A. The customer and functional managers
B. The risk owners and stakeholders
C. The sponsors and stakeholders
D. The project management team
عرض الإجابة
اجابة صحيحة: C
السؤال #50
Who selects the appropriate processes for a project?
A. Project stakeholders
B. Project sponsor and project stakeholder
C. Project manager and project team
D. Project manager and project sponsor
عرض الإجابة
اجابة صحيحة: C
السؤال #51
The scope management plan is a subsidiary of which project document?
A. Schedule management plan
B. Project management plan
C. Quality management plan
D. Resource management plan
عرض الإجابة
اجابة صحيحة: A
السؤال #52
Which is an example of Administer Procurements?
A. Negotiating the contract
B. Authorizing contractor work
C. Developing the statement of work
D. Establishing evaluation criteria
عرض الإجابة
اجابة صحيحة: B
السؤال #53
An input to the Create WBS process is a:
A. project charter
B. stakeholder register
C. project scope statement
D. requirements traceability matrix
عرض الإجابة
اجابة صحيحة: C
السؤال #54
An input of the Control Schedule process is the:
A. resource calendar
B. activity list
C. risk management plan
D. organizational process assets
عرض الإجابة
اجابة صحيحة: B
السؤال #55
The Verify Scope process is primarily concerned with:
A. formalizing acceptance of the completed project deliverables
B. accuracy of the work deliverables
C. formalizing approval of the scope statement
D. accuracy of the work breakdown structure (WBS)
عرض الإجابة
اجابة صحيحة: D
السؤال #56
What is the total float of the critical path?
A. Can be any number
B. Zero or positive
C. Zero or negative
D. Depends on the calendar
عرض الإجابة
اجابة صحيحة: B
السؤال #57
Portfolio Management is management of:
A. a project by dividing the project into more manageable sub-projects
B. a project by utilizing a portfolio of general management skills such as planning, organizing, staffing, executing, and controlling
C. all projects undertaken by a company
D. a collection of projects that are grouped together to facilitate effective management and meet strategic business objectives
عرض الإجابة
اجابة صحيحة: B
السؤال #58
Which action should a project manager take to ensure that the project management plan is effective and current?
A. Conduct periodic project performance reviews
B. Identify quality project standards
C. Follow ISO 9000 quality standards
D. Complete the quality control checklist
عرض الإجابة
اجابة صحيحة: C
السؤال #59
While implementing an approved change, a critical defect was introduced. Removing the defect will delay the product delivery. What is the MOST appropriate approach to managing this situation?
A. Utilize the change control process
B. Crash the schedule to fix the defect
C. Leave the defect in and work around it
D. Fast-track the remaining development
عرض الإجابة
اجابة صحيحة: A
السؤال #60
Which tool and technique identifies inefficient and ineffective policies, processes, and procedures?
A. Scope audits
B. Scope reviews
C. Quality audits
D. Control chart
عرض الإجابة
اجابة صحيحة: D
السؤال #61
Which type of analysis would be used for the Plan Quality process?
A. Schedule
B. Checklist
C. Assumption
D. Cost-Benefit
عرض الإجابة
اجابة صحيحة: B
السؤال #62
The integrative nature of project management requires which Process Group to interact with the other Process Groups?
A. Planning
B. Executing
C. Monitoring and Controlling
D. Project Management
عرض الإجابة
اجابة صحيحة: C
السؤال #63
Which is a tool or technique used in Define Scope?
A. Templates, forms, and standards
B. Change requests
C. Product analysis
D. Project assumptions
عرض الإجابة
اجابة صحيحة: A
السؤال #64
Identifying major deliverables, deciding if adequate cost estimates can be developed, and identifying tangible components of each deliverable are all part of which of the following?
A. Work breakdown structure
B. Organizational breakdown structure
C. Resource breakdown structure
D. Bill of materials
عرض الإجابة
اجابة صحيحة: C
السؤال #65
Which type of analysis systemically gathers and analyzes qualitative and quantitative information to determine which interests should be taken into account throughout the project?
A. Product
B. Cost-benefit
C. Stakeholder
D. Research
عرض الإجابة
اجابة صحيحة: A
السؤال #66
Which of the following is an output of the Define Activities process?
A. Activity list
B. Project plan
C. Activity duration estimates
D. Project schedule
عرض الإجابة
اجابة صحيحة: B
السؤال #67
When is a project finished?
A. After verbal acceptance of the customer or sponsor
B. After lessons learned have been documented in contract closure
C. When the project objectives have been met
D. After resources have been released
عرض الإجابة
اجابة صحيحة: B
السؤال #68
Which process documents the business needs of a project and the new product, service, or other result that is intended to satisfy those requirements?
A. Develop Project Management Plan
B. Develop Project Charter
C. Direct and Manage Project Execution
D. Collect Requirements
عرض الإجابة
اجابة صحيحة: B
السؤال #69
Which Process Group typically consumes the bulk of a project's budget?
A. Monitoring and Controlling
B. Executing
C. Planning
D. Initiating
عرض الإجابة
اجابة صحيحة: B
السؤال #70
Which of the following involves making information available to project stakeholders in a timely manner?
A. Plan Communications
B. Performance reporting
C. Project status reports
D. Distribute Information
عرض الإجابة
اجابة صحيحة: B
السؤال #71
Which process uses occurrence probability and impact on project objectives to assess the priority of identified risks?
A. Identify Risks
B. Perform Qualitative Risk Analysis
C. Plan Risk Management
D. Perform Quantitative Risk Analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #72
What is one of the objectives of Project Risk Management?
A. Decrease the probability and impact of an event on project objectives
B. Distinguish between a project risk and a project issue so that a risk mitigation plan can be put in place
C. Increase the probability and impact of positive events
D. Removal of project risk
عرض الإجابة
اجابة صحيحة: A
السؤال #73
Which process involves documenting the actions necessary to define, prepare, integrate, and coordinate all subsidiary plans?
A. Collect Requirements
B. Direct and Manage Project Execution
C. Monitor and Control Project Work
D. Develop Project Management Plan
عرض الإجابة
اجابة صحيحة: C
السؤال #74
Which Project Management Process Group includes Collect Requirements, Define Activities, Sequence Activities, Perform Qualitative Risk Analysis, and Perform Quantitative Risk Analysis?
A. Initiating
B. Monitoring and Controlling
C. Planning
D. Closing
عرض الإجابة
اجابة صحيحة: B
السؤال #75
A work package has been scheduled to cost $1,000 to complete and was to be finished today. As of today, the actual expenditure is $1,200 and approximately half of the work has been completed. What is the cost variance?
A. -700
B. -200
C. 200
D. 500
عرض الإجابة
اجابة صحيحة: B
السؤال #76
Which type of managers do composite organizations involve?
A. Functional managers and manager of project managers
B. Functional managers only
C. Project managers only
D. Technical managers and project managers
عرض الإجابة
اجابة صحيحة: C
السؤال #77
Assigned risk ratings are based upon:
A. Root cause analysis
B. Risk probability and impact assessment
C. Expert judgment
D. Revised stakeholders' tolerances
عرض الإجابة
اجابة صحيحة: D
السؤال #78
Which tool is used to develop technical details within the project management plan?
A. Expert judgment
B. Project management methodology
C. Project management information system (PMIS)
D. Project selection methods
عرض الإجابة
اجابة صحيحة: A
السؤال #79
What is the name of a graphic display of project team members and their reporting relationships?
A. Role dependencies chart
B. Reporting flow diagram
C. Project organization chart
D. Project team structure diagram
عرض الإجابة
اجابة صحيحة: C
السؤال #80
Which of the following consists of the detailed project scope statement and its associatedWBSand WBS dictionary?
A. Scope plan
B. Product scope
C. Scope management plan
D. Scope baseline
عرض الإجابة
اجابة صحيحة: D
السؤال #81
What type of reward can hurt team cohesiveness?
A. Sole-sum
B. Win-lose
C. Lose-win
D. Partial-sum
عرض الإجابة
اجابة صحيحة: A
السؤال #82
What type of planning is used where the work to be accomplished in the near term is planned in detail, while work in the future is planned at a higher level?
A. Finish-to-start planning
B. Rolling wave planning
C. Short term planning
D. Dependency determination
عرض الإجابة
اجابة صحيحة: A
السؤال #83
Which Develop Schedule tool and technique produces a theoretical early start date and late start date?
A. Critical path method
B. Variance analysis
C. Schedule compression
D. Schedule comparison bar charts
عرض الإجابة
اجابة صحيحة: C
السؤال #84
Perform Quality Control is accomplished by:
A. Identifying quality standards that are relevant to the project and determining how to satisfy them
B. Monitoring and recording the results of executing the quality activities to assess performance and recommend necessary changes
C. Ensuring that the entire project team has been adequately trained in quality assurance processes
D. Applying Monte Carlo, sampling, Pareto analysis, and benchmarking techniques to ensure conformance to quality standards
عرض الإجابة
اجابة صحيحة: D
السؤال #85
Which type of estimating can produce higher levels of accuracy, depending upon the sophistication and underlying data built into the model?
A. Bottom-up
B. Three-point
C. Parametric
D. Analogous
عرض الإجابة
اجابة صحيحة: C
السؤال #86
Activity resource requirements and the resource breakdown structure (RBS) are outputs of which Project Time Management process?
A. Control Schedule
B. Define Activities
C. Develop Schedule
D. Estimate Activity Resources
عرض الإجابة
اجابة صحيحة: C
السؤال #87
Which of the following statements best describes the influence of stakeholders and the cost of changes as project time advances?
A. The influence of the stakeholders increases, the cost of changes increases
B. The influence of the stakeholders decreases, the cost of changes increases
C. The influence of the stakeholders increases, the cost of changes decreases
D. The influence of the stakeholders decreases, the cost of changes decreases
عرض الإجابة
اجابة صحيحة: A
السؤال #88
Which process includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
A. Perform Qualitative Risk Analysis
B. Perform Quantitative Risk Analysis
C. Plan Risk Management
D. Plan Risk Responses
عرض الإجابة
اجابة صحيحة: A
السؤال #89
A change log for communications can be used to communicate to the appropriate stakeholders that there are changes:
A. To the project management plan
B. To the risk register
C. In the scope verification processes
D. And their impact to the project in terms of time, cost, and risk
عرض الإجابة
اجابة صحيحة: C
السؤال #90
A procurement management plan is a subsidiary of which other type of plan?
A. Resource plan
B. Project management plan
C. Cost control plan
D. Expected monetary value plan
عرض الإجابة
اجابة صحيحة: A
السؤال #91
An electronics firm authorizes a new project to develop a faster, cheaper, and smaller laptop after improvements in the industry and electronics technology. With which of the following strategic considerations is this project mainly concerned?
A. Customer request
B. Market demand
C. Technological advance
D. Strategic opportunity
عرض الإجابة
اجابة صحيحة: C
السؤال #92
Which of the following processes are part of the Project Integration Management Knowledge Area?
A. Develop Project Management Plan, Collect Requirements, Create WBS
B. Develop Project Management Plan, Control Scope, Develop Schedule
C. Develop Project Charter, Define Scope, Estimate Costs
D. Develop Project Charter, Direct and Manage Project Execution, Close Project or Phase
عرض الإجابة
اجابة صحيحة: B
السؤال #93
To which process is work performance information an input?
A. Administer Procurements
B. Direct and Manage Project Execution
C. Create WBS
D. Perform Qualitative Risk Analysis
عرض الإجابة
اجابة صحيحة: B
السؤال #94
Which defines the portion of work included in a contract for items being purchased or acquired?
A. Procurement management plan
B. Evaluation criteria
C. Work breakdown structure
D. Procurement statement of work
عرض الإجابة
اجابة صحيحة: D
السؤال #95
Cost baseline is an output of which of the following processes?
A. Control Costs
B. Determine Budget
C. Estimate Costs
D. Estimate Activity Resources
عرض الإجابة
اجابة صحيحة: B
السؤال #96
Which group creativity technique asks a selected group of experts to answer questionnaires and provide feedback regarding the responses from each round of requirements gathering?
A. The Delphi technique
B. Nominal group technique
C. Affinity diagram
D. Brainstorming
عرض الإجابة
اجابة صحيحة: C
السؤال #97
At which point of the project is the uncertainty the highest and the risk of failing the greatest?
A. Final phase of the project
B. Start of the project
C. End of the project
D. Midpoint of the project
عرض الإجابة
اجابة صحيحة: D
السؤال #98
What type of project structure is a hierarchically organized depiction of the resources by type?
A. Organizational breakdown structure (OBS)
B. Resource breakdown structure (RBS)
C. Work breakdown structure (WBS)
D. Project breakdown structure (PBS)
عرض الإجابة
اجابة صحيحة: C
السؤال #99
When can pre-assignment of project team members occur?
A. When the project uses capital expenditures
B. When the required staff can be acquired from outside sources
C. When the project would be ignored due to travel expenses
D. When the project is the result of specific people being promised as part of a competitive proposal
عرض الإجابة
اجابة صحيحة: A
السؤال #100
Change requests are an output from which Project Integration Management process?
A. Direct and Manage Project Execution
B. Develop Project Management Plan
C. Close Project
D. Develop Project Charter
عرض الإجابة
اجابة صحيحة: A
السؤال #101
Which process involves aggregating the estimated costs of the individual schedule activities or work packages?
A. Estimate Costs
B. Estimate Activity Resources
C. Control Costs
D. Determine Budget
عرض الإجابة
اجابة صحيحة: B
السؤال #102
Plan Risk Management is the process of defining how to:
A. Communicate identified risks to the project stakeholders
B. Conduct risk management activities for a project
C. Analyze the impact a specific risk may have on the project
D. Address unexpected risks that may occur during a project
عرض الإجابة
اجابة صحيحة: A
السؤال #103
If the most likely duration of an activity is five weeks, the best-case duration is two weeks, and the worst-case duration is 14 weeks, how many weeks is the expected duration of the activity?
A. One
B. Five
C. Six
D. Seven
عرض الإجابة
اجابة صحيحة: C
السؤال #104
The CPI is .92, and the EV is US$172,500.What is the actual cost of the project?
A. US$158,700
B. US$172,500
C. US$187,500
D. US$245,600
عرض الإجابة
اجابة صحيحة: D
السؤال #105
Which type of analysis is used to examine project results through time to determine if performance is improving or deteriorating?
A. Control chart
B. Earned value
C. Variance
D. Trend
عرض الإجابة
اجابة صحيحة: B
السؤال #106
Which is one of the major outputs of Sequence Activities?
A. Responsibility assignment matrix (RAM)
B. Work breakdown structure (WBS) update
C. Project schedule network diagram
D. Mandatory dependencies list
عرض الإجابة
اجابة صحيحة: B
السؤال #107
What are the formal and informal policies, procedures, and guidelines that could impact how the project's scope is managed?
A. Organizational process assets
B. Enterprise environmental factors
C. Project management processes
D. Project scope management plan
عرض الإجابة
اجابة صحيحة: A
السؤال #108
Organizational planning impacts projects by means of project prioritization based on risk, funding, and an organizations:
A. Budget plan
B. Resource plan
C. Scope plan
D. Strategic plan
عرض الإجابة
اجابة صحيحة: B
السؤال #109
When does Monitor and Control Risks occur?
A. At project initiation
B. During work performance analysis
C. Throughout the life of the project
D. At project milestones
عرض الإجابة
اجابة صحيحة: C
السؤال #110
Conflict should be best addressed in which manner?
A. Early, in private, using a direct, collaborative approach
B. Early, in public, using an indirect, collaborative approach
C. Early, in private, using an indirect, cooperative approach
D. As late as possible, in public, using a direct, confrontational approach
عرض الإجابة
اجابة صحيحة: D
السؤال #111
The project management processes presented in the PMBOK Guide? should:
A. always be applied uniformly
B. be selected as appropriate by the sponsor
C. be selected as appropriate by the project team
D. be applied based on ISO guidelines
عرض الإجابة
اجابة صحيحة: B
السؤال #112
Which type of contract is most commonly used by buying organizations because the price for goods is set at the outset and is not subject to change unless the scope of work changes?
A. Fixed Price with Economic Price Adjustments Contract (FP-EPA)
B. Cost-Reimbursable Contract (CR)
C. Firm-Fixed -Price Contract (FFP)
D. Fixed-Price-Incentive-Fee Contract (FPIF)
عرض الإجابة
اجابة صحيحة: A
السؤال #113
Which schedule compression technique has phases or activities done in parallel that would normally have been done sequentially?
A. Crashing
B. Fast tracking
C. Leads and lags adjustment
D. Parallel task development
عرض الإجابة
اجابة صحيحة: D
السؤال #114
What name(s) is (are) associated with the Plan-Do-Check-Act cycle?
A. Pareto
B. Ishikawa
C. Shewhart-Deming
D. Delphi
عرض الإجابة
اجابة صحيحة: B
السؤال #115
A project management office manages a number of aspects including the:
A. Project scope, schedule, cost, and quality of the products of the work packages
B. Central coordination of communication management across projects
C. Assignment of project resources to best meet project objectives
D. Overall risk, overall opportunity, and interdependencies among projects at the enterprise level
عرض الإجابة
اجابة صحيحة: C
السؤال #116
Which of the following techniques is used during Control Scope?
A. Cost-benefit analysis
B. Variance analysis
C. Reserve analysis
D. Stakeholder analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #117
As part of a mid-project evaluation, the project sponsor has asked for a forecast of the total project cost. What should be used to calculate the forecast?
A. BAC
B. EAC
C. ETC
D. WBS
عرض الإجابة
اجابة صحيحة: C
السؤال #118
A weighting system is a tool for which area of Conduct Procurements?
A. Plan contracting
B. Requesting seller responses
C. Selecting seller's
D. Planning purchase and acquisition
عرض الإجابة
اجابة صحيحة: A
السؤال #119
Which type of chart is a graphic representation of a process showing the relationships among process steps?
A. Control
B. Bar
C. Flow
D. Pareto
عرض الإجابة
اجابة صحيحة: D
السؤال #120
What is the schedule performance index (SPI) using the following data? BAC = $100,000 PV = $50,000 AC = $80,000 EV = $40,000
A. 1
B. 0
C. 0
D. 0
عرض الإجابة
اجابة صحيحة: B
السؤال #121
What provides information regarding the ways people, teams, and organizational units behave?
A. Organizational chart
B. Organizational theory
C. Organizational structure
D. Organizational behavior
عرض الإجابة
اجابة صحيحة: A
السؤال #122
What is a deliverable-oriented, hierarchical decomposition of the work to be executed to accomplish the project objectives and create the required deliverables?
A. Organizational breakdown structure (OBS)
B. Work performance information
C. Work package
D. Work breakdown structure (WBS)
عرض الإجابة
اجابة صحيحة: B
السؤال #123
What causes replanning of the project scope?
A. Project document updates
B. Project scope statement changes
C. Variance analysis
D. Change requests
عرض الإجابة
اجابة صحيحة: B
السؤال #124
Which of the following is an output of the Distribute Information process?
A. Project calendar
B. Communications management plan
C. Organizational process assets updates
D. Project document updates
عرض الإجابة
اجابة صحيحة: D
السؤال #125
In the Develop Project Team process, which of the following is identified as a critical factor for a project's success?
A. Team meetings
B. Subcontracting teams
C. Virtual teams
D. Teamwork
عرض الإجابة
اجابة صحيحة: A
السؤال #126
The project scope statement and resource calendars are inputs to which Project Time Management process?
A. Sequence Activities
B. Estimate Activity Resources
C. Develop Schedule
D. Control Schedule
عرض الإجابة
اجابة صحيحة: A
السؤال #127
Which process determines the risks that might affect the project?
A. Perform Qualitative Risk Analysis
B. Identify Risks
C. Plan Risk Management
D. Perform Quantitative Risk Analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #128
Which of the following factors is lowest at the start of the project?
A. Cost of changes
B. Stakeholder influences
C. Risk
D. Uncertainty
عرض الإجابة
اجابة صحيحة: B
السؤال #129
In which domain of project management would a Pareto chart provide useful information?
A. Project Scope Management
B. Project Time Management
C. Project Communications Management
D. Project Quality Management
عرض الإجابة
اجابة صحيحة: C
السؤال #130
Ensuring that both parties meet contractual obligations and that their own legal rights are protected is a function of:
A. Conduct Procurements
B. Close Procurements
C. Administer Procurements,
D. Plan Procurements
عرض الإجابة
اجابة صحيحة: C
السؤال #131
In which process might a project manager use risk reassessment as a tool and technique?
A. Perform Qualitative Risk Analysis
B. Monitor and Control Risk
C. Monitor and Control Project Work
D. Plan Risk Responses
عرض الإجابة
اجابة صحيحة: D
السؤال #132
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract?
A. Cost-reimbursable
B. Time and material
C. Fixed price or lump-sum
D. Cost-plus-fixed-fee
عرض الإجابة
اجابة صحيحة: C
السؤال #133
What risk technique is used to quantify the probability and impact of risks on project objectives?
A. Expert judgment
B. Risk registry
C. Risk response planning
D. Interviewing
عرض الإجابة
اجابة صحيحة: A
السؤال #134
Which of the following terms indicates a deliverable-oriented hierarchical decomposition of the project work?
A. WBS directory
B. Activity list
C. WBS
D. Project schedule
عرض الإجابة
اجابة صحيحة: A
السؤال #135
Which process occurs within the Monitoring and Controlling Process Group?
A. Control Costs
B. Plan Quality
C. Perform Quantitative Risk Analysis
D. Determine Budget
عرض الإجابة
اجابة صحيحة: D
السؤال #136
Which of the following processes audits the quality requirements and the results from quality control measures to ensure appropriate quality standards and operational definitions are used?
A. Perform Quality Control
B. Quality Metrics
C. Perform Quality Assurance
D. Plan Quality
عرض الإجابة
اجابة صحيحة: C
السؤال #137
How is the schedule variance calculated using the earned value technique?
A. EV less AC
B. AC less PV
C. EV less PV
D. AC less EV
عرض الإجابة
اجابة صحيحة: A
السؤال #138
Which Perform Quality Control tool graphically represents how various elements of a system interrelate?
A. Control chart
B. Flowchart
C. Run chart
D. Pareto chart
عرض الإجابة
اجابة صحيحة: C
السؤال #139
Which type of analysis is used as a general management technique within the Plan Procurements process?
A. Risk assessment analysis
B. Make or buy analysis
C. Contract value analysis
D. Cost impact analysis
عرض الإجابة
اجابة صحيحة: C
السؤال #140
Which of the following tools and techniques is used in the Verify Scope process?
A. Inspection
B. Variance analysis
C. Expert judgment
D. Decomposition
عرض الإجابة
اجابة صحيحة: B
السؤال #141
Define Activities and Estimate Activity Resources are processes in which project management Knowledge Area?
A. Project Time Management
B. Project Cost Management
C. Project Scope Management
D. Project Human Resource Management
عرض الإجابة
اجابة صحيحة: B
السؤال #142
Which is a communication method used in the Report Performance process?
A. Expert judgment
B. Project management methodology
C. Stakeholder analysis
D. Status review meetings
عرض الإجابة
اجابة صحيحة: C
السؤال #143
Prioritizing risks for further analysis or action by assessing and combining their probability of occurrence and impact takes place in which process?
A. Monitor and Control Risks
B. Plan Risk Management
C. Perform Qualitative Risk Analysis
D. Perform Quantitative Risk Analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #144
In which process is a project manager identified and given the authority to apply resources to project activities?
A. Acquire Project Team
B. Develop Project Management Plan
C. Manage Project Execution
D. Develop Project Charter
عرض الإجابة
اجابة صحيحة: B
السؤال #145
Which of the following documents allows the project manager to assess risks that may require near term action?
A. Probability and impact matrix
B. Contingency analysis report
C. Risk urgency assessment
D. Rolling wave plan
عرض الإجابة
اجابة صحيحة: B
السؤال #146
Which activity involves ensuring that the composition of a projects configuration items is correct?
A. Configuration Identification
B. Configuration Status Accounting
C. Configuration Verification and Audit
D. Configuration Quality Assurance
عرض الإجابة
اجابة صحيحة: C
السؤال #147
Change requests, project management plan updates, project document updates, and organizational process assets updates are all outputs of which project management process?
A. Plan Risk Responses
B. Manage Stakeholder Expectations
C. Define Scope
D. Report Performance
عرض الإجابة
اجابة صحيحة: C
السؤال #148
Which process involves identifying and documenting the logical relationships between project activities?
A. Develop Schedule
B. Sequence Activities
C. Create WBS
D. Applying leads and lags
عرض الإجابة
اجابة صحيحة: D
السؤال #149
Which of the following is an example of the simplest fixed-price contract?
A. Purchase requisition
B. Purchase order
C. Verbal agreement
D. Request for quote
عرض الإجابة
اجابة صحيحة: C
السؤال #150
Which technique helps to determine the risks that have the most potential impact on a project?
A. Cost risk simulation analysis
B. Expected monetary value analysis
C. Modeling and simulation
D. Sensitivity analysis
عرض الإجابة
اجابة صحيحة: B
السؤال #151
Analogous cost estimating relies on which of the following techniques?
A. Expert judgment
B. Project management software
C. Vendor bid analysis
D. Reserve analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #152
A method to manage stakeholder expectations in the scope statement is to clearly:
A. state the guiding principles of the organization
B. identify alternatives to generate different approaches
C. state what is out of scope
D. outline the results of the Delphi technique
عرض الإجابة
اجابة صحيحة: D
السؤال #153
Which type of management focuses on ensuring that projects and programs are reviewed to prioritize resource allocation?
A. Project
B. Functional
C. Program
D. Portfolio
عرض الإجابة
اجابة صحيحة: C
السؤال #154
One of the tools and techniques of the Manage Project Team process is:
A. organization charts
B. ground rules
C. organizational theory,
D. conflict management
عرض الإجابة
اجابة صحيحة: D
السؤال #155
The process of monitoring the status of the project to update project progress and manage changes to the schedule baseline is:
A. Control Schedule
B. Quality Control
C. Perform Integrated Change Control
D. Develop Schedule
عرض الإجابة
اجابة صحيحة: C
السؤال #156
Changes to formally controlled documentation, plans, etc. to reflect modified or additional ideas or content are known as:
A. updates
B. defect repairs
C. preventive actions
D. corrective actions
عرض الإجابة
اجابة صحيحة: B
السؤال #157
Which provides the basic framework for managing a project?
A. Project life cycle
B. Work breakdown structure (WBS)
C. Enterprise environmental factors
D. Project initiation
عرض الإجابة
اجابة صحيحة: A
السؤال #158
A tool and technique used during the Perform Qualitative Risk Analysis process is:
A. risk data quality assessment
B. variance and trend analysis
C. data gathering and representation techniques
D. risk audits
عرض الإجابة
اجابة صحيحة: A
السؤال #159
In the Estimate Activity Durations process, productivity metrics and published commercial information inputs are part of the:
A. enterprise environmental factors
B. organizational process assets
C. project management plan,
D. project funding requirements
عرض الإجابة
اجابة صحيحة: D
السؤال #160
The milestone list is an input to which process from the Planning Process Group?
A. Define Activities
B. Estimate Activity Durations
C. Estimate Activity Resources
D. Sequence Activities
عرض الإجابة
اجابة صحيحة: C
السؤال #161
Quality metrics are an output of which process?
A. Plan Quality
B. Perform Quality Control
C. Perform Quality Assurance
D. Perform Qualitative Risk Analysis
عرض الإجابة
اجابة صحيحة: B
السؤال #162
The purpose of inspection in Perform Quality Control is to keep errors:
A. in line with a measured degree of conformity
B. out of the hands of the customer
C. in a specified range of acceptable results
D. out of the process
عرض الإجابة
اجابة صحيحة: C
السؤال #163
An input to the Perform Quantitative Risk Analysis process is the:
A. quality management plan
B. project management plan
C. communications management plan
D. schedule management plan
عرض الإجابة
اجابة صحيحة: D
السؤال #164
When large or complex projects are separated into distinct phases or subprojects, all of the Process Groups would normally be:
A. divided among each of the phases or subprojects
B. repeated for each of the phases or subprojects
C. linked to specific phases or subprojects
D. integrated for specific phases or subprojects
عرض الإجابة
اجابة صحيحة: C
السؤال #165
A project has a current cost performance index (CPI) of 1.25. To date, US$10,000 have been spent on performing the project work. What is the earned value of the work completed to date?
A. US$S000
B. US$9500
C. US$10,000
D. US$12,500
عرض الإجابة
اجابة صحيحة: A
السؤال #166
The project manager at an organization has just realized that some of the engineering staff has been allocated to project Y and will not be available to finish task X. The project manager has also discovered that at the current pace, it will not be possible to complete the project on time. Due to cost constraints, hiring more work force is not a viable option. Which tools are at the manager's disposal?
A. Resource leveling and fast tracking
B. Fast tracking and crashing
C. Crashing and applying leads and lags
D. Scheduling tools and applying leads and lags
عرض الإجابة
اجابة صحيحة: C
السؤال #167
Which process should be conducted from the project inception through completion?
A. Monitor and Control Project Work
B. Perform Quality Control
C. Perform Integrated Change Control
D. Monitor and Control Risks
عرض الإجابة
اجابة صحيحة: C
السؤال #168
Which piece of information is part of the WBS Dictionary?
A. Responsible organization
B. Change requests
C. Validated deliverables
D. Organizational process assets
عرض الإجابة
اجابة صحيحة: B
السؤال #169
When calculating the cost of quality (COQ) for a product or service, money spent for cost of conformance would include the areas of:
A. training, testing, and warranty work
B. equipment, rework, and scrap
C. training, document processes, and inspections
D. inspections, rework, and warranty work
عرض الإجابة
اجابة صحيحة: B
السؤال #170
Which of the following is a tool or technique of the Define Activities process?
A. Rolling wave planning
B. Precedence diagramming method (PDM)
C. Alternatives analysis
D. Parametric estimating
عرض الإجابة
اجابة صحيحة: A
السؤال #171
Which of the following is a set of interrelated actions and activities performed to achieve a prespecified product, result, or service?
A. Portfolio
B. Process
C. Project
D. Program
عرض الإجابة
اجابة صحيحة: A
السؤال #172
Which degree of authority does a project manager have on a project in a strong matrix organizational structure?
A. Limited
B. Low to moderate
C. Moderate to high
D. High to almost total
عرض الإجابة
اجابة صحيحة: D
السؤال #173
Documented identification of a flaw in a project component together with a recommendation is termed a:
A. corrective action
B. preventive action
C. non-conformance report,
D. defect repair
عرض الإجابة
اجابة صحيحة: C
السؤال #174
Which of the following is developed from the project scope baseline and defines only that portion of the project scope that is to be included within a related contract?
A. Product scope description
B. Procurement statement of work
C. Project schedule
D. Work breakdown structure (WBS)
عرض الإجابة
اجابة صحيحة: D
السؤال #175
Which of the following strategic considerations often results in project authorization?
A. Customer requests and/or issue resolution
B. Stakeholder expectations and/or strategic opportunity (business need)
C. Technological advancement and/or senior executive request
D. Market demand and/or legal requirements
عرض الإجابة
اجابة صحيحة: C
السؤال #176
In which Process Group are lessons learned documented?
A. Planning
B. Closing
C. Executing
D. Initiating
عرض الإجابة
اجابة صحيحة: C
السؤال #177
Tools and techniques used for Plan Communications include the communication:
A. requirements analysis, communication technology, communication models, and communication methods
B. methods, stakeholder register, communication technology, and communication models
C. requirements, communication technology, communication requirements analysis, and communication methods
D. management plan, communication technology, communication models, and communication requirements analysis
عرض الإجابة
اجابة صحيحة: B
السؤال #178
In Project Cost Management, which input is exclusive to the Determine Budget process?
A. Scope baseline
B. Organizational process assets
C. Project schedule
D. Resource calendars
عرض الإجابة
اجابة صحيحة: B
السؤال #179
Which of the following is a conflict resolution technique that emphasizes areas of agreement rather than areas of difference?
A. Compromising
B. Collaborating
C. Smoothing
D. Problem Solving
عرض الإجابة
اجابة صحيحة: B
السؤال #180
The precedence diagramming method (PDM) is also known as:
A. Arrow Diagram
B. Critical Path Methodology (CPM)
C. Activity-On-Node (AON)
D. schedule network diagram
عرض الإجابة
اجابة صحيحة: D
السؤال #181
Change request status updates are an output of which process?
A. Perform Integrated Change Control
B. Direct and Manage Project Execution
C. Close Project or Phase
D. Monitor and Control Project Work
عرض الإجابة
اجابة صحيحة: C
السؤال #182
As the project progresses, which of the following is routinely collected from the project activities?
A. Communication management activities
B. Change requests
C. Configuration verification and audit
D. Work performance information
عرض الإجابة
اجابة صحيحة: A
السؤال #183
Which Process Group contains those processes performed to define a new project?
A. Initiating
B. Planning
C. Executing
D. Closing
عرض الإجابة
اجابة صحيحة: C
السؤال #184
The risk management team of a software project has decided that due to the lack of adequate talent in the company, development of a specific part of the system is under high risk, so the team has decided to outsource it. This is an example of which risk response?
A. Transfer
B. Share
C. Avoid
D. Accept
عرض الإجابة
اجابة صحيحة: D
السؤال #185
Which type of agreement is legal, contractual, and between two or more entities to form a partnership, joint venture, or some other arrangement as defined by the parties?
A. Teaming
B. Collective bargaining
C. Sharing
D. Working
عرض الإجابة
اجابة صحيحة: D
السؤال #186
The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline is:
A. Determine Budget
B. Baseline Budget
C. Control Costs
D. Estimate Costs
عرض الإجابة
اجابة صحيحة: A
السؤال #187
To please the customer, a project team member delivers a requirement which is uncontrolled. This is not part of the plan. This describes:
A. scope creep
B. a change request
C. work performance information
D. deliverables
عرض الإجابة
اجابة صحيحة: A
السؤال #188
The definition of operations is a/an:
A. organizational function performing the temporary execution of activities that produce the same product or provide repetitive service
B. temporary endeavor undertaken to create a unique product, service, or result
C. organization that provides oversight for an administrative area
D. organizational function performing the ongoing execution of activities that produce the same product or provide repetitive service
عرض الإجابة
اجابة صحيحة: A
السؤال #189
How many Project Management Process Groups are there?
A. 3
B. 4
C. 5
D. 6
عرض الإجابة
اجابة صحيحة: A
السؤال #190
Which type of estimating is used to improve the accuracy of an activity's duration?
A. Analogous
B. Parametric
C. Three-point
D. What-if scenario analysis
عرض الإجابة
اجابة صحيحة: A
السؤال #191
The Project Management Process Group in which performance is observed and measured regularly from project initiation through completion is:
A. Executing
B. Initiating,
C. Monitoring and Controlling
D. Planning
عرض الإجابة
اجابة صحيحة: D
السؤال #192
Which of the following are outputs of Develop Project Team?
A. Human resources plan changes and project staff assignment updates
B. Project management plan updates and enterprise environmental factor updates
C. Resource calendars and project management plan updates
D. Team performance assessments and enterprise environmental factor updates
عرض الإجابة
اجابة صحيحة: A
السؤال #193
Which tool or technique is used in Manage Stakeholder Expectations?
A. Stakeholder management strategy
B. Communication methods
C. Issue log
D. Change requests
عرض الإجابة
اجابة صحيحة: B
السؤال #194
Which of the following is a tool and technique used in the Develop Schedule process?
A. Three-point estimates
B. Resource leveling
C. Precedence diagramming method
D. Bottom-up estimating
عرض الإجابة
اجابة صحيحة: D
السؤال #195
The output that defines an approach to increase the support and minimize negative impacts of stakeholders is the:
A. stakeholder management strategy
B. communications management plan,
C. stakeholder register,
D. performance report
عرض الإجابة
اجابة صحيحة: B
السؤال #196
Which of the following project documents is an input to the Control Scope process?
A. Vendor risk assessment diagram
B. Risk register
C. Requirements traceability matrix
D. Area of responsibility summary
عرض الإجابة
اجابة صحيحة: D
السؤال #197
The progressive detailing of the project management plan is called:
A. expert judgment
B. rolling wave planning
C. work performance information
D. specification
عرض الإجابة
اجابة صحيحة: A
السؤال #198
What is the responsibility of the project manager and the functional manager respectively?
A. Oversight for an administrative area; a facet of the core business
B. Achieving the project objectives; providing management oversight for an administrative area
C. A facet of the core business; achieving the project objectives
D. Both are responsible for achieving the project objectives
عرض الإجابة
اجابة صحيحة: A
السؤال #199
Which is used to solicit proposals from prospective sellers?
A. Procurement statement of work
B. Resource calendars
C. Procurement document
D. Independent estimates
عرض الإجابة
اجابة صحيحة: C
السؤال #200
In which Project Management Process Group is the project charter developed?
A. Monitoring and Controlling
B. Executing
C. Initiating
D. Planning
عرض الإجابة
اجابة صحيحة: A
السؤال #201
Which can be used to determine whether a process is stable or has predictable performance?
A. Matrix diagram
B. Histogram
C. Control chart
D. Flowchart
عرض الإجابة
اجابة صحيحة: C
السؤال #202
When sequencing activities, what does the common acronym FF stand for?
A. Fixed Fee
B. Free Float
C. Fixed Finish
D. Finish-to-Finish
عرض الإجابة
اجابة صحيحة: A
السؤال #203
Monte Carlo is which type of risk analysis technique?
A. Probability
B. Quantitative
C. Qualitative
D. Sensitivity
عرض الإجابة
اجابة صحيحة: B
السؤال #204
When addressing roles and responsibilities,which item ensures that the staff has the skills required to complete project activities?
A. Authority
B. Role
C. Competency
D. Responsibility
عرض الإجابة
اجابة صحيحة: C
السؤال #205
Which of the following reduces the probability of potential consequences of project risk events?
A. Preventive action
B. Risk management
C. Corrective action
D. Defect repair
عرض الإجابة
اجابة صحيحة: B
السؤال #206
The project manager needs to review the templates in use. The templates are part of the:
A. Enterprise environmental factors
B. Historical information,
C. Organizational process assets
D. Corporate knowledge base
عرض الإجابة
اجابة صحيحة: D
السؤال #207
Which of the following Project Communication Management processes uses performance reports as an input?
A. Manage Stakeholder Expectations
B. Report Performance
C. Distribute Information
D. Plan Communications
عرض الإجابة
اجابة صحيحة: B
السؤال #208
Which cost estimate technique includes contingencies to account for cost uncertainty?
A. Vendor bid analysis
B. Three-point estimates
C. Parametric estimating
D. Reserve analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #209
Which of the following is an output of the Perform Integrated Change Control process?
A. Project document updates
B. Organizational process assets updates
C. Change requests
D. Deliverables
عرض الإجابة
اجابة صحيحة: B
السؤال #210
Lessons learned documentation is gathered during which of the following Project Management Process Groups?
A. Planning
B. Executing
C. Closing
D. Initiating
عرض الإجابة
اجابة صحيحة: A
السؤال #211
The key benefit of the Monitoring and Controlling Process Group is the ability to:
A. establish and manage project communication channels, both external and internal to the project team
B. influence the stakeholders that want to circumvent integrated change control so that their changes are implemented
C. monitor the ongoing project team against the team performance assessments and the project performance baseline
D. observe and measure project performance regularly and consistently to identify variances from the project management plan
عرض الإجابة
اجابة صحيحة: D
السؤال #212
Which written document helps monitor who is responsible for resolving specific problems and concerns by a target date?
A. Project Plan
B. Responsibility Matrix
C. Issue Log
D. Scope Document
عرض الإجابة
اجابة صحيحة: C
السؤال #213
Who provides the inputs for the original estimates of activity durations for tasks on the project plan?
A. Project sponsor
B. Project manager
C. Person responsible for project scheduling
D. Person who is most familiar with the task
عرض الإجابة
اجابة صحيحة: D
السؤال #214
Which of the following is the primary output of the Identify Risks process?
A. Risk management plan
B. Risk register
C. Change requests
D. Risk response plan
عرض الإجابة
اجابة صحيحة: C
السؤال #215
Which type of elaboration allows a project management team to manage at a greater level of detail as the project evolves?
A. Cyclic
B. Progressive
C. Repetitive
D. Iterative
عرض الإجابة
اجابة صحيحة: A
السؤال #216
Which of the following helps to ensure that each requirement adds business value by linking it to the business and project objectives?
A. Requirements traceability matrix
B. Work breakdown structure (WBS) dictionary
C. Requirements management plan
D. Requirements documentation
عرض الإجابة
اجابة صحيحة: D
السؤال #217
Which category of contracts are sellers legally obligated to complete, with possible financial damages if the project objectives are not met?
A. Cost-reimbursable contracts
B. Time and Material contracts (T&M)
C. Fixed-price contracts
D. Cost Plus Fixed Fee Contracts (CPFF)
عرض الإجابة
اجابة صحيحة: A
السؤال #218
Types of internal failure costs include:
A. inspections
B. equipment and training
C. lost business
D. reworking and scrapping
عرض الإجابة
اجابة صحيحة: A
السؤال #219
In a weak matrix, the project managers role is:
A. part-time
B. full-time
C. occasional
D. unlimited
عرض الإجابة
اجابة صحيحة: A
السؤال #220
Which of the following is an example of schedule compression?
A. Activity sequencing
B. Resource leveling
C. Lead and lag adjusting
D. Crashing
عرض الإجابة
اجابة صحيحة: A
السؤال #221
Which of the following types of a dependency determination is used to define the sequence of activities?
A. Legal
B. Discretionary
C. Internal
D. Resource
عرض الإجابة
اجابة صحيحة: A
السؤال #222
Control charts, flowcharting, histograms, Pareto charts, and scatter diagrams are tools and techniques of which process?
A. Perform Quality Control
B. Perform Quality Assurance
C. Plan Quality
D. Report Performance
عرض الإجابة
اجابة صحيحة: D
السؤال #223
Co-location is a tool and technique of:
A. Develop Human Resource Plan
B. Manage Project Team
C. Develop Project Team
D. Acquire Project Team
عرض الإجابة
اجابة صحيحة: C
السؤال #224
During which process would stakeholders provide formal acceptance of the completed project scope?
A. Perform Quality Control
B. Verify Scope
C. Control Scope
D. Develop Schedule
عرض الإجابة
اجابة صحيحة: C
السؤال #225
The PV is $1000, EV is $2000, and AC is $1500. What is CPI?
A. 1
B. 2
C. 0
D. 0
عرض الإجابة
اجابة صحيحة: C
السؤال #226
A given schedule activity is most likely to last four weeks. In a best-case scenario, the schedule activity is estimated to last two weeks. In a worst-case scenario, the schedule activity is estimated to last 12 weeks. Given these three estimates, what is the expected duration of the activity?
A. Three weeks
B. Four weeks
C. Five weeks
D. Six weeks
عرض الإجابة
اجابة صحيحة: D
السؤال #227
What is the primary benefit of meeting quality requirements?
A. Quality metrics
B. Less rework
C. Quality control measurements
D. Benchmarking
عرض الإجابة
اجابة صحيحة: B
السؤال #228
What is a tool to improve team performance?
A. Staffing plan
B. External feedback
C. Performance reports
D. Co-location
عرض الإجابة
اجابة صحيحة: B
السؤال #229
Which tool within the Perform Quality Control process identifies whether or not a process has a predictable performance?
A. Cause and effect diagram
B. Control charts
C. Pareto chart
D. Histogram
عرض الإجابة
اجابة صحيحة: A
السؤال #230
Based on the following metrics: EV= $20,000, AC= $22,000, and PV= $28,000, what is the project CV?
A. -8000
B. -2000
C. 2000
D. 8000
عرض الإجابة
اجابة صحيحة: C
السؤال #231
Which type of risk diagram is useful for showing time ordering of events?
A. Ishikawa
B. Milestone
C. Influence
D. Decision tree
عرض الإجابة
اجابة صحيحة: B
السؤال #232
In a construction project schedule, what is the logical relationship between the delivery of the concrete materials and the pouring of concrete?
A. Start-to-start (SS)
B. Start-to-finish (SF)
C. Rnish-to-finish (FF)
D. Finish-to-start (FS)
عرض الإجابة
اجابة صحيحة: B
السؤال #233
A required input for Create WBS is a project:
A. quality plan
B. schedule network
C. management document update
D. scope statement
عرض الإجابة
اجابة صحيحة: C
السؤال #234
Which of the following statements is true regarding project and product lifecycles?
A. A single product lifecycle may consist of multiple project lifecycles
B. A product lifecycle is always shorter than the project lifecycle
C. A single product lifecycle can only have one project lifecycle
D. A single project lifecycle may consist of multiple product lifecycles
عرض الإجابة
اجابة صحيحة: C
السؤال #235
Which tool or technique is used in Close Procurements?
A. Contract plan
B. Procurement plan
C. Closure process
D. Procurement audits
عرض الإجابة
اجابة صحيحة: C
السؤال #236
Which of the following is an output of Direct and Manage Project Execution?
A. Project management plan
B. Change request status updates
C. Organizational process assets updates
D. Work performance information
عرض الإجابة
اجابة صحيحة: D
السؤال #237
Which of the following is an input to Develop Human Resource Plan?
A. Team performance assessment
B. Roles and responsibilities
C. Staffing management plan
D. Enterprise environmental factors
عرض الإجابة
اجابة صحيحة: C
السؤال #238
Which of the following outputs from the Control Schedule process aids in the communication of schedule variance (SV), schedule performance index (SPI), or any performance status to stakeholders?
A. Performance organizations
B. Schedule baselines
C. Work performance measurements
D. Change requests
عرض الإجابة
اجابة صحيحة: B
السؤال #239
Testing falls into which of the following categories of cost of quality?
A. Internal failure costs
B. Prevention costs
C. Appraisal costs
D. External failure costs
عرض الإجابة
اجابة صحيحة: C
السؤال #240
Another name for an Ishikawa diagram is:
A. cause and effect diagram
B. control chart
C. flowchart
D. histogram
عرض الإجابة
اجابة صحيحة: A
السؤال #241
Which of the following strategies is used to deal with risks that may have a negative impact on project objectives?
A. Exploit
B. Share
C. Enhance
D. Transfer
عرض الإجابة
اجابة صحيحة: C
السؤال #242
Which of the following correctly explains the term "progressive elaboration'?
A. Changing project specifications continuously
B. Elaborate tracking of the project progress
C. Elaborate tracking of the project specifications with a change control system
D. Project specifications becoming more explicit and detailed as the project progresses
عرض الإجابة
اجابة صحيحة: C
السؤال #243
A project has an EV of 100 workdays, an AC of 120 workdays, and a PV of 80 workdays. What should be the concern?
A. There is a cost underrun
B. There is a cost overrun
C. The project may not meet the deadline
D. The project is 20 days behind schedule
عرض الإجابة
اجابة صحيحة: D
السؤال #244
Which characteristic do projects and operational work share in common?
A. Performed by systems
B. Constrained by limited resources
C. Repetitiveness
D. Uniqueness
عرض الإجابة
اجابة صحيحة: A
السؤال #245
What does a CPI value greater than 1.0 indicate?
A. Cost right at the estimated value
B. Cost under the estimated value
C. Cost right at the actual value
D. Cost over the estimated value
عرض الإجابة
اجابة صحيحة: D
السؤال #246
Which of the following is an output from Control Scope?
A. Change requests
B. Variance analysis
C. Accepted deliverables
D. Requirements documentation
عرض الإجابة
اجابة صحيحة: C
السؤال #247
Managing procurement relationships and monitoring contract performance are part of which process?
A. Conduct Procurements
B. Plan Procurements
C. Administer Procurements
D. Close Procurements
عرض الإجابة
اجابة صحيحة: D
السؤال #248
Which technique is commonly used for the Perform Quantitative Risk Analysis process?
A. Brainstorming
B. Strategies for opportunities
C. Decision tree analysis
D. Risk data quality assessment
عرض الإجابة
اجابة صحيحة: C
السؤال #249
In which type of organizational structure are staff members grouped by specialty?
A. Functional
B. Projectized
C. Matrix
D. Balanced
عرض الإجابة
اجابة صحيحة: D
السؤال #250
Which of the following is an input to the Perform Qualitative Risk Analysis process?
A. Risk register
B. Risk data quality assessment
C. Risk categorization
D. Risk urgency
عرض الإجابة
اجابة صحيحة: B
السؤال #251
Which of the following Process Groups covers all nine Project Management Knowledge Areas?
A. Executing
B. Monitoring and Controlling
C. Planning
D. Initiating
عرض الإجابة
اجابة صحيحة: B
السؤال #252
The process of identifying the stakeholders' information needs is completed during:
A. Plan Communications
B. Manage Stakeholder Expectations
C. Stakeholder Analysis
D. Identify Stakeholders
عرض الإجابة
اجابة صحيحة: A
السؤال #253
What is the most accurate rough order of magnitude (ROM)?
A. In the Initiation phase, the estimate is in the range of +/- 50%
B. In the Planning phase, the estimate is in the range of +/- 50%
C. In the Monitoring and Controlling phase, the estimate is in the range of +/- 15%
D. In the Closing phase, the estimate is in the range of +/- 15%
عرض الإجابة
اجابة صحيحة: C
السؤال #254
Project contracts generally fall into which of the following three broad categories?
A. Fixed-price, cost reimbursable, time and materials
B. Make-or-buy, margin analysis, fixed-price
C. Time and materials, fixed-price, margin analysis
D. Make-or-buy, lump-sum, cost-plus-incentive
عرض الإجابة
اجابة صحيحة: D
السؤال #255
Which of the following events would result in a baseline update?
A. A project is behind schedule and the project manager wants the baseline to reflect estimated actual completion
B. A customer has approved a change request broadening the project scope and increasing the budget
C. One of the risks identified in the risk management plan occurs, resulting in a schedule delay
D. One of the key project team resources has left the team and no replacement is available
عرض الإجابة
اجابة صحيحة: A
السؤال #256
Which of the following schedule network analysis techniques is applied when a critical path method calculation has been completed and resources availability is critical?
A. Applying calendars
B. Resource leveling
C. Resource planning
D. Resource conflict management
عرض الإجابة
اجابة صحيحة: D
السؤال #257
"Tailoring" is defined as the:
A. effort of addressing each process to determine which are appropriate and their appropriate degree of rigor
B. act of creating a project team with the specialized skills required to produce a required product or service
C. action taken to bring a defective or nonconforming component into compliance with requirements or specifications
D. adjustment of the respective influences of time, cost, and quality in order to most efficiently achieve scope
عرض الإجابة
اجابة صحيحة: B
السؤال #258
Which is an input to the Verify Scope process?
A. Performance report
B. Work breakdown structure (WBS)
C. Requested changes
D. Project management plan
عرض الإجابة
اجابة صحيحة: C
السؤال #259
Which is an output from Distribute Information?
A. Earned value analysis
B. Trend analysis
C. Project records
D. Performance reviews
عرض الإجابة
اجابة صحيحة: C
السؤال #260
Fast tracking is a schedule compression technique used to shorten the project schedule without changing project scope. Which of the following can result from fast tracking?
A. The risk of achieving the shortened project time is increased
B. The critical path will have positive total float
C. Contingency reserves are released for redeployment by the project manager
D. Duration buffers are added to maintain a focus on planned activity durations
عرض الإجابة
اجابة صحيحة: B
السؤال #261
Requirements documentation, requirements management plan, and requirements traceability matrix are all outputs of which process?
A. Control Scope
B. Collect Requirements
C. Create WBS
D. Define Scope
عرض الإجابة
اجابة صحيحة: A
السؤال #262
Which of the following is a strategy to deal with positive risks or opportunities?
A. Mitigate
B. Transfer
C. Exploit
D. Avoid
عرض الإجابة
اجابة صحيحة: C
السؤال #263
What are the identified risks for doing excessive decomposition in a WBS?
A. Insufficient project funding and disqualification of sellers
B. Insufficient project funding and ineffective use of resources
C. Disqualification of sellers and non-productive management efforts
D. Non-productive management effort and inefficient use of resources
عرض الإجابة
اجابة صحيحة: B
السؤال #264
The initial development of a Project Scope Management plan uses which technique?
A. Alternatives identification
B. Scope decomposition
C. Expert judgment
D. Product analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #265
Which of the following is a project constraint?
A. Twenty-five percent staff turnover is expected
B. The technology to be used is cutting-edge
C. Project leadership may change due to volatile political environment
D. The product is needed in 250 days
عرض الإجابة
اجابة صحيحة: B
السؤال #266
An input to the Estimate Activity Resources process is:
A. Activity resource requirements
B. Published estimating data
C. Resource calendars
D. Resource breakdown structure (RBS)
عرض الإجابة
اجابة صحيحة: B
السؤال #267
The project budget is set at $150,000. The project duration is planned to be one year. At the completion of Week 16 of the project, the following information is collected: Actual cost = $50,000, Plan cost = $45,000, Earned value = $40,000. What is the cost performance index?
A. 0
B. 0
C. 1
D. 1
عرض الإجابة
اجابة صحيحة: C
السؤال #268
Which technique is utilized in the Control Schedule process?
A. Performance measure
B. Baseline schedule
C. Schedule network analysis
D. Variance analysis
عرض الإجابة
اجابة صحيحة: D
السؤال #269
What happens to a stakeholder's project influence over time?
A. Increases
B. Decreases
C. Stays the same
D. Has no bearing
عرض الإجابة
اجابة صحيحة: D
السؤال #270
Which is one of the determining factors used to calculate CPI?
A. EV
B. SPI
C. PV
D. ETC
عرض الإجابة
اجابة صحيحة: A
السؤال #271
Which quality control technique illustrates the 80/20 principle?
A. Ishikawa diagram
B. Control chart
C. Run chart
D. Pareto chart
عرض الإجابة
اجابة صحيحة: D
السؤال #272
At the end of the project, what will be the value of SV?
A. Positive
B. Zero
C. Negative
D. Greater than one
عرض الإجابة
اجابة صحيحة: D
السؤال #273
The process of identifying specific actions to be performed to produce project deliverables is:
A. Define Activities
B. Create WBS
C. Define Scope
D. Develop Schedule
عرض الإجابة
اجابة صحيحة: D
السؤال #274
What is project management?
A. A logical grouping of project management inputs, outputs, tools, and techniques
B. Applying knowledge, skills, tools, and techniques to project activities to meet the project requirements
C. Launching a process that can result in the authorization of a new project
D. A formal, approved document that defines how the project is executed, monitored, and controlled
عرض الإجابة
اجابة صحيحة: C
السؤال #275
Resource calendars are included in the:
A. staffing management plan
B. work breakdown structure (WBS)
C. project communications plan
D. project charter
عرض الإجابة
اجابة صحيحة: C
السؤال #276
Expected monetary value (EMV) is computed by which equation?
A. Value of each possible outcome multiplied by probability of occurrence
B. Value of each possible outcome multiplied by probability of non-occurrence
C. Multiplying the value of each possible outcome by the probability of occurrence and adding the products together
D. Multiplying the value of each possible outcome by the probability of non-occurrence and adding the products together
عرض الإجابة
اجابة صحيحة: A
السؤال #277
An input to the Collect Requirements process is the:
A. stakeholder register
B. project management plan
C. project scope statement
D. requirements management plan
عرض الإجابة
اجابة صحيحة: D
السؤال #278
Projects are separated into phases or subprojects; these phases include:
A. feasibility study, concept development, design, and prototype
B. initiate, plan, execute, and monitor
C. Develop Charter, Define Activities, Manage Stakeholder Expectations, and Report Performance
D. Identify Stakeholders, develop concept, build, and test
عرض الإجابة
اجابة صحيحة: D
السؤال #279
In which type of contract are the performance targets established at the onset and the final contract price determined after completion of all work based on the sellers performance?
A. Firm-Fixed-Price (FFP)
B. Fixed Price with Economic Price Adjustments (FP-EPA)
C. Fixed-Price-Incentive-Fee (FPIF)
D. Cost Plus Fixed Fee (CPFF)
عرض الإجابة
اجابة صحيحة: D
السؤال #280
Which of the following is an input to the Develop Project Charter process?
A. Work performance information
B. Project management plan
C. Business case
D. Change requests
عرض الإجابة
اجابة صحيحة: B
السؤال #281
The diagram below is an example of a:
A. Risk breakdown structure (RBS)
B. Project team
C. SWOT Analysis
D. Work breakdown structure (WBS)
عرض الإجابة
اجابة صحيحة: B
السؤال #282
Who is responsible for initiating a project?
A. Project sponsor
B. Project manager
C. Program manager
D. Project management office (PMO)
عرض الإجابة
اجابة صحيحة: B
السؤال #283
Which type of diagram includes groups of information and shows relationships between factors, causes, and objectives?
A. Affinity
B. Scatter
C. Fishbone
D. Matrix
عرض الإجابة
اجابة صحيحة: A
السؤال #284
Activity cost estimates are quantitative assessments of the probable costs required to:
A. Create WBS
B. complete project work
C. calculate costs
D. Develop Project Management Plan
عرض الإجابة
اجابة صحيحة: C
السؤال #285
The item that provides more detailed descriptions of the components in the work breakdown structure (WB5) is called a WBS:
A. dictionary
B. chart
C. report
D. register
عرض الإجابة
اجابة صحيحة: C
السؤال #286
How should a stakeholder who is classified as high power and low interest be grouped in a power/interest grid during stakeholder analysis?
A. Keep satisfied
B. Keep informed
C. Manage closely
D. Monitor
عرض الإجابة
اجابة صحيحة: A
السؤال #287
The project has a current cost performance index of 0.80. Assuming this performance wi continue, the new estimate at completion is $1000. What was the original budget at completion for the project?
A. $800
B. $1000
C. $1250
D. $1800
عرض الإجابة
اجابة صحيحة: A
السؤال #288
Who determines which dependencies are mandatory during the Sequence Activities process?
A. Project manager
B. External stakeholders
C. Internal stakeholders
D. Project team
عرض الإجابة
اجابة صحيحة: C
السؤال #289
Risk exists the moment that a project is:
A. planned
B. conceived
C. chartered
D. executed
عرض الإجابة
اجابة صحيحة: A
السؤال #290
Which type of contract is a hybrid of both a cost-reimbursable and a fixed-price contract?
A. Cost Plus Award Fee Contract (CPAF)
B. Firm-Fixed -Price Contract (FFP)
C. Time and Material Contract (T&M)
D. Cost Plus Incentive Fee Contract (CPIF)
عرض الإجابة
اجابة صحيحة: A
السؤال #291
Which characteristics do effective project managers possess?
A. Project management knowledge, performance skills, and personal effectiveness
B. Preparedness, project management knowledge, and personality characteristics
C. General management, preparedness, and project management knowledge
D. Assertiveness, collaboration, and performance skills
عرض الإجابة
اجابة صحيحة: A
السؤال #292
In the basic communication model, which term refers to the method that is used to convey the message?
A. Decode
B. Encode
C. Medium
D. Noise
عرض الإجابة
اجابة صحيحة: B
السؤال #293
During project selection, which factor is most important?
A. Types of constraints
B. Internal business needs
C. Budget
D. Schedule
عرض الإجابة
اجابة صحيحة: B
السؤال #294
The staffing management plan is part of the:
A. organizational process assets
B. resource calendar
C. human resource plan
D. Develop Project Team process
عرض الإجابة
اجابة صحيحة: A
السؤال #295
Which is an output of the Collect Requirements process?
A. Requirements traceability matrix
B. Project scope statement
C. WBS dictionary
D. Work performance measurements
عرض الإجابة
اجابة صحيحة: D
السؤال #296
Which activity may occur at project or phase closure?
A. Acceptance of deliverables
B. Change requests
C. Project management plan updates
D. Benchmarking
عرض الإجابة
اجابة صحيحة: C
السؤال #297
Which of the following is an input to Direct and Manage Project Execution?
A. Performance reports
B. Project charter
C. Outputs from planning processes
D. Enterprise environmental factors
عرض الإجابة
اجابة صحيحة: A
السؤال #298
Using the three-point estimating technique, if the most likely duration is four months, the optimistic duration is two months, and the pessimistic duration is one year, how many months is the expected activity duration?
A. Two
B. Four
C. Five
D. Twelve
عرض الإجابة
اجابة صحيحة: B

عرض الإجابات بعد التقديم

يرجى إرسال البريد الإلكتروني الخاص بك والواتس اب للحصول على إجابات الأسئلة.

ملحوظة: يرجى التأكد من صلاحية معرف البريد الإلكتروني وWhatsApp حتى تتمكن من الحصول على نتائج الاختبار الصحيحة.

بريد إلكتروني:
رقم الواتس اب/الهاتف: